April 6, 1972 PCB - LOSS CONTROL PROGRAM STATUS
Mr. A. E. Lelsy
COMPANY CONFIDENTIAL
" G. L. Bratsch W. C. Engman P. E. Heisler D. B. Hosmer - G.O. G. A. Hlppe W. B. Papageorge - G.O J. R. Savage - G.O.
It is believed that a pending paper from the Office of Science and Technology, an element of the executive branch
of the Federal government, will recommend that polychlori nated biphenyl (PCB) levels in effluent streams*be virtually reduced to zero. The paper will recommend that no PCB's will be detected in the plant effluent stream and PCB levels from the department will be a. maximum of 0.01 parts per billion (ppb).
Comments related to the above possibility and how it relates to our current program for PCB control ere summarized below.
I.Methodology - Chromatographic interference present when analyzing any plant stream will limit our detection of PCB's to about 1 ppb.
II. Current Levels - Village and plant losses measured at
the Waste Treatment Plant Influent during past four months have averaged 191 ppb. (Equivalent to 2'4 jf/io-y average.) Daily range of 27 to 54? ppb. Dosses from the Waste Treatment Plant Effluent to the river have averaged 86 ppb. (Equivalent to 9 #/day average.) Dally range of 12 to 282 ppb.
III.
Current Technology - Normal carbon treatment arid filtra tion will permit removal of PCB's to about 5 ppb. No research is in progress to permit removal of PCB below the carbon adsorption-filtration capability. Carbon treatment at this time is not planned.
IV. Current Program - An existing program has been developed that should permit control of PCB losses from the depart
ment, the incinerator and the Rip Trade wash.area to an average daily loss of about 1 #/day in the fourth quarter
of 1972. The program is based primarily on scrubbing all the HC1 off-gas from the Aroclor department, and controlllngcontaining-recovering physical losses of PCB's in the operating areas.
HONS 098745
Mr. A. E. Leisy PCB - LOSS CONTROL PROORAM STATUS
Page 2 WOK
IV. Current Program (continued)
It is conceivable and highly probable that residual PCB in WGK soils and sewers will continue to be leached for months to come. This amount could approach a daily average of 5 #/day.
V. Costs - The program to reduce PCB's from the current level to about 1 #/day will cost about $200,000 in project costs and technical effort.
At this time the technology is not available and the coats would probably be prohibitive to meet the standards that may be recom mended by the Office of Science and Technology.
All plant efforts are directed toward reducing losses from known sources to 1 #/day.
See details attached.
Edward E. Stewart Technical Services Department
/tm att
MGNS 098796
DETAILS
1.
I. METHODOLOGY
At present we have no analytical method capable of measuring PCB's In plant effluent streams at a level of 0.01 ppb. Chromatographic Interference present when analyzing any plant streams will limit our detection of PCB's to about 1 ppb. We report "no detectable PCB's" when none are detected at the 1 ppb level. Our method is accurate to about + 30#.
The instrument itself is capable of measuring PCB's at the 0.01 ppb level but this would only be true if the sample were comparable to distilled water and the sample prepared at some point removed from the WGK environment. Background levels of PCB's in the WGK laboratory can distort results by as high as
5 ppb.
II. CURRENT LEVELS
Average or ranges of PCB levels in various streams are tabulated
below.
A. Department 246 zone Effluent stream
Discontinued sampling at this point pfending installation of facilities to permit more reliable and representative sampling of stream. Past data ranged from 70 to>5000 ppb. Equivalent to 0.2 to 15 w PCB/day.
B. Waste Treatment Plant Influent. (Reflects plant losses and input
from Monsanto Village and neighbor industries)
Monthly daily average value during
past four months was 191 ppb with a range of 27 to 543 ppb. Equiva lent to 24 #/day average.
C. Waste Treatment Plant Effluent (plow to river after removing scum and settleable solids.)
Monthly daily average value during past four months was 86 ppb with a range of 12 to 282 ppb. (Equiva lent to 9 #/day average.)
D. Miscellaneous streams analyzed during past year.
1. River Raney Well Water
4-33 ppb
_
2. Ground Water
adjacent to Dept. 246
83 - 290 ppb
MQNS 098717
2.
II. CURRENT LEVELS (continued)
D. 3. Streams from
6-56 ppb
neighboring Indus
tries (Midwest Rubber,
American Zinc, Cerro,
Mobil, Cooper.)
4. Tank Car Wash Water from Rip Track
6,000 - 150,000 ppb
5. Plant Cooling Tower Water
No detectable PCB's
6. Plant City Water
No detectable PCB's
III. CURRENT TECHNOLOGY - Removal from aqueous streams
A. Filtration - Can remove about 80-90# of the PCB that
are initially present. Have been about 3 ppb
after filtration of material at 40 ppb level
Initially.
,
B. Carbon Treatment - Anniston data indicate PCB reduction to 20 ppb by carbon adsorption of PCB and reduction to 5 ppb when filtration follows carbon treatment.
. Muriatic acid after carbon treatment has residual PCB content about 3.5 ppb.
Carbon treatment and filtration have permitted reduction in PCB content of tank car washes from about 50,000 ppb to 7 ppb.
C. Waste Treatment Pilot Plant
Pilot data indicate reduction as follows. Average of two runs.
Influent Lime treated Sand filtered Carbon treated
77 ppb PCB's 27 ppb 22 ppb
7 ppb
At this time there is no research in progress to permit removal
of PCB from aqueous streams to values below the carbon remo/a] capability of 5 ppb. Carbon treatment of all streams are not contemplated at this time.
MUNS 098748
1-
IV. CURRENT PROGRAM
During the past four months PCB monthly average daily losses as measured at the Waste Treatment Plant in #/PCB/day are as follows:
Waste Treatment Waste Treatment
Influent
Effluent
December, 1971
12 lbs/day
5 lbs/day
January, 1972
13
11
February
47 9
March
24 8
is believed the Waste Treatment Influent represents losses from the plant. In turn it is believed the major source of plant losses is the Aroclor department. Calculations and recent plant field data would indicate the major source of PCB to the sewer from the Aroclor department to be organics present in the HC1 off-gas. This premise is the basis for the control program that has been developed by the PCB Task Force Committee that will permit control of PCB losses from the department, the incinerator and the Rip Track at an average daily loss of about
1 #/day in the fourth quarter of 1972.
The program for PCB loss control that has been developed by the PCB Task Force and is currently being implemented can be
summarized as follows:
A, Department operational control - containment - and recovery
of PCB's to-ln-from department effluent streams. Currently in effect and consists primarily of:
1. Off-gas temperature control and Brink's mist eliminator operational control.
2. Settling basin operational control
2. Depts. 246-217 production coordination
4. Drip pan-bucket control of minor leaks
5. Dry clean-up procedure in place of profuse jiater cleaning of ares.
B. HC1 off-gas and air blow scrubbing projects. Calculations and field sampling would indicate losses of 14 to 31 # PCB's/day can be present in the off-gas leaving the department.
MONS 098 749
IV. CURRENT PROGRAM
4.
B. (continued)
It is believed we can reduce this quantity by 95# by additional scrubbing of the off-gas. Laboratory work is in progress to verify, and then a project will be prepared. Estimated costs of $30,000 - $50,000.
C. Modifications to existing tank car wash procedures at
Repair Track to permit limiting PCB in wash water to about
400 ppb. This is equivalent to about 0.02 #/PCB/day when
tank cars are washed.
'
D. Complete current project work
1, Settling basin modification to permit improved separa tion of PCB from department Effluent discharge.
2. Major repair to main sewer from department to eliminate cross flow of ground water and permit improved sampling and flow measurements of department Effluent discharge. A $50,000 project.
The current program should permit us to reduce PCB loss to the
sewer to about 1 #/day from those areas where PCB contamination is a possibility. Namely the Aroclor production department,
the Incinerator and the Repair Track. 1 #/day would be equiva lent to 13 ppb from yGK plant assuming 6400 GPM total effluent flow from plant. Any reduction in water flow from the plant to reduce costs of Secondary Waste Treatment would result in Increase in PCB content above 13 ppb.
It is also conceivable and highly probable that residual PCB In
WOK soils will continue to be leached for months to come. It is
estimated this amount could approach the equivalent of 5 #/day
average (65 ppb at 6400 gpm flow). This amount would show up in
WOK Effluent streams.
.
V. COSTS
A COST
A. Department said off-gas system could be contributing about
. 30 # PCB/day.
B. Program to get to about 1 #/day cw 13 ppb from plant exclusive of
residue PCB's in the total WGK ground system.
$100,000 major projects $100,000 minor projects,
analysis, research and additional technical
. effort. Possibly
$20,000/year operating costs
M0NS 09#750
V. COSTS (cont'd)
C. Program to get to 5 ppb 2*0.01 #/day by carbon treating Dept. 246 Effluent of 200 GPM.
D. Program to get to 5 ppb cs 0.4 #/day by carbon treating total plant Effluent.
E. No process known to get below 5 ppb PCB In Effluent streams.
COSTS Costs not known at this time
Costs not known at this time
Costs not known at this time
Edward E. Stewart Technical Services Department