SHELL OIL COMPANY
SHELL CHEMICAL COMPANY
DEER PARK MANUFACTURING COMPLEX
TO DEER PARK MANUFACTURING COMPLEX E MAINTENANCE SUPERVISOR MR. M. J. CURTIS
DATE AUGUST 1, 1978 FROM PROJECT ENGINEER
DEER PARK MANUFACTURING COMPLEX
SUBJECT DEMOLITION OF SR-1 TUBE
As per our telecon, this letter is to inform you that the projec for removal of asbestos containing insulation from the Sulfur 1 and 2 Recovery Units has been approved. The necessary letter has been sent to the EPA (copy attached). The funds allocated to you are as follows:
Labor allotted Material allotted Estimated disposal
cost at land fill
1000 man-hours $5,000
$15,000
This is to include all cost included with the removal, bagging, tagging, putting in closed barrels, transportation costs to land fill and the disposal cost at the land fill.
I would appreciate your estimate of the caleridar days required to complete the demolition and also a by-weekly summary of charges to the demolition account both for labor and material so that I might control the costs on this project. The account number that has been assigned to the project is 961617 with retirement labor detail codes.
RAW/ps Attachment cc: Messrs.
R. M. Kentoall-Cook J. G. Massey D. G. Miller R. M. Nicodemus W. H. Probst R. P. Saxby W. W. Wright OP-II Files
/<
LAM 000252
DPMC-15975
r
t
C
SHELL CHEMICAL COMPANY
A DIVISION OF SHELL OIL COMPANY P. O. BOX 2633
DEER PARK, TEXAS 77536
June 14, 1978
Subject: Removal of Asbestos Insulation
CERTIFIED MAIL RETURN RECEIPT REQUESTED
Regional Administrator, Region VI U. S. Environmental Protection Agency 1201 Elm Street, First International Building Dallas, Texas 75270
Gentlemen:
This letter is to give notice of the start of demolition of a facility containing equipment and piping insulated with asbestos material as required by CFR 40, Part 61.22(d). The following information is for your consideration.
(1) Name of Owner or Operator
Shell Oil Company
(2) Address of Owner or Operator
One Shell Plaza, Houston, Texas 77002
(3) Description of Facility to Be Demolished
A sulfur recovery unit was built in 1952. A second unit was constructed in 1966. These facilities, which have been idle for several years because of the construction of more modern recovery units, will be dismantled. Approximately 10,000 square feet of nominal two-inch thick pipe insulation will be removed by contract per sonnel under Shell supervision from lines ranging from 2 inches to 30 inches in diameter. Also, approximately 15,000 square feet of insulation will be removed from eleven pieces of process equipment such as columns, vessels, and furnaces. The smallest vessel is. 3 feet in diameter and 15 feet high. The largest is 10 feet in diameter and 20 feet high.
(4) Location of the Facility to be Demolished Deer Park Manufacturing Complex, Deer Park, Texas
LAM 000253
DPMC-15976
Regional Administrator, Region VI
C U. S. Environmental Protection Agency
2
(5) Scheduled Starting and Completion Dates
Starting Date:
July 5, 1978
Completion Date: October 1, 1978
(6) Procedures to be Employed
(a) Insulated piping shall be removed as units or in sections in accordance with paragraph (d)(4)(iii) of the regulations. Asbestos materials exposed during cutting or disjointing or exposed to permit lowering of equipment to grade shall be wetted. Units, sections, or other parts will be lowered carefully to ground level to avoid air scattering of asbestos material.
(b) The asbestos insulation materials shall be stripped from removed piping by removing the weatherproof cover, immediately wetting the exposed asbestos material, and promptly removing this wetted asbestos material into fibreboard drums lined with heavy weight plastic bags. Filled drums shall have the plastic liner bags tied tightly at the top, lids installed, warning labels affixed in accordance with regulations, and stored, adequately protected from the weather, pending transportation to an approved disposal site or facility.
(c) When sufficient asbestos-filled drums are accumulated, they will be transported by truck to Rollins Disposal Service at Deer Park, Texas, for final disposal..
If there are any questions concerning this operation, please contact W. W. Wright, (713) 476-7248.
Very truly yours.
H. J. Bettencourt Superintendent - Chemical Deer Park Manufacturing Complex
be: Head Office Manufacturing -
Environmental Conservation -
Manager, Mr. A. G. Smith
c bbc: R. P. Frutiger
R, A. Walsh
co^Tr^
W. V. Jacks
EVC File
J. D. Ransdell
EVC-RO
J. L, Rivard
Env. Con. Chron (2)
D. G. Miller
LAM 000254
DPMC-15977