Document jKz7NG9mYJ4mNe1Mx9LZNgn2
DANA CORPORATION
'
VICTOR PRODUCTS DIVISION
F. S. #10-3
FACTORY STANDARD
March 10, 1976
Supersedes -issue of
-
'______ ________________ December 11, 1972______ ___________________ _______________
VTCTOCOR 190 WITH HOLLINGSWORTH & VOSE FACING
DESCRIPTION:
This Factory Standard covers the manufacture of various gauges of VICTOCOR l0 made with Black Plate Steel Low Prong Core and Hollingsworth & Vose ASBESTOPAC 998 fac ing material.
MATERIALS:
.1. .0066" (6C#) P. S. #103 Black Plate F.S>J^6 Core
2 .0083" ll) P. S. #103 Black Plate^rS.
Core
3. ASBESTOPAC 998 from Hollingsworth & Vose,
#096
U. Water
\ \\
9. Formula #997
_'
. \ vt Vi
PROCEDURE:
Assembling: Dept. 205
When individual steel of proper gauge is perforated and\ cuij^i two pieces of Rollings; the- gauge also spec^Lfie
Dg^Bratde, below
between ASBESTOPAC 998 of
When VICTOCOR 150 is to be made on the continuous process equipment, the steel is set up to feed into the equipment between two continuous lengths of asbestos.
Combining: Dept 209
The assembled materials are combined on an individual
sheet combiner or on the continuous process equipment.
The following table correlates the proper core; the
proper gauge and basis weight of asbestos facing; and
the corresponding aim, combined, and final gauge of
VICTOCOR 190:
.
Core Material,
Steel Phickness,
HfeV ASBESTOPAC 998
Basis Weight,
Thickness
lb/U80 sq.ft..
in.
in. Nominal Range
VICTOCOR 150 Aim Combined Gauge,' Gauge,
in. in.
.0066 .0083 .0083 .0003 .0083
99
92-98
.018-.022 .039-.037 03U-.039
67
63-70
.023-.027 .01*2-. OLD .0L1-.0L6
78
7L-81
.026-.030 .0L9-.091 .0L9-.09L
82
78-86
.028-.033 .05L-.096 .09L-.099'
109
100-110
.036-.0U2 .063-.069 .06L-.069
Final Gauge,
in.
.039--0L0 .OL2-.OL7 .090-.099 .095-.060 .065-.070
Aim gauge is the desired gauge of material leaving the combiner. Combined gauge is the required gauge of material after having been combined and allowed to recover. Final gauge is the required gauge of finished gaskets that have
been blanked, then coated viith Formula #997 and baked (if required).
. VPD-101-0001756
DANA-323
DANA
DANA CORPORATION
Page 2
F. S. #10.3
March 10, 1976
A very small amount of water may be used to moisten the
rolls of the individual sheet combiner if necessary to
prevent stick.
-
The continuous process equipment shall be operated with the roll surfaces at 180-210F.
Inspection of Combined Material; _ Dept. 2l3 .
Before proceeding with an order after set-up, the In
spection Department shall examine and approve of the* quality of the mechanical bond between the core and facing, by attempting to peel the facing from the core on both sides of combined material. It must not be possible to pull the facing from the core, with one exception: material is acceptable even though the facing may be pulled from the core, as long as the prongs remain somewhere between a condition of verti cal after separation and a condition of .020" apart at each perforation, and the facing shows that the prongs have cut into the facing and not merely in dented.
Finished material shall be free of creases, scuff marks, and warp.
Blanking:
Per analysis card.
Coating: Dept 217
When specified on the order. Formula #597 shall be applied to the blanked parts in accordance with Fac tory Standard #319-
Then the gaskets shall be baked in the #5 or #6
Precote oven for an 18-20 minute cycle during which the temperature is maintained at 280-300F for at least 8 minutes, to dry the coating and cure the facing material.
Uncoated gaskets need not be baked unless specified on the order.
Flanging: ,- Per analysis card.
cont'd.
VPD-101'0001757
DANA CORPORATION
Page 3
F. S..#la3 March 10^ 1976
Inspection of Gaskets: Dept. 21*3
Gaskets shall be inspected per analysis card re
quirements. The final gauge shall be as specified in the above table.
Indicates change. Revised by:
Materials Engineering
Copies to: Application Engineering Chief Engineer Gasket Inspection Gasket Prototype Shop Gen. Foreman, Gasket Mfg. Gen. Foreman, Material Mfg. Industrial Engineering International - 6
Manufacturing Supt. Plant Controller Plant Mgr. - Chgo. Plant Mgr. - Havana Qual.Cont .Mgr.-Chgo. Qual.Cont .Mgr. -H avana Raw Material Inspection Tool Engineering
Dept. Dept.
203 217
DAKA CORPORATION
VICTOR PRODUCTS DIVISION FACTORY STANDARD
Supersedes issue of '_________Decemher 11, 1972_______________________
F. S. #1(13 March 10, 1976
VTCTOCOR 150 WITH HOLLINGSWORTH & VOSE FACING
DESCRIPTION: MATERIALS: PROCEDURE:
This Factory Standard covers the manufacture of 'various
gauges of VICTOCOR 150 made with Black Plate Steel Low Prong Core and Hollingsworth & Vose ASBESTOPAC 95>8 fac ing material.
1. .0066" (60#) P. S. #103 Black Plate F.S. #3b6 Core
2. .0083" (75#) P. S. #103 Black Plate F.S. #3U6 Core
3. ASBESTOPAC 958 from Hollingsworth & Vose, P. S . #096
b- Water
5. Formula #597
,
Assembling: Dept. 205
When individual sheets of VICTOCOR 150 are to he made. steel of proper gauge as required per the table below
is perforated and cut to size, then assembled between two pieces of Hollingsworth & Vose ASBESTOPAC 958 of the- gauge also specified in the table.
When VICTOCOR 150 is to be made on the continuous process equipment, the steel is set up to feed into the equipment between two continuous lengths of asbestos.
Combining: Dept 205
The assembled materials are combined on an individual sheet combiner or on the continuous process equipment.
The following table correlates the proper core; the proper gauge and basis weight of asbestos facing; and the corresponding aim, combined, and final gauge of VICTOCOR 150: `
Core
HfcV ASBESTOPAC 958
Material,
Basis Weight,
Thickness
Steel
lb/b80 sc.ft.
in.
thickness, in. Nominal Range
_______ VICTOCOR 150
Aim
Combined
Gauge,
Gauge,
in. in.
.0066 .0083 .0083 .0083. .0083
55
52-58
.018-.022 .035-.037 -.03U- .039
67
63-70
.023-.027 .0R2-.0UU .0hl-.0l|6
78
7b-8l
.026-.030 .0R9-.051 .0U9-.05R
82
78-86
.028-.033 .05U-.056 .05b-.059
105
100-110
.036-.0ij2 .063-.065 .06b-.069
Final Gauge,
in.
.O35-.Ol<0 .0U2--.05J .050-.055 .055-.Oto
065-. wo
Aim gauge is the desired gauge of material leaving the
combiner. Combined gauge, is the required gauge of material
.
after having been combined and allowed to recover,^ Final .
gauge is the required gauge of finished gaskets that have
been blanked, then coated v.ith Formula #597 and baked (if
.
required).
1.
VPD-101-0001759
OSAKA . DANA CORPORATION
Page 2 F. S. #la3 March 10, 1976
A very small amount of water may be used to moisten the rolls of the individual sheet combiner if necessary to prevent stick.
The continuous process equipment shall be operated with the roll surfaces at 180-210F.
Inspection of Combined Material: Dept. 2ii3
Before proceeding with an order after set-up, the Inspection Department shall examine and approve of the quality of the mechanical bond between the core and facing, by attempting to peel the facing from the core on both sides of combined material. It must not be possible to pull the facing from the core, with one exception: material is acceptable even though the facing may be pulled from the core, as long as the prongs remain somewhere between a condition of verti cal after separation and a condition of .020" apart at each perforation, and the facing shows that the prongs have cut into the facing and not merely in dented.
Finished material shall be free of creases, scuff marks, and warp.
Blanking:
Coating: Dept 217
Per analysis card.
When specified on the order. Formula #597 shall be applied to the blanked parts in accordance with Fac tory Standard #319-
Then the gaskets shall be baked in the #5 or #6
Precote oven for an 18-20 minute cycle during which
the temperature is maintained at 280-300F for at
least 8 minutes, to dry the coating and cure the
facing material.
-
Uncoated gaskets need not be baked unless specified on the order.
Flanging:
Per analysis card.
'
cont-'d.
VPD-101-0001760