HEATING VENTILATING AIR CONDITIONING GUIDE 1944
a second-stage reduction. If a two-stage reduction is made, it is well to install a pressure gage immediately before the reducing valve of the second-stage reduction also. In sizes 3 in. and above, it is advisable to tap the bodies of the reducing valve on inlet side for purposes of draining condensate accumulation through steam traps. Control Valves
Gate valves are recommended in all cases where service demands that the valve be either entirely open or entirely closed, but they should never
Fig. 6. Typical Connections foe Two-Pipe System
Fig. 7. Top and Bottom Opposite End Radiator Connections
Fig. 8. Connections to Radiator Hung on Wall
be used for throttling. Angle globe valves and straight globe valves should be used for throttling, as done on by-passes around pressure reducing valves or on by-passes around traps. Connection to Heating Units
Riser, radiator and convector connections must not only be properly pitched at the time they are installed but must be arranged so that the pitch will be maintained under the strains of expansion and contraction. These connections may be made by swing joints which permit the ex pansion or contraction to occur under heating and cooling without bending of pipes. To take care of expansion in long risers, either expansion joints of commercial construction or pipe swing joints are used. Anchoring of pipes between expansion joints is desirable.
296
CHAPTER 15. PIPING FOR STEAM HEATING SYSTEMS
Fig. 9. Typical Pipe Coil Connections
Indirect radiator
Gate vahre-
Dry return or air line/
Check valve Wet return
Dirt pocket-
This point to be at . least 24 in. above boiler
water line or as required
by pressure drop.
Fig. 10. Typical Piping Connections to Concealed Heating Units with Wet Returns
Indirect radiator
Fig. 11.
Dirt pocket
Trap
Piping Connections to Indirect Radiators with Dry Returns