Document gaEB1MVb8OZqqxqvmnLNzZZQV
DATE: SUBJECT: FROM: THRO: TO:
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY REGIONS
77 WEST JACKSON BOULEYARD CHICAGO, ILLINOIS 60604
MAY 2 0 2019
CLEAN AIR ACT INSPECTION REPORT North American Stevedoring Company, Chicago, Illinois
Patrick Miller, Environmental Engineer ABC.AB (MN/OH)
Brian Dickens, Section Chief AECAB (MN/OH)
File
BASIC INFORMATION
Facility Name: North American Stevedoring Company (NASCO)
Facility Location: 3901 South Kreiter Ave, Chicago, lllinois
Date of Inspection: April 02, 2019
EPA Inspector(s): 1. Patrick Miller, Environmental Engineer
Other Attendees 1. Rudy Becerra, Safety and Compliance Manager, NASCO 2. Emmanuel Adesanya, Environmental Engineer, Chicago Department of Public Health
Contact Email Address: rudy.becerra@qsl.com
Purpose of Inspection: Verify the installation of ambient air monitors at NASCO
Facility Type: Bulk-manganese handling facility
Regulations Central to Inspection: lllinois State Implementation Plan and the Clean Air Act
Arrival Time: 9:11 AM Departure Time: 10:00 AM
Inspection Type: [:gJ Unannounced Inspection D Announced Inspection
0PFNJN(: C'ONFF.RF.Nf'F
[:gJ Credentials Presented [:gJ CBI warning to facility provided The following infonnation was obtained verbally from Mr. Becerra unless otherwise noted. Process Description: NASCO processes several different kinds of bulk-solid materials including manganese ferroalloys. Bulk solid silicomanganese and ferromanganese arrive approximately four times a year by ship, with occasional deliveries via truck. Bulk-manganese is stored in a warehouse onsite. Bulk-manganese materials are mainly shipped to customers in trucks. NASCO installed ambient air monitors throughout the facility. A Federal Reference Method (FRM) monitor for respirable particulate matter (PM10) and metals, including manganese, was installed and is operating. There are four Federal Equivalent Method (FEM) monitors for PM10. The FR.cM. monitor is co-located with one of the FEM monitors. NASCO also installed a meteorological station that measures wind speed and wind direction.
TOUR INFORMATION
EPA toured the facility: Yes Data Collected and Observations: Each monitoring location was visited. Photos are attached in Appendix A. There was no truck loadout taking place during the inspection. A water truck was wetting the paved road ways. Photos and/or Videos: were taken during the inspection. Field Measurements: were not taken during this inspection.
Page 2 of3
CLOSING CONFERENCE
Compliance Assistance: Mr. Becerra explained that all managers have computer access to the FEM PM1 omonitoring data and the meteorological data. EPA explained that it is helpful to have a notification system to all managers when PM10 concentrations are elevated and there are high wind events. A notification system would allow for managers to then make operational changes to minimize fugitive emissions during those time frames.
SIGNATURES
Report Author: ~
Section Chief: ,. } ~
Date: Date:
<} 1 ~- / I 1
SI ZD/t q
Page 3 of 3
Facility Name: North American Stevedoring Company Facility Location: 3901 South Kreiter Ave, Chicago, lllinois Date of Inspection: April 02, 2019
APPENDICES AND ATTACHMENTS
L I
Appendix 1- Digital Image Log
Page 1 of 1
Facility Name: North American Stevedoring Company Facility Location: 3901 South Kreiter Ave, Chicago, Illinois Date of Inspection: April 02, 2019
APPENDIX A: DIGITAL IMAGE LOG
1. Inspector Name: Patrick Miller
3. Company/Facility Name:
North American Stevedoring Company
5. Number of Images:
6
2. Date(s) of Inspection:
April02,2019 4. Street Address, City, State:
3901 South Kreiter Ave, Chicago, Illinois
6. Archival Record Location:
CD-R labeled NASCO Inspection 04/02/2019
Appendices Page 1 of 7
Facility Name: North American Stevedoring Company Facility Location: 3901 South Kreiter Ave, Chicago, Illinois Date 9f Inspection: April 02, 2019
1: IMG_OOOI.JPG
Location: North American Stevedoring Company Photographer: Patrick Miller Date/Time: 4/2/2019 9:19 AM Camera Direction: Nmihwest Description: Co-located air monitors at Location 3. FRM monitor (right) and FEM continuous monitor (left)
Appendices Page 2 of7
Facility Name: North American Stevedoring Company Facility Location: 3901 South Kreiter Ave, Chicago, Illinois Date of Inspection: April 02, 2019
2: IMG_0002.JPG
Location: North American Stevedoring Company Photographer: Patrick Miller Date/Time: 4/2/2019 9: 19 AM Camera Direction: Northwest Description: FEM continuous monitor at Location 3
Appendices Page 3 of 7
Facility Name: North American Stevedoring Company Facility Location: 3901 South Kreiter Ave, Chicago, Illinois Date of Inspection: April 02, 2019
3: IMG_0003.JPG
Location: North American Stevedoring Company Photographer: Patrick Miller Date/Time: 4/2/2019 9:19 AM Camera Direction: Northwest Description: FRM monitor at Location 3
Appendices Page 4 of7
Facility Name: North American Stevedoring Company Facility Location: 3901 South Kreiter Ave, Chicago, Illinois Date of Inspection: April 02, 2019
4: IMG_0004.JPG
Location: North American Stevedoring Company Photographer: Patrick Miller Date/Time: 4/2/2019 9:22 AM Camera Direction: Northeast Description: FEM continuous monitor at Location 1
Appendices Page 5 of 7
Facility Name: No11h Ame1ican Stevedoring Company Facility Location: 3901 South Kreiter Ave, Chicago, Illinois Date of Inspection: April 02, 2019
5: TMG_000S.JPG
Location: North American Stevedoring Company Photographer: Patiick Miller Date/Time: 4/2/2019 9:30 AM Camera Direction: Southeast Description: FEM continuous monitor at Location 2
Appendices Page 6 of 7
Facility Name: North American Stevedoring Company Facility Location: 3901 South Kreiter Ave, Chicago, Illinois Date of Inspection: April 02, 2019
6: IMG_ 0006.JPG
Location: North American Stevedoring Company Photographer: Patrick Miller Date/Time: 4/2/2019 9:35 AM Camera Direction: Northeast Description: Meteorological station
Appendices Page 7 of 7