TO: BA MELAAS
FROM: CD BARRETT
SUBJECT: MID-YEAR STATUS OF 1979 OBJECTIVES DEPARTMENT OF INDUSTRIAL HYGIENE AND TOXICOLOGY
I. Medical Surveillance
A. Coordinate the implementation of the computer-assisted Health Monitoring System.
Rating TT Meet formal Project Team implementation schedule. 2. Implementation within 3 months of formal schedule. 3. Delayed implementation (over 3 months).
Status
Phased implementation of the Health Monitoring Project during 1979 is presently on schedule in terms of both time and cost. Employee participation in Phase I of the Medical Examination Program exceeded 98% company-wide. The most Significant problem that we have encountered thus far has been our inability to provide employees who are examined during the first pass of the program with a complete computer report of their exam results. This problem should be corrected by the second pass of the exam program beginning in late August. Corporate Systems Services had projected spending $110M of Chemical Com pany funds on the computer program development during 1979. Presently, approximately $50M has been spent as of June 15, 1979. We have spent approximately $10M of the projected $25M allocation for consultants during 1979. I am optimistic that we can meet our overall 1979-80 project schedule.
However, significant problems must be overcome in the following areas.
1. Development of an effective time card system for zone tracking of employees.
27 Development of historical work history infor mation on all employees.
3. Development of an effective system for coding medical data.
A significant delay in hiring the Company Medical Director (which had been anticipated by July, 1979) could result in higher consulting fees next year with Dr. Irv Tabershaw.
004476
Page 2 - Mid-Year Status of 1979 objectives
B. Assist the Plants and Technical Center in establishing the "exposure zones".
1. Complete by March 31, 1979. 2. Complete by 3. Complete by
Status
Exposure zones were established at all the Plants by March 31. Moderate progress has been made in developing a modified exposure zone concept for the Tech Center. Hopefully, the Tech Center modified zone concept (using sanction numbers) will be fully developed by late July, 1979.
C. Coordinate the design of the required industrial hygiene forms (i.e., qualitative exposure data and quantitative exposure data).
Status
The quantitative industrial hygiene form was completedduring May, 1979. Several drafts of the qualitative' forms have been developed. Hopefully, the qualitative . forms will be finalized by late July, 1979.
D. Define the industrial hygiene report requirements.
Rating 1. Complete by February 28, 2. Complete by 3. Complete by
1979.
Status
Industrial Hygiene report requirements were completed during March, 1979. They have been reviewed by Dr. Irv Tabershaw's consulting group and by Dr. Lee Starr's organi zation.
E. Coordinate the development of the computerized "chemical inventory" system.
Status
1
Development of the computerized chemical inventory system was completed by the end of May, 1979. This was approxi
mately 6 weeks to 2 months behind schedule because of lengthy delays in the initial loading of the computer systems with existing safety and health information on Plant chemicals. Mr. Grover Vos will be working closely with
004477
Page 3 - Mid-Year Status of 1979 Objectives
the Plants during the next three months to assure the
complete implementation and utilization of the new
inventory system. This Chemical Company system is
V> w rr
Ut*
P v >> v* ^
^
- -- v*
-
wide chemical inventory system entitled "Celmis".
F. Ensure that the computer-assisted health monitoring system meets the recordkeeping (and reporting) require ments of a noise conservation program.
Status
Marginal progress has been made on this objective. Grover Vos will be evaluating the record-keeping requirements associated with the noise conservation program during the coming months.
II. Training Programs
Conduct an Industrial Hygiene/Toxicology training program
for Marketing S/A employees.
--
status
r-
An informal Industrial Hygiene & Toxicology seminar relating to the MFA's was held in May, 1979, with Marketing, Technical Center and Pampa Plant represen tatives. I have made preliminary contacts with Mr. Ed Vant and Mr. Bob Brown in scheduling a formal IH&T training seminar at the fall Marketing meeting.
Complete training programs on medical surveillance, methanol and carbon monoxide.
Rating 1. Complete by February 15, 1979. 2. Complete by March 15, 1979.
Status
The medical surveillance and carbon monoxide video-tape training programs were completed on schedule. The methanol program was completed during April, 1979.
C. Coordinate `the development of a training program on the work history and industrial hygiene requirements of the health monitoring system.
Rating 1. Complete by July 15, 1979.
Status
004478
The second medical surveillance training program has been re-scheduled for completion during the last quarter of
Page 4 - Mid-Year Status of 1979 Objectives
1979. The program cannot be developed until the Industrial Relations Organization finalizes the Dlans for the time cara ioiie cracjcing syscem.
III. Toxicology
A. Maintain (and promote) management understanding and sup port of the toxicity testing program.
Rating Grade on effectiveness.
Status
Moderate progress has been made in this area. I feel that Company management has a much better understanding and more actively supports our toxicity testing program than does Plant management. I hope to increase my efforts during the last half of the year in promoting . better understanding at the Plants of the toxicity testing program.
. ^
B. Prioritize all Company products for toxicity testing indicating what toxicity data already exists and what needs to be developed. Estimate testing and cost re quirements for the next 3 years.
Rating 1. Complete by March 15, 1979. 2. Complete by April 15, 1979.
Status
This objective was completed on schedule.
C. Coordinate Celanese participation in inter-industry toxicity studies.
Status
Due to time requirements associated with the Health Monitoring System, I have been unable to play an active role in coordinating Celanese participation in inter industry toxicity studies. We need to increase our efforts during the last half of 1979 in initiating indus try-wide studies involving aliphatic alcohols and aldehydes, and possibly several other products.
004479
Page 5 - Mid-Year Status of 1979 Objectives
D. Obtain the toxicity data required for FIFRA registration of paraformaldehyde.
Status
Our department formally assumed full responsibility for the FIFRA registration of paraformaldehyde during May, 1979. The contract and protocol have already been developed with Bio/dynamics to conduct the necessary toxicity testing for the registration. Furthermore, a meeting has been scheduled for June 20 with Dr. Bill Olsen and Company representatives to develop a detailed action plan for pursuing the registration.
E. Serve as Chairman for the Toxicity Review Committee.
Status
The Toxicity Review Committee is still functioning on an informal basis. Hopefully, during the last half of 1979l, fc-1'
the.committee responsibilities and functions can be
:
formalized and semi-regular meetings can be held to
r--
resolve many key toxicity questions. I am still only
marginally happy with our performance in developing
interpretive statements of toxicity test results for
the Plants.
IV. Analytical Support/Monitoring Surveys
A. Obtain or develop a validated air monitoring method for acrylic acid.
Rating 1. Complete by February 1,. 1979. 2. Complete by
Status
We were unable to meet our schedule. Pampa is presently working on the development of an acrylic acid monitoring method, and we are not presently in a position to establish a firm completion date. We have determined that the Union Carbide acrylic acid method is unacceptable. This has been our most challenging method validation project.
v
B. Determing the feasibility of a solid sorbent formaldehyde method.
Rating 1. Complete by March 31, 1979. 2. Complete by
004480
Page 6 - Mid-Year Status of 1979 Objectives
Status
We have lowered our priority in developing a solid
developing such a method will probably be conducted, however, this summer at the Tech Center.
C. Complete validation experiments on the solid sorbent formaldehyde method.
Rating 1. Complete by end of 1979.
Status
See "B" above.
D. Develop an acceptable thermal desorption monitoring method for methanol (including the design of validation experiments).
Rating 1. Complete by the end of 1979.
Status
We have expanded this objective to include the develop ment of acceptable thermal desorption monitoring methods for methanol, acetaldehyde, acetic acid and vinyl acetate by the end of the year.
E. Assist the Pampa Plant in completing a comprehensive industrial hygiene welding survey (including determining the analytical requirements of the survey).
Rating 1. Complete by July 1, 1979.
Status
The Pampa welding study was completed during May, 1979. As you are aware, this study identified serious occupa tional over-exposures to nickel and chrome (VI). As a result of this survey, respirator requirements are being implemented Corporate-wide. Mark Stenzel played a major role in coordinating and directing this overall study.
F. Define the industrial hygiene monitoring requirements for the Terminals.
Rating 1. Complete (and report issued) by February 1, 1979. 2. Complete by March 1, 1979.
Page 7 - Mid-Year Status of 1979 Objectives
Status
in late March, 1979.
G. Complete the industrial hygiene monitoring studies at the Terminals (including the coordination of the analysis of the samples with the Technical Center and outside laboratories).
Rating 1. Complete by August 1, 1979.
Status
Limited progress has been made in this area. The method validation program at the Tech Center this summer will hopefully provide methods for doing much of the sampling at the Terminals. We must significantly increase the ' industrial hygiene support that we are providing our Terminals.
te r
V. Assisting the Corporation
A. Assist the other Operating Companies in defining their medical surveillance requirements.
Rating Grade on effectiveness.
Status
We have made major progress in assisting other operating companies in defining their medical surveillance require ments. We presented an all-day seminar in New York during February for all the operating companies'. Presentations were also given at the Corporate Loss Control Conference in May on the Chemical Company Medical Surveillance Program. Furthermore, we have had numerous telephone contacts with the other operating companies, and have visited both Summit and Louisville to discuss our exposure zone concept. Also, comprehensive workbooks of our project have been disseminated to all operating companies within Celanese. The Chemical Company training programs on benzene, carbon monoxide, methanol, medical surveillance and toxicology are in significant demand with the other operating com panies. They have been used in Fibers, Plastics, Celanese Canada, Charlotte headquarters. New York headquarters, etc.
B. Provide Chemical Company training programs to the other Operating Companies.
Status
See "A" above.
Page 8 - Mid-Year Status of 1979 Objectives
C. Assist the Corporation in defining TSCA requirements for the computerized "chemical inventory" system.
Status
As previously stated, the Chemical Company has played a major role in defining toxicity requirements for the computerized chemical inventory system. The Chemical Company inventory system is being expanded into the Corporate TSCA chemical inventory system.
D. Assist the Director of Product Safety and the other Operating Companies in evaluating new products.
Status
No progress in this area.
E. Provide analytical support as requested.
^
Status
Analytical support has been provided to all other operating companies in the area of monitoring of welding fumes. We have also disseminated our acrylate monitoring methods to other operating companies.
F. Coordinate the Company Industrial Hygiene and Toxicology program with the Corporate program in order to avoid conflict.
Status
As you are aware, considerable conflict has resulted with our attempt to coordinate the Chemical Company toxicity testing program with Dr. John Clary. In spite of this, I feel that progress has been made. Much of our conflict has resulted because of a major difference in philosophy as.to whether the toxicity testing program should be a strong Corporate program or one controlled by the Company and coordinated by the Corporation.
VI. Special Projects
A. Sponsor a Texas A&M student in an industrial hygiene summer program.
Status
Mr. Rod Simmons, graduate student from Texas A&M is presently conducting a method validation program at the Tech Center under the coordination of Mr. Mark Stenzel.
004483
Page 9 - Mid-Year Status of 1979 Objectives
VII. TSCA
Status
One substantial risk report was processed during the first half of 1979. The Company and Corporate procedure worked extremely well in evaluating the Clear Lake report on acetic acid. No substantial risk was indicated
B. Work closely with the Technical Center and other organi zations in assisting compliance with all TSCA-related requirements, such as premanufacturing notification, etc.
Status
Two key meetings have already been held with Tech Center management to coordinate present and proposed TSCA-relate requirements, including pre-manufacturing notification. ~Nevertheless, we need to increase our efforts in working closely with the Tech Center in the area of TSCA-related programs. Depending on medical surveillance manpower requirements, Grover Vos will attempt to conduct this study during the last quarter of 1979.
VIII. Noise Control
A. Determine whether the noise monitoring program should be coordinated by our Department and conducted by the Plant Industrial Hygienists.
Rating 1. Complete by March 1, 1979.
Status
Presently, no focal point has been established either at . the Company or Plant level to direct a noise monitoring program. Grover Vos has been assigned the task of evaluating the Company's current situation with regard to noise monitoring and control. This task will commence late this summer or in the early fall.
B. Establish a noise monitoring program at each facility.
Rating 1., Initiate program by July 1, 1979.
Status
004484
Recommendations concerning the establishment of noise monitoring programs at each facility will be included in the results of Mr. Vos' evaluation.
Page 10 - Mid-Year Status of 1979 Objectives
IX. Customer Service
hygiene and toxicology.
Status
Customer service requests are being coordinated by our department on a weekly, if not daily, basis. Many of our customers are confused and frustrated because of expanding governmental requirements involving FIFRA and TSCA. I envision our customer service responsibilities increasing significantly during the next year.
B. Develop an improved system for filing all customer requests, customer complaints, and responses (system should meet all TSCA requirements).
Status
Minimal progress to date. This objective will be one of the main responsibilities of the proposed Environmental Health Specialist position in our department.
Become knowledgeable of the Transportation Emergency Response Guidelines.
Moderate progress in this area. Our department presently serves as consultant to the Emergency Response Program. We have re cently been requested by Mr. Herb Reed to develop toxicology press releases on each of our products. We hope to work jointly with Dr. John Clary in completing this request during the latter half of 1979.
XI. Miscellaneous
A. Coordinate the industrial hygiene review of all new facilities, major RFA's, etc.
Status
Moderate progress has been made in this area. We have worked closely with the Bay City Plant in evaluating the necessity of extensive engineering controls to limit methanol exposure in the nylon salt unit. We need to significantly increase our efforts in this area. Grover Vos will be working closely with the Tech Center in evaluating new processes early in the development and
evaluation stages.
B. Assist the Plants in developing engineering and work practice controls to alleviate potential health hazards.
Status
004485
Significant progress has been made in working with the
c
Page 11 Mid-Year Status of 1979 Objectives
Plants in developing controls to protect welders, employees
played an active role in evaluating the proposed acrylic acid inhibitor at the Clear Lake Plant.
C. Develop a policy for the industrial hygiene monitoring of contractor employees.
Rating 1. Implement policy by March 1, 1979.
Status
A policy was developed and proposed to the Plants prior to March, 1979. The new policy has been partially im plemented at the Plants. However, follow-up needs to be conducted to promote a thorough understanding of our new ' policy by major contractors, such as Arthur Brothers.
The Chemical Company policy, again, is being expanded into, a Corporate guideline.
fe
r`
D. Represent the Company in the Formaldehyde Institute.
Status
I have not played an active role in the Formaldehyde Institute during the first half of 1979. However, I have kept Marketing and Management informed of the status of the Institute, and I did work closely with Dr. Dave Medley in' writing his introductory speech. It was pre sented at the opening meeting of the Formaldehyde Institute.
E. Coordinate the Company Industrial Hygiene and Toxicology Program with the Employee Relations Organization.
Status
I have worked closely with Mr. Bob Swanbeck and the Plant Industrial Relations Organization in coordinating our Industrial Hygiene and Toxicology program. Overall, I am pleased with our efforts in this area. However, we must continue to actively support this area since Industrial Hygiene and1 Toxicology can be easily misunderstood by both management and our employees.
F. Advise management on the potential impact of new or proposed Federal regulations (such as OSHA, EPA, FIFRA, etc.)
Status
Most efforts in this area have been directed through the Company Product Safety Committee and the direct involve ment at the Tech Center in the area of TSCA and
Page 12 - Mid-Year Status of 1979 Objectives
premanufacturing notification. We need to play a more significant role in apprising management of the impact
G. Assume responsibility for coordinating the FIFRA program.
Status
Our department assumed partial responsibility for FIFRA in January, 1979. Complete responsibility for FIFRA, including responsibilities for obtaining FIFRA registration of Celanese products, was assumed by the department in May of 1979.
H. Review the Company's Occupational Health Policies for possible revision.
Rating 1. Complete by June 1, 1979.
Status
No action at present. I hope to review our occupational health policies during the last quarter of 1979 for possible revision.
I. Develop internal permissible exposure limits (PEL's) when applicable.
Status
Although we follow informal procedures in developing internal permissible exposure limits, I am satisfied with our performance in this area.
J. Provide meaningful input to the regulatory agencies.
Status
We are channeling Chemical Company comments on proposed regulations through Dr. Lee Starr's organization for formal input to the regulatory agencies. We are pre sently commenting only on major proposed regulations such as pre-manufacturing notification due to limita tions in manpower.
SUMMARY:
Overall, I am extremely pleased with the progress our department has made against our 1979 objectives. Our major project from a manpower standpoint will continue to be the Health Monitoring Project through the end of 1980. Increasing record-keeping, filing, and adminis trative requirements associated with TSCA, FIFRA, the chemical inventory system, and the toxicity testing program have necessitated the addition of an Environ mental Health Specialist to our department. Assistance
004487
Page 13 - Mid-Year Status of 1979 Objectives
in this area will free Mark Stenzel, Grover Vos and myself to resolve more pressing problems.
CDB/dr
DAVE BARRETT