MEMORANDUM San Francisco, California December 1, 1969 Cost Estimate HCC Conversion to Crude Wait El Paso Refinery MR. R. W. DAVIS: EL PASO r At your request, we have prepared a cost estimate for converting the HCC frac tionator into a crude topping still, the first of a 3-stage crude unit. We estimate the cost of the work at $3,390>000 hut suggest a range of $3,200,000 to $4,000,000. While you have asked for an appropriation request accuracy estimate, we "believe it a matter of prudence to_consider it of less accuracy for the following reasons: 1. The process design is very preliminary and does not eantain^jtaeh fluid stream data as flow rates, temperatures and properties. Only a very rough heat and material balance was prepared. 2. Wo condensation dataT is available for any of the column overhead services. 3- Only preliminary data is available for furnace vaporization and the Alcorn furnace evaluation has not come through. While the furnace appears to be able to handle the 30,000 BPQD rate, its capacity to handle the 40,000 BPOD rate seems very questionable, even with a flash drum removing light ends from the crude. The estimate for 40,000 BPOD includes only the amount 1 of money included in the 1966 estimate, updated. We estimate the cost reduction for 30,000 BPOD Crude throughput at &300,000 or a cost of $3,090,000. The suggested cost range for this facility is $2,900,000 to $3,550,000. Several other alternates sure shown on the report pages entitled "Estimate Alternates." The estimate includes no allowance for escalation of material, labor or design costs, which have been increasing substantially in the last few years. The estimate is based on El Paso direct labor costs and experience for Group I-B prorates. The basis of the cost estimate is the following, all attached to this report: CRC Preliminary Process Design GT-23259 . Proposed Plot Plan GT-23257 El Paso Jet Bender Sweetener PfcID GT-23258 El Paso Off-Plot Marked up PfcID GT-23258 El Paso Off-Plot Marked up B&ID PA-13-21751 (included in work file only) Bender and Tankage Scheme - Sketch #1 Materials Selection of Nov. 5, 19&9 Previous Cost Estimate for #7 Crude Unit Feb. 1966 (not attached) Description of Estimate and report Chevron BB 014328 Mr. R. W. Davis -2- December 1, 1969 The CRC preliminary process design was revised to reflect equipment numbering, same of the assumed temperatures, and new equipment where existing equipment proposed by CRC for re-use was either inadequate or where such equipment has already been dismantled and removed. _: Estimated utility requirements are indicated on the attached tables along with various alternates for air cooling vs. water cooling. We plan to return the 1966 cost estimate work files to you very soon and will also ship the work files for this estimate. Please advise if we can furnish further information on this cost estimate. JL: ff Attachments cc: Mr. F. S. Gates - El Paso Mr. T. K. Ling - CRC ^ SCA/BTU/Sm/JUi HLK JL (2) 3 W. F. BRUSHER Chevron BB 014329 EXCHANGER COST ESTIMATING WORK SHUT lff-51 This sheet assumes the designer Is familiar vith the Date n7n/&9 By no "Froa Uf Basis S^T7KMiM(^ , -pRessutiis ( tuaet. 2, SLL. ivro"**' Selection Shells 2UO Ft2 Each V//ATST52- <5c? 1.' . i>:_. Material Design Notes Ifc-AlTY N.12. TS, chAwnsi- M* ^ 5 4dC ludeS, Si4<5LL COST = Xfcs ^ 'ZS' M . f.0.->-oo ) (^5ooo ) No Shheellls / From Curve --' C C U2.2. ^--EDC Ratio / MKB T% O >~L'~2, --l Extras (fa 6>ft Mw. TuCo 64^ ("iJ 1 LoM<$. > 11.^0 'L 1 ' ~ 2, \ 2.0 Field Extras (l<#) ( ) S mT5 TeTEM- Test Jig SO r 0, IS~(-2110)= S'Of 320 11,4^0 -1.340 37a Exchanger Cost Revision <> <$> PRINTED IN USA Chevron BB 014327 ^ I^I^Q [] c EF-51D (150-CD-1-66) ioc