As of July 1, 1948, the status of v/ork on the Zinc Plant was as follows: (Koto items previously listed as couplet are omitted).
2--B STEARNS-BOGER CONSTRUCTION
PRIMARY CRUSHING!- PLANT
J ' 'Airveyor 100$ complete, Panfeedera 100$ complete. Damaged shaft on mag netic head pulley of belt conveyor due to poor alignment o Being repaired?
CONDENSER CIRCULATING PUMPS
All pumps complete 100$. One motor drive installed complete using rented motor. Steam turbine one pump 90$ complete o Short motor one pump.
FUMING FURNACE COOLING K20 PIPING
100$ 'Complete
**
PRIMARY AIR FURNACE
Complete except installing air valves and heater cover on one heaters
TERTIARY AIR
Headers 100$ complete? Piping headers to furnace 15$ complete. 300 Tan Coal Bins - 100$ complete except alterations discharge gate?
CONVEYORS 300 TON TO 30 TON BINS
All conveyor chain received 20$ in place.
FURNACE BUILDING 100$ Complete.
BOILER BUILDING ' 100$ Complete except gutters and. drain spouts.
FUMING FURNACE
100$ Complete.
30 TON SENS
Operating mechanism 100$. Piping 100$. Limit switches 5$ Level indica tors 70$. Vibrators 10$.
PULVERIZERS
100$ Complete except'automatic controls and calibration tests.
.JACKET CIRCULATING WATER PUMPS
Complete on steam units except steam piping which is 30$ complete. I ask
pumps for motor driven units.; `
___________ __
PLAINTIFF'S EXHIBIT
ASA-1003
ASARCO ELP 0001224
AIR HEATER STEAM PIPING "* 70$ Complete*
BOUSE BLQif DOWN & MISC. STEAK & WATER PIPING
SOOT BLO'Ml AIR PIPING RECEIVERS TO BOILER C$ Complete.
BOILER FANS Complete except damper operators 15$ complete, expansion joint 80$ com
plete, belt guards 0$ complete*
INTERMEDIATE FAN Complete except damper operator 80$ complete, expansion joint 80$ com
plete, belt guard 0$ complete*
BAGHOUSE FAN Complete except damper control 0$, drive motor 0$, belt guards 0$, ex
pansion joint 0$*
ZINC BLOWER Complete except piping* Piping' 98$ complete.
5000 KW GENERATOR Complete except piping* Piping 98$ complete*
ZINC WASTE HEAT BOILER Pressure parts 100$ complete* Steam drum baffles and separators 30$.
Insulation water walls: Plastic insulation 80$, Vitrobestos 0$, casing 0$, lance doors 100$*
CONVECTION SECTIONTile 75$, Vitrobestos 0$, lance doors 100$, casing 0$* Economizer: Steel
casing 80$, lance doors 0$, insulation 0$ Water wall supply headers and super heater feeder insulation 5$
BOILER FEED PUMPS 1 ' 95$ Complete*
ROT WELL & HOT WELL POMPS 100$ Complete*
OIL REMOVAL FILTERS & PIPING~~~ 8^ Complete*
ZINC BLOWER AIR LINE POWERHOUSE TO FURNACE lDO$Complete
MAIN STEAM LINS 100$ Complete*
BOILER FEEDWATER LINE. 500# AIR LISE. TRAP LINE. BLOWDOWN LINS. POWERHOUSE
TO FURNACE Complete except 500# Air line which is 95$ complete*
ASARCO ELP 0001225
STSAKHS-RQGER ENGINEERING 13000 C0P0 Lead Blower - 95% Complete M n n " piping to Bio Fcee 90% complete. Misc. Motor & Belt Guards 90% Complete
' STEARNS-ROGER ENGINEERING STAFF Chief Draftsman, 2 draftsmen One draftsman working on other El Paso
Works
CD-*5121 - BAUMAN ELECTRIC CONTRACT Moo 1 SUBSTATION - Complete and in sendee One item not completed is
the differential protection for transformers Awaiting shipment of correct dif ferential relay.
HO. 2 SUBSTATION - Complet and in service
NO. 3 SUBSTATION - Complete and in service
" IX). 4 SUBSTATION - Complete end in service Shut down at present to install metering transformers that just arrived
WIRING 500# AIR COMPRESSORS
&5% Complete
WIRING BOIIER FEED PUMPS
100*> Complete
CONDENSER CIRCULATING'PUMPS 95^_campiebe can't collets until receive motors
DELEADING PLANT-DRIVES 60$ complete - held up by excavation and Millwrights
COAL HANDLING & PRIMARY CRUSHING 100? Complete and tested
EQUIPMENT BOHiER & FURNACE AREA 40? Complete
2300 VOLT .SWITCHGEAR 100^ Complete
POWERHOUSE LIGHTING ~ 90? Complete
POWERHOUSE MOTORS 100? Caaplete
5000 EW GENERATOR "" ia^T. r
*
CONVENORS 1 TO IB IHCL-, 46, 47, 48, 49, 93, 94, 73, 100, 101, 50, 51, 52, 56, 57,
58. 59. 60. 90. 91. 61. 62. 63__________
_______________ ;
These conveyors 100? complete except plugging switch interlocks
CD-5117 - STEEL CONTRACT
NO. 2 COOLER - 100% Complete
ASARCO ELP 0001226
-4-
NO. 1 COOLER - 100$ Complete.
FIDE FAN TO #1 COOLER Complete except floor grating.
FIDE BOILER TO BOILER PAH ' IGQ$'.Complete.^'
NO. 3 COOLER'
-- Hfc90&- Complete except floor grating tack raiding.
THW FEEDER HLDQ't .100$ Complete except floor and stair grating.
KILN BURNER BLDG. 100$ Complete except floor and stair gratingi
FIDE ib COOLER. TO IJ5AD BAGHQUSB 100$ Complete. ~
ziwc oxids bin 100$ Complete, welding 80$ complete.
white: oxide loading 100$ Complete, grating 100$ complete.
' dsnsified OXIDE-LOADING 100$ "Complete
COLD SLAG HANDLING 100$ erected, 15$ welded, no grating on floor plate.
We are still short some floor and etair grating on this order.
HESO. MECHANICAL INSTALLATION & IgLLWRIGHT WORK NOT PREVIOUSLY MENTIONED
BAGHOUSE SHAKER KECRANISH - 100$ Complete inel, adjusting bags. BAGHOUSE DAKPER CONTROL~ 100$ Complete except flow control valves. CONVEYORS # 1 to 18. 46. 47, 48, 49, 95, 94, 101, 73, 100, 50, 51, 52, S3,
' 57, 58, 59, 6o, 90, 91, 61, 62 and 63 - 100$ Complete.
ROTARY COOLERS - 100$ Complete except cooling H20 piping. WEST KILNS - 100$ Complete, except seals which are 90$ complete-and gear guard. EAST KILN - 100$ Complete except seals which are 90$ complete. ELEVATORS 81. 82,/H, and 85 - 98$ Complete
CONVEYORS 20, 21, 22, 23, 24, 25, 19, 26, 27, 28 - 98$ Cocpleter CONVEYORS 30 AND 31 - 80$ Complete. CONVEYORS 102 AND 103 -50$ Complete. CONVEYORS 29, 36, 32, 37, 34, 35, 38, 39, 33, 40, 41, 42, 43, 44, 45 - 10$ complete. VIBRATING SCREEN - 40$ Complete. JAW CRUSHER -- 95$ Complete,
Yours very truly.
LF/olc
LEROY FRENIN Resident Construction
ASARCO ELP 0001227