Document g259N03qEjqpb7jEODON6RdL3

Hr. E<j IfcLc Tittmarm Present El Paso, Texas July 1948 ZINC PLANT CONSTRUCTION Dear Sir; As of July 1, 1948, the status of v/ork on the Zinc Plant was as follows: (Koto items previously listed as couplet are omitted). 2--B STEARNS-BOGER CONSTRUCTION PRIMARY CRUSHING!- PLANT J ' 'Airveyor 100$ complete, Panfeedera 100$ complete. Damaged shaft on mag netic head pulley of belt conveyor due to poor alignment o Being repaired? CONDENSER CIRCULATING PUMPS All pumps complete 100$. One motor drive installed complete using rented motor. Steam turbine one pump 90$ complete o Short motor one pump. FUMING FURNACE COOLING K20 PIPING 100$ 'Complete ** PRIMARY AIR FURNACE Complete except installing air valves and heater cover on one heaters TERTIARY AIR Headers 100$ complete? Piping headers to furnace 15$ complete. 300 Tan Coal Bins - 100$ complete except alterations discharge gate? CONVEYORS 300 TON TO 30 TON BINS All conveyor chain received 20$ in place. FURNACE BUILDING 100$ Complete. BOILER BUILDING ' 100$ Complete except gutters and. drain spouts. FUMING FURNACE 100$ Complete. 30 TON SENS Operating mechanism 100$. Piping 100$. Limit switches 5$ Level indica tors 70$. Vibrators 10$. PULVERIZERS 100$ Complete except'automatic controls and calibration tests. .JACKET CIRCULATING WATER PUMPS Complete on steam units except steam piping which is 30$ complete. I ask pumps for motor driven units.; ` ___________ __ PLAINTIFF'S EXHIBIT ASA-1003 ASARCO ELP 0001224 AIR HEATER STEAM PIPING "* 70$ Complete* BOUSE BLQif DOWN & MISC. STEAK & WATER PIPING SOOT BLO'Ml AIR PIPING RECEIVERS TO BOILER C$ Complete. BOILER FANS Complete except damper operators 15$ complete, expansion joint 80$ com plete, belt guards 0$ complete* INTERMEDIATE FAN Complete except damper operator 80$ complete, expansion joint 80$ com plete, belt guard 0$ complete* BAGHOUSE FAN Complete except damper control 0$, drive motor 0$, belt guards 0$, ex pansion joint 0$* ZINC BLOWER Complete except piping* Piping' 98$ complete. 5000 KW GENERATOR Complete except piping* Piping 98$ complete* ZINC WASTE HEAT BOILER Pressure parts 100$ complete* Steam drum baffles and separators 30$. Insulation water walls: Plastic insulation 80$, Vitrobestos 0$, casing 0$, lance doors 100$* CONVECTION SECTIONTile 75$, Vitrobestos 0$, lance doors 100$, casing 0$* Economizer: Steel casing 80$, lance doors 0$, insulation 0$ Water wall supply headers and super heater feeder insulation 5$ BOILER FEED PUMPS 1 ' 95$ Complete* ROT WELL & HOT WELL POMPS 100$ Complete* OIL REMOVAL FILTERS & PIPING~~~ 8^ Complete* ZINC BLOWER AIR LINE POWERHOUSE TO FURNACE lDO$Complete MAIN STEAM LINS 100$ Complete* BOILER FEEDWATER LINE. 500# AIR LISE. TRAP LINE. BLOWDOWN LINS. POWERHOUSE TO FURNACE Complete except 500# Air line which is 95$ complete* ASARCO ELP 0001225 STSAKHS-RQGER ENGINEERING 13000 C0P0 Lead Blower - 95% Complete M n n " piping to Bio Fcee 90% complete. Misc. Motor & Belt Guards 90% Complete ' STEARNS-ROGER ENGINEERING STAFF Chief Draftsman, 2 draftsmen One draftsman working on other El Paso Works CD-*5121 - BAUMAN ELECTRIC CONTRACT Moo 1 SUBSTATION - Complete and in sendee One item not completed is the differential protection for transformers Awaiting shipment of correct dif ferential relay. HO. 2 SUBSTATION - Complet and in service NO. 3 SUBSTATION - Complete and in service " IX). 4 SUBSTATION - Complete end in service Shut down at present to install metering transformers that just arrived WIRING 500# AIR COMPRESSORS &5% Complete WIRING BOIIER FEED PUMPS 100*> Complete CONDENSER CIRCULATING'PUMPS 95^_campiebe can't collets until receive motors DELEADING PLANT-DRIVES 60$ complete - held up by excavation and Millwrights COAL HANDLING & PRIMARY CRUSHING 100? Complete and tested EQUIPMENT BOHiER & FURNACE AREA 40? Complete 2300 VOLT .SWITCHGEAR 100^ Complete POWERHOUSE LIGHTING ~ 90? Complete POWERHOUSE MOTORS 100? Caaplete 5000 EW GENERATOR "" ia^T. r * CONVENORS 1 TO IB IHCL-, 46, 47, 48, 49, 93, 94, 73, 100, 101, 50, 51, 52, 56, 57, 58. 59. 60. 90. 91. 61. 62. 63__________ _______________ ; These conveyors 100? complete except plugging switch interlocks CD-5117 - STEEL CONTRACT NO. 2 COOLER - 100% Complete ASARCO ELP 0001226 -4- NO. 1 COOLER - 100$ Complete. FIDE FAN TO #1 COOLER Complete except floor grating. FIDE BOILER TO BOILER PAH ' IGQ$'.Complete.^' NO. 3 COOLER' -- Hfc90&- Complete except floor grating tack raiding. THW FEEDER HLDQ't .100$ Complete except floor and stair grating. KILN BURNER BLDG. 100$ Complete except floor and stair gratingi FIDE ib COOLER. TO IJ5AD BAGHQUSB 100$ Complete. ~ ziwc oxids bin 100$ Complete, welding 80$ complete. white: oxide loading 100$ Complete, grating 100$ complete. ' dsnsified OXIDE-LOADING 100$ "Complete COLD SLAG HANDLING 100$ erected, 15$ welded, no grating on floor plate. We are still short some floor and etair grating on this order. HESO. MECHANICAL INSTALLATION & IgLLWRIGHT WORK NOT PREVIOUSLY MENTIONED BAGHOUSE SHAKER KECRANISH - 100$ Complete inel, adjusting bags. BAGHOUSE DAKPER CONTROL~ 100$ Complete except flow control valves. CONVEYORS # 1 to 18. 46. 47, 48, 49, 95, 94, 101, 73, 100, 50, 51, 52, S3, ' 57, 58, 59, 6o, 90, 91, 61, 62 and 63 - 100$ Complete. ROTARY COOLERS - 100$ Complete except cooling H20 piping. WEST KILNS - 100$ Complete, except seals which are 90$ complete-and gear guard. EAST KILN - 100$ Complete except seals which are 90$ complete. ELEVATORS 81. 82,/H, and 85 - 98$ Complete CONVEYORS 20, 21, 22, 23, 24, 25, 19, 26, 27, 28 - 98$ Cocpleter CONVEYORS 30 AND 31 - 80$ Complete. CONVEYORS 102 AND 103 -50$ Complete. CONVEYORS 29, 36, 32, 37, 34, 35, 38, 39, 33, 40, 41, 42, 43, 44, 45 - 10$ complete. VIBRATING SCREEN - 40$ Complete. JAW CRUSHER -- 95$ Complete, Yours very truly. LF/olc LEROY FRENIN Resident Construction ASARCO ELP 0001227 1 . -J AfiADn