Johns-Manville
Internal Correspondence
To: See below
OCT 1 0 1977
From: T. M. Faas for W. E. Volwiler 3-06
Copies: S. B. Gillespie, file/chrono
Subject: PROTECTIVE CLOTHING
D.iie: October 7, 19 7 7
The protective clothing programs and estimates have been reviewed. Please proceed with appropriation submittals.
t
For your information, one plant is using a sand filter on discharge to sewers. This was requested by their municipality.
If there are any questions, please advise.
ma
c
TO:
L. I. Richards/Denison
C. G. Stelchek/Green Cove Springs
W. A. Ford/Long Beach.
J. W. Bird/Stockton
J. H. Scott/Waukegan
,, o, ' 'U Johns-iVJanviMi
!/ r. * ,r \ ; r f ' : J i
.
jo: W. E. Volwilwer, V7IIQ 3-06
/Di.u;: September 7, 1977
crrom: L. I. Rich. ards/M. E. Hatley, Denison
Copies:
Bergman
J. F. Compton
Subject: PROTECTIVE' CLOTHING
II. T. Erode
As suggested in your 8/2/77 letter, we have developed t.'.r
following proposal for protective clothing.
"-
A. Employees to be Covered
*
1. Willow Operators (3) will change coveralls
each day. Estimate usage - 10/person/year ,
0 $20
$600
Disposables For Fill-ins 0 $2.35 x 100 Occurrences
$235
2. Other Production Personnel Disposables
0 $2.35 x 100
$235
3. Maintenance Personnel - Raw Asbestos
Disposables @ $2.35 x 500
'
$117i
4. Receiving Personnel - Raw Asbestos Disposables 0 $2.35 x 200
$470
(Estimated usage for disposables based on first 6 month 1977) . '
$2715 '
B. Maintenance of-Clothing
1. Disposables to be ordered by Transits
Dept.- and transferred to designated
departments. Disposables to be issued
by foreman.
'
'2. Coveralls to be ordered by Transits Dept, and issued by foreman.
3. Coveralls to be washed by Transits
janitor
(no additional manpower
required).
,
`
4. Replace present washer and dryer.
$120C
5. Miscellaneous supplies and clothing repair.
$100
$13 CO
W. K. Volwil.ci:
!i('|/l...'llll.'< -i
l`s
C. Facilities
Locker, room for Willow Operators with laundry and shower facilities 250 sq. to be constructed near willow area.
it.
$10,000
The first year cost for this plan is $14,015 and $2,815 per year thereafter. We are presently spending $4,000 each year on disposable clothes for Willow Operators, Maintenance, Receiving and other production personnel who work around raw asbestos. Also, our present washer and dryea: are in need of replacement. Therefore, the program to supply Willow Operators with coveralls will save money except for the one time cost of $10,000 for the locker, shower, and laundry facilities. These facilities will only be used by the 3 Willow Operators and the Janitor who washes clothes. The separate facility is needed to prevent' raw asbestos from contaminating the regular locker room.
LIR/mb