Document ev5KnKwMNVdM4z1gGYpJNjVYp

Johns-Manville Internal Correspondence To: See below OCT 1 0 1977 From: T. M. Faas for W. E. Volwiler 3-06 Copies: S. B. Gillespie, file/chrono Subject: PROTECTIVE CLOTHING D.iie: October 7, 19 7 7 The protective clothing programs and estimates have been reviewed. Please proceed with appropriation submittals. t For your information, one plant is using a sand filter on discharge to sewers. This was requested by their municipality. If there are any questions, please advise. ma c TO: L. I. Richards/Denison C. G. Stelchek/Green Cove Springs W. A. Ford/Long Beach. J. W. Bird/Stockton J. H. Scott/Waukegan ,, o, ' 'U Johns-iVJanviMi !/ r. * ,r \ ; r f ' : J i . jo: W. E. Volwilwer, V7IIQ 3-06 /Di.u;: September 7, 1977 crrom: L. I. Rich. ards/M. E. Hatley, Denison Copies: Bergman J. F. Compton Subject: PROTECTIVE' CLOTHING II. T. Erode As suggested in your 8/2/77 letter, we have developed t.'.r following proposal for protective clothing. "- A. Employees to be Covered * 1. Willow Operators (3) will change coveralls each day. Estimate usage - 10/person/year , 0 $20 $600 Disposables For Fill-ins 0 $2.35 x 100 Occurrences $235 2. Other Production Personnel Disposables 0 $2.35 x 100 $235 3. Maintenance Personnel - Raw Asbestos Disposables @ $2.35 x 500 ' $117i 4. Receiving Personnel - Raw Asbestos Disposables 0 $2.35 x 200 $470 (Estimated usage for disposables based on first 6 month 1977) . ' $2715 ' B. Maintenance of-Clothing 1. Disposables to be ordered by Transits Dept.- and transferred to designated departments. Disposables to be issued by foreman. ' '2. Coveralls to be ordered by Transits Dept, and issued by foreman. 3. Coveralls to be washed by Transits janitor (no additional manpower required). , ` 4. Replace present washer and dryer. $120C 5. Miscellaneous supplies and clothing repair. $100 $13 CO W. K. Volwil.ci: !i('|/l...'llll.'< -i l`s C. Facilities Locker, room for Willow Operators with laundry and shower facilities 250 sq. to be constructed near willow area. it. $10,000 The first year cost for this plan is $14,015 and $2,815 per year thereafter. We are presently spending $4,000 each year on disposable clothes for Willow Operators, Maintenance, Receiving and other production personnel who work around raw asbestos. Also, our present washer and dryea: are in need of replacement. Therefore, the program to supply Willow Operators with coveralls will save money except for the one time cost of $10,000 for the locker, shower, and laundry facilities. These facilities will only be used by the 3 Willow Operators and the Janitor who washes clothes. The separate facility is needed to prevent' raw asbestos from contaminating the regular locker room. LIR/mb