GUIDANCE FOR IMPLEMENTING PROGRAMS FOR OSHA 29 CFR 1910.119
PROCESS SAFETY MANAGEMENT OF HIGHLY HAZARDOUS CHEMICALS
PART FOUR PRE-STARTUP SAFETY REVIEW
by
PrimaTech
June 10, 1994
Primatech Inc. 445 Hutchinson Avenue, Suite 200
Columbus, Ohio 43235 (614) 841-9800
ABDOO102875
GUIDANCE FOR IMPLEMENTING PROGRAMS FOR OSHA PSM
PRE-STARTUP SAFETY REVIEW
This document contains information that may assist a company in establishing, or reviewing and updating, the pre-startup safety review (PSSR) element of their process safety management (PSM) program. The information in this document is based upon the U.S. Occupational Safety and Health Administration's regulation, 29 CFR 1910.119, Process Safety Management of Highly Hazardous Chemicals. However, this information may be of use to anyone developing or updating a PSM program for any purpose.
In 1993 the U.S. Department of Labor Occupational Safety and Health Administration (OSHA) commissioned Primatech Inc. to develop a `training material reference manual" related to 1910.119. The purpose of the manual is to provide OSHA's Office of Training and Education with a resource for training federal and state OSHA field officers on enforcing the PSM regulation.
The training material reference manual features an annotated form of the Program-QualityVerification (PQV) inspection checklist originally presented in Appendix A of OSHA Instruction CPL 2-2.45A. Example programs are provided to illustrate the positive and negative indicators of the checklist questions. OSHA has agreed to allow Primatech to make this information available to interested parties. This should in no way be construed as acceptance by OSHA of the suitability of the information or examples provided herein.
The format of this document follows the PQV inspection checklist presented in Appendix A of OSHA Instruction CPL 2-2.45A, often referred to as the "compliance directive". For each question in the PQV inspection checklist, clarification is provided on the checklist item along with positive program indicators and negative program indicators for each question. The positive and negative program indicators are intended to provide ideas for the user to help them in assessing their existing or planned program.
The example programs provided in this document illustrate approaches taken by companies seeking to address the requirements of 1910.119. These examples have not been reviewed and/or endorsed by OSHA and should not be construed as model programs.
The example programs provided herein were developed for specific processes, and are not generic in nature. Since the OSHA PSM regulation is performance-based, readers are strongly encouraged to develop programs tailored to their own covered processes.
1
ABDOO102876 This document is offered for the user's general guidance only. This document does not attempt to provide any interpretation of the OSHA regulations. Primatech makes no claims regarding the acceptability to OSHA of the information contained herein to OSHA. Consequently, Primatech can accept no liability for any use which the user may make of the information contained herein. Note that the information contained in this manual does not necessarily represent the opinion of Primatech.
i
i2 i
ABDOO102877
f
OVERVIEW
This guidance document is arranged in a tabular format. The following is a description of each of the column headings used in the table:
PQV Question
The PQV question is derived from the checklist in Appendix A of the OSHA Compliance Directive (CPL 2-2.45A), which is based on the specific regulatory requirements for the element. Note that the verification portion of the checklist includes questions for records review, on-site conditions, and interviews. In order to avoid unnecessary duplication of information, this guidance document references thr- rnecklist questions from the records review section only. Specific questions or concerns from the on-site conditions and interviews sections that are not addressed in the records review section are accounted for in the positive and/or negative program indicators column.
Explanation
The explanation clarifies or provides additional insight into the PQV question. In some cases, the explanation provides an interpretation of the PSM requirement. In no cases should the information contained in this column be viewed as a substitute for the actual regulatory requirement.
Positive Program Indicators
The information included in the positive program indicators column is intended to provide guidance and examples on what to look for in a well developed program. This column also includes guidance on what to look for when evaluating PSM programs. This column is not intended to contain all conceivable attributes of a good program for all industry types. Rather, it is intended to provide suggestions and ideas on what a good program might include.
ABDOO102878
Negative Program Indicators
The information in the negative program indicators column is intended to provide guidance on possible signs of a poor or incomplete program. This information could be of assistance for identifying potential problem areas when conducting PSM program evaluations. A PSM program that contains one or more of these attributes does not necessarily constitute a poor program. Rather, this information is intended to sen/e as a guide on what to look for in a less developed program.
It is important for the user of this manual to understand that over 25,000 employers may be covered under the PSM standard. Covered facilities range from large complex chemical, petrochemical, or petroleum facilities, to relatively simple ammonia refrigeration or chlorination systems. This guidance document cannot cover all of the possible ranges regarding the content of PSM program elements in the various industry groups. Additionally, since the PSM standard is a performance based regulation, this guidance document can not address the specific approaches different companies or facilities may choose to implement in complying with the requirements.
In addition to the table, this guidance document contains several helpful appendices, including:
Appendix A - List of Acronyms
Contains description of key acronyms used in the guidance document.
Appendix B - Glossary of Terms
Contains definitions of key terms used in the guidance document.
Appendix C - Technical References
Contains a list of helpful technical references to support the information presented in the table.
Appendix D - Example Program(s)
Contains example(s) of how this PSM element has been adopted. Most of the examples are actual programs provided by industrial companies.
PSM TRAINING MATERIAL REFERENCE MANUAL
ABDOO102879
CT>
a> cc
u_
o o> 5 yj >
Ui
QC
LU U_
<
CO
Q_ 3I--
CC
2
CO LLl CC Q_
PSM TRAINING MATERIAL REFERENCE MANUAL
ABDOO102880
CD
O
05
cc
Li.
o
05
CM
<:
UJ
> UccJ LU
LL
< 69 C=>L I--
CC
< h-
C/9 UJ CC CL
ABDOO102881
LIST OF ACRONYMS
AlChE *
American Institute of Chemical Engineers
ANSI *
American National Standards Institute
API *
American Petroleum Institute
ASHRAE * American Society of Heating, Refrigeration and Air-Conditioning Engineers
ASME *
American Society of Mechanical Engineers
ASTM
American Society for Testing and Material
AWS *
American Welding Society
BFD
Block Flow Diagram
CCPS *
Center for Chemical Process Safety
CGA *
Compressed Gas Association
CMA *
Chemical Manufacturers Association
DIERS
Design Institute for Emergency Relief Systems
EPA
Environmental Protection Agency
FEMA
Federal Emergency Management Agency
FMEA
Failure Mode and Effects Analysis
FTA Fault Tree Analysis
HAZOP
Hazard and Operability Study
HHC
Highly Hazardous Chemical
IDLH
Immediately Dangerous to Life and Health
IIAR *
International Institute of Ammonia Refrigeration
ISA Instrument Society of America
8
ABDOO102882
LC LD MSDS NFPA * OSHA P&ID PEL PFD PHA PSM PQV SOCMA SOP STEL
Lethal Concentration Lethal Dose Material Safety Data Sheet National Fire Protection Association Occupational Safety and Health Administration Piping and Instrument Diagram Permissible Exposure Limit Process Flow Diagram Process Hazard Analysis Process Safety Management Program-Quality-Verification Synthetic Organic Chemical Manufacturers Association Standard Operating Procedure Short Term Exposure Limit
* Mailing address and telephone numbers included
9
a a a a a a a a a a a <
i
i
i
g
i
i
ABDOO102883
Referenced Agency Addresses and Phone Numbers
AlChE American institute of Chemical Engineers 345 East 47th Street New York, New York 10017 Phone: 212-705-7338
ANSI American National Standards Institute 11 West 42nd Street New York, New York 10036 Phone: 212-642-4900
ASHRAE American Society of Heating, Refrigerating and Air-Conditioning Engineers 1791 Tullie Circle, N.E. Atlanta, Georgia 30329 Phone: 404-636-8400
ASME American Society of Mechanical Engineers 22 Law Drive P. O. Box 2300 Fairfield, New Jersey 07007-2300 Phone: 800-843-2763
AWS American Welding Society 550 N.W. LeJeune Road Miami, Florida 33126 Phone: 800-443-9353
CCPS Center for Chemical Process Safety of the AlChE 345 East 47th Street New York, New York 10017 Phone: 212-705-7319
10
ABDOO102884
Referenced Agency Addresses and Phone Numbers (Continued)
CGA Compressed Gas Association 1725 Jefferson Davis Highway, Suite 1004 Arlington, Virginia 22202 Phone: 703-412-0900
CMA Chemical Manufacturers Association 2501 M Street, N.W. Washington, D.C. 20037 Phone: 202-887-1100
IIAR International Institute of Ammonia Refrigeration 1101 Connecticut Avenue, N.W., Suite 700 Washington, D.C. 20036 Phone: 202-857-1110
ISA Instrument Society of America 67 Alexander Drive P.O. Box 12277 Research Triangle Park, North Carolina 27709 Phone: 919-549-8411
NFPA National Fire Protection Association 1 Batterymarch Park Quincy, Massachusetts 02169 Phone: 800-344-3555
ABDOO102885
APPENDIX B
Glossary of Terms
12
ABDOO102886
GLOSSARY OF TERMS
BLOCK FLOW DIAGRAM or BFD1 A diagram used to show the major process equipment and interconnecting process flow lines as well as flow rates, stream composition, temperatures, and pressures. The BFD is intended as a simplified diagram.
CHECKLIST2 Detailed list of desired system attributes or steps for a system or operator to perform. Usually written from experience and used to assess the acceptability or status of the system or operation compared to established norms.
CONSEQUENCE2 The direct, undesirable result of an accident sequence usually involving afire, explosion, or release of toxic material. Consequence descriptions may be qualitative or quantitative estimates of the effects of an accident in terms of factors such as health impacts, economic loss, and environmental damage.
DECISION TREES4 Decision trees are a special case of event tree models used to guide the user through multiple questions and provide a course of action based on the outcome of all of the questions. They provide no logical method of choosing the initiating event.
ELECTRICAL ONE-LINE DIAGRAM1 A diagram including legend of the electrical power distribution system that could contribute to a highly hazardous chemical release showing such items as power consumers, the chain of supply back through starters, distribution centers, substations to the main feeder, emergency power supply, and connections to various components. For complex systems, the one-line diagram may be a group of drawings.
FACILITY3 The buildings, containers and equipment that could reasonably participate in a catastrophic release as a result of being physically interconnected or of their proximity and in which dangerous substances are used, stored, manufactured, handled, or moved.
13 /
ABDOO102887
FAILURE MODE AND EFFECTS ANALYSIS or FMEA1 A specifically designed method to identify the conceivable ways that a highly hazardous chemical equipment or its components can fail and the effect of the failure on the system with respect to a release. The failure and effects are determined in a study of updated piping and instrument diagrams that describe the facility taking into consideration process chemistry, standard operating procedures, maintenance procedures, operator job descriptions, process flow diagrams, inventory tabulations, electrical one-line diagrams and other documents. The resulting qualitative analysis is translated into a quantitative FMEA when probabilities of the failure of components are assigned. The results of the FMEA are reported for a unit or system of a facility on an FMEA table. The results are entered on a FMEA table for each equipment item or component studied are as follows: the identification number of the item, the name of the item, the other equipment potentially affected with the equipment identification number and the effect of the failure on that equipment, a classification of the criticality ranking of the failure based on quantity or rate of the potential release, the probability of the failure and the suggested action in terms of equipment or procedure to prevent the failure or to mitigate the results of the failure.
FAULT TREE ANALYSIS or FTA1 The analysis of the logic diagram constructed from a study of the updated piping and instrument diagrams that describe the facility taking into consideration process chemistry, standard operating procedures, maintenance procedures, operator job descriptions, process flow diagrams, inventory tabulations, electrical one-line diagrams and other documents. The logic diagram is called a fault tree and represents a qualitative analysis of the hazards. Results of the FTA are reported for a unit or system on a table. Entered on the table are the descriptions of the various combinations of equipment or procedural failures that can lead to a release. The combinations are determined by solving the fault tree logic diagram for the minimal cut sets, that is, the smallest combination of equipment or procedural failures, which if all occur, will result in the "top event", that is the highly hazardous chemical release. The table is also entered with a criticality ranking based on the quantity or rate of the potential release, a probability for the respective failures and the suggested action in terms of equipment or procedure to prevent the failure or to mitigate the results of the failure. The anafysis of the logic diagram includes the identification of "minimal cut sets." When probabilities are assigned to each element of the event sequence, a qualitative fault tree is obtained which gives the probability or frequency of occurrence of the release.
HAZARD2 An inherent physical or chemical characteristic that has the potential for causing harm to people, property, or the environment.
14
ABDOO102888
HAZARD ANALYSIS1 A systematic identification of the potential conditions that may result in an EHS accident.
HAZARD AND OPERABILITY STUDY or HAZOP1 A systematic study of updating piping and instrument diagrams that describe the highly hazardous chemical facility taking into consideration process chemistry, standard operating procedures, maintenance procedures, operatorjob descriptions, process flow diagrams, chemical inventory tabulations, electrical one-line diagrams and other documents. The study is performed by a multidisciplinary team to identify hazard or operability problems that would result in a highly hazardous chemical accident Deviations from the design value of key parameters (flow, temperature, composition, time, quantity, etc.) of each segment of the highly hazardous chemical facility and its procedures are studied using guide words (such as, more of, less of, none of, part of, more than and other) to control the examination and evaluation. The study team shall consist of trained personnel knowledgeable in the technology and operations, such as process chemistry, the design of the system, the procedures of its operation and maintenance, and the related codes, standards and practices. In addition, the study team shall have technical expertise to answer most questions of the review without resorting to further expertise. The study team shall include a study leader specifically qualified for his or her leadership role by training or previous experience in HAZOP studies and a team secretary who shall record the results of the study. Persons who occupy these team study positions shall be technically trained and be available for the duration of the study. Results of the HAZOP study shall be reported by tabulation for a unit by key equipment, such as vessels or pipelines, and process parameter. The results are entered on the table as follows: guide word, causes of the deviation, consequences of the deviation in terms of a potential release, the criticality based on the quantity or rate of potential release and the suggested action in terms of equipment or procedure to mitigate the deviation.
HIGHLY HAZARDOUS CHEMICAL or HHC3 A substance possessing toxic, reactive, flammable, or explosive properties.
HUMAN ERROR2 Actions by or failures to act on the part of designers, operators, managers, or other individuals that may contribute to or result in accidents.
MATERIAL SAFETY DATA SHEET or MSDS1 A document which describes, at a minimum, the chemical and physical properties and the physical and health hazards of a substance.
15
ABDOO102889
MODIFICATION1 Any change in existing equipment or procedures that would require a change in process safety information and/or operating procedures. Modification does not include routine maintenance or replacement in kind.
OPERATOR2 An individual responsible for monitoring, controlling, and performing other tasks as necessary to accomplish the productive activities of a system. Often used in a generic sense to include people who perform various tasks (e.g.; reading, calibration, maintenance).
PIPING AND INSTRUMENT DIAGRAM or P&ID1 One or more detailed drawings including legends and citations of referenced documents showing: every item of highly hazardous chemical equipment and its identification number {including installed spare equipment); every pipe size, flow direction, identification number and identification of ANSI piping specification and break between piping specifications; symbols and identification of every instrument including instrument function to show trips and interlocks represented in accordance with Instrument Society of America standards or a standard adequate for the conduct of a safety review or hazard analysis with an appropriate symbol legend shown, every valve, the failsafe position, of control valves or non-hand operated valves in the case of instrument air or power failure; steam traps; representation of insulation or heat tracing of piping, highly hazardous chemical equipment and instruments; sizes of all important equipment nozzles with location shown schematically to reflect function and elevation, such as, drains, vents, flushing connections and steam connections; references to inter facing with other diagrams describing process, service, treatment, disposal, or utility systems; data on type, size, and set pressures of every relief valve and relieving device; instruments to monitor early detection of abnormal conditions or a highly hazardous chemical release; where critical, the relative elevations between equipment and of key piping; notes or symbols on such items as slope of critical piping to avoid pockets, or, where critical symmetrical piping; notes on each item of highly hazardous chemical equipment, such as, material of construction, design temperature, design pressure, design thermal duty of heat exchangers, design capacity and dynamic head of rotating equipment, etc.
PRELIMINARY HAZARD ANALYSIS2 A technique that is derived from the U.S. Military Standard System Safety Program Requirements. Focuses in a general way on the hazardous materials and major process areas of a plant, and is often used as a precursor to further hazard analyses.
16
ABDOO102890
PROCESS CHEMISTRY1 The chemical reactions which are relevant to possible scenarios of highly hazardous chemical releases, including information on raw materials, intermediates, products, and waste products.
PROCESS FLOW DIAGRAM or PFD1 A diagram including a legend of a facility which depicts the use, generation, storage or handling of a highly hazardous chemical showing items of equipment (groups of duplicate equipment may be represented by one symbol if desired), flow of material from item to item, simplified basic control loops or major control schemes, points of discharge to the environment, and showing or cross-referencing documents which give details of material balance, flows, raw materials, products, intermediates, treatment chemicals, operating conditions of temperature, pressure and steam characteristics, operating cycles and batch sizes where applicable. A process flow diagram includes, or references, a block flow diagram that depicts the receipt, handling and storage steps at the site of shipping containers of the highly hazardous chemical.
PROCESS SAFETY MANAGEMENT2 The application of management systems to the identification, understanding, and control of process hazards to prevent process-related incidents and injuries.
REPLACEMENT IN KIND1 The replacement of existing highly hazardous chemical equipment with identical or equivalent highly hazardous chemical equipment, and installation according to criteria for design and operation.
RISK2 Combination of the expected frequency (events/year) and the consequence (effects/event) of a single accident or a group of accidents.
STANDARD OPERATING PROCEDURE1 The document setting forth the operating procedures covering all details of the operation involving highly hazardous materials that are currently in effect at the facility.
TRUTH TABLES4 A listing of all combinations of the states of basic events, the resulting occurrence or non-occurrence of a top event, and the corresponding probabilities for the combinations.
17
ABDOO102891
WHAT-1F CHECKLIST1 A method of hazard analysis based on a systematic study of updated piping and instrument diagrams that describe the highly hazardous chemical facility taking into consideration process chemistry, standard operating procedures, maintenance procedures, operator job descriptions, process flow diagrams, inventory tabulations, electrical one-line diagrams and other documents. The study is performed by a multidisciplinary team to identify hazards or operability problems that could result in a highly hazardous chemical accident. The study is composed of a comprehensive list of questions prepared in advance from study of documents by team members either in conference or independently usually corresponding to their individual background. The study team shall consist of trained personnel knowledgeable in the technology and operations, such as process chemistry, the design of the equipment, the procedures of operation and maintenance and the related criteria for design and operation. In addition they shall have technical expertise to answer most of the questions of the review without recourse to further expertise. The team shall include a person assigned to lead the study and a person to record the results who are technically trained and will be available for the duration of the study. Results of the study shall be reported for a unit on a table. The results are entered on the table as follows: the "what if" question and its corresponding consequence/hazard, the criticality based on the quantity or rate of the potential release and the recommended action in terms of equipment or procedure to mitigate the consequence/hazard.
1. New Jersey Toxic Catastrophe Prevention Act, N.J.A.C. 7:31, New Jersey Department of Environmental Protection and Energy, June 18, 1993.
2. Guidelines for Hazard Evaluation Procedures. 2nd. ed., Center for Chemical Process Safety of the American Institute of Chemical Engineers, 1992.
3. Process Safety Management of Highly Hazardous Chemicals, 29 CFR Part 1910.119, Occupational Safety and Health Administration, February 24, 1992.4
4. Reliability Engineering and Risk Assessment. Ernest J. Henley and Hiromitsu Kumamoto, Princeton-Hall, Inc., 1981.
18
ABDOO102892 TECHNICAL REFERENCES PRE-STARTUP SAFETY REVIEW "American National Standard for Equipment Design and Installation of Ammonia Mechanical Refrigeration Systems," ANSI/IIAR-2-1984. "Management Practices, Self-Assessment Process and Resource," API RP 9000. Guidelines for Hazard Evaluation Procedures. 2nd ed., Center for Chemical Process Safety of the American Institute of Chemical Engineers, 1992. Plant Guidelines for Technical Management of Chemical Process Safety. Center for Chemical Process Safety of the American Institute of Chemical Engineers, 1992. WAC 296-67-033 Pre-startup Safety Review WAC 296-67-045 Management of Change
20
ABD00102893
GENERAL REFERENCES
Ammonia Plant Safety (and related facilities), vol. 23, American Institute of Chemical Engineers, 1981.
Ammonia Plant Safety fand related facilities), vol. 24, American Institute of Chemical Engineers, 1984.
Ammonia Plant Safety fand related facilities), vol. 27, American Institute of Chemical Engineers, 1987.
Ammonia Plant Safety fand related facilities). vol. 28, American Institute of Chemical Engineers, 1988.
Ammonia Plant Safety fand related facilities!. vol. 31, American Institute of Chemical Engineers, 1988.
"Guidelines for Safe Automation of Chemical Processes," American Institute of Chemical Engineers, 220p.
"Guidelines for Investigating Chemical Process Incidents," American Institute of Chemical Engineers, 347p.
"Guidelines for Auditing Process Safety Management Systems," American Institute of Chemical Engineers, 136p.
"Management of Process Hazards," American Petroleum Institute, Recommended Practice 750.
"Process Safety Management (Control of Acute Hazards)," CMA.
Chemical Manufacturers Association (CMA's Manager Guide), First Edition, September 1991.
\
"The Revised Field Operations Manual (FOM)," OSHA Instruction CPL 2.54B, June 15, 1989.
"State Plan Policies and Procedures Manual," OSHA Instructions STP 2.22A, Ch-2, January 29, 1990.
"Integrated Management Information Systems (IMIS) Forms Manual, Chapter V " OSHA Instruction ADM 1-1.12B, December 29, 1989.
21
ABDOO102894
"Systems Safety Evaluation of Operations with Catastrophic Potential," OSHA Instruction CPL 2-2.45, September 6, 1988. "Process Safety Management Guidelines for Compliance," OSHA 3133; U.S. DOL, 1992. "Process Safety Management," OSHA 3132; U.S. DOL, 1992. "Safety and Health Program Management Guidelines," U.S. DOL, 1989. "Review of Emergency Systems," June 1988; U.S. EPA, Office of Solid Waste and Emergency Response, Washington DC 20480. "Chemical Exposure Index," Dow Chemical Co., May 1988. "Accident Investigation * * * A New Approach," National Safety Council, 1983. Process Safety Management Resources from the American Institute of Chemical Engineers for Use by Industrial Hygienists. James A. Gideon and Thomas W. Carmody, American Industrial Hygiene Association Journal (53), June 1992. "Improving Construction Safety Performance," Report A-3, The Business Roundtable. "Recommended Guidelines for Contractor Safety and Health," Texas Chemical Council. "Loss Prevention in the Process Industries," Volumes I and II, Frank P. Lees, Butterworth, 1983. "Guidelines for Engineering Design for Process Safety," 500p.
22
ABDOO102895
APPENDIX D
Example Programs
The following examples illustrate approaches taken by companies seeking to address the Pre-startup Safety Review requirements of 29 CFR 1910.119. These examples have not been reviewed and/or endorsed by OSHA and should not be construed as model programs. Primatech makes no claims regarding the acceptability to OSHA of the information contained herein. The example programs provided herein were developed for specific processes, and are not generic in nature. Since the OSHA PSM regulation is performance-based, readers are strongly encouraged to develop programs tailored to their own covered processes.
CONTENTS D-1 Pre-startup safety review procedures - ammonia refrigeration system D-2 Pre-startup safety review procedures - petroleum refinery
23
ABDOO102896
I
D-1 Pre-startup Safety Review Procedures - Ammonia Refrigeration System
The following example contains a pre-startup safety review program for an ammonia refrigeration facility. The program includes typical safety review team personnel, safety review procedures and a pre-startup review report to ensure a safe startup and operation of the facility.
24
ABDOO102897
i PRE-STARTUP SAFETY REVIEW PROCEDURES
Ammonia Refrigeration System
TABLE OF CONTENTS
Page
1.0 SUMMARY........................................................................................................................... 1 2.0 SAFETY REVIEW TEAM .................................................................................................. 2 3.0 PRE-STARTUP SAFETY REVIEW PROCEDURES..................................................... 3 4.0 PRE-STARTUP SAFETY REVIEW DOCUMENTATION............................................. 5
APPENDIX A PRE-STARTUP SAFETY REVIEW REPORT
ABDOO102898
I
11 1.0 SUMMARY
Pre-startup safety reviews should be conducted for the ammonia refrigeration system I prior to the introduction of ammonia into the refrigeration facility. The pre-startup safety
reviews are conducted for new facilities and for modifications to the existing ammonia 1 refrigeration facility where the modifications require a change in either the equipment
design basis or the technical design basis. Pre-startup safety reviews are not required 1 for replacements in kind.
1 The objective of pre-startup safety reviews is to ensure that the following items have been addressed prior to the introduction of ammonia into the refrigeration system:
Construction is in accordance with specifications; | Appropriate testing and inspections have been performed;
Safety, operating, maintenance, and emergency procedures are in place and
j adequate;
Process hazard analysis recommendations have been addressed and actions ] required for startup have been completed; and
Operating procedures are in place and training of personnel has been completed.
The site maintenance supervisor has the responsibility to ensure that the pre-startup safety reviews are conducted.
ABDOO102899
2 2.0 SAFETY REVIEW TEAM
The pre-startup safety review should be conducted by a team who by reason of knowledge, training and experience are competent for ine review. Such persons typically include:
In-house design/engineeiing staff such as the site maintenance supervisor or the regional engineer;
Experienced refrigeration contractors, possibly in combination with an engineering code authority, authorized inspection agency or property insurance underwriter;
Consulting engineers; and The refrigeration equipment supplier.
ABDOO102900
3 3.0 PRE-STARTUP SAFETY REVIEW PROCEDURES
Pre-startup safety reviews are conducted for new facilities and for modifications to the existing ammonia refrigeration facility where the modifications require a change in either the equipment design basis or the technical design basis. They are to be conducted prior to the introduction of ammonia into the refrigeration system.
The first step in performing a pre-startup safety review is to complete the requirements of the quality assurance program. The purpose of the quality assurance program is to ensure that the critical equipment handling ammonia is fabricated to meet design specifications and that appropriate checks and inspections are conducted to ensure the equipment is installed properly. The specific procedures involved with the quality assurance program are contained in a separate document.
The technical basis for process design and the equipment design basis should be reviewed and updated as necessary as part of the pre-startup safety review procedure. This process involves a review of the following drawings and documentation:
Process description and chemistry: Process flow sheets; Piping and instrumentation diagrams; Facility site plans and equipment layout; Ammonia inventory; Operating limits for key process variables; Ammonia refrigeration equipment list; and Ammonia refrigeration safety systems list.
The pre-startup safety review also involves a review of the following policies and procedures to ensure that they are in place, adequate, and have been updated to reflect any modifications to the ammonia refrigeration system:
ABDOO102901
4 Operating procedures; Hot work permit procedures; Lockout and/or tagout procedures; Maintenance procedures; and Emergency procedures.
One of the requirements involved in the startup of a new facility or modifications to the existing facility is to conduct a process hazards analysis to identify, evaluate and control the hazards associated with the process. The pre-startup safety review documents that the recommendations from the process hazard analysis have been addressed and that the actions required for startup have been completed.
Finally, the pre-startup safety review will document that all necessary personnel are informed of the modification and have been trained in accordance with any new or revised operating procedures.
Any deficiencies in the Process Safety Management (PSM) Program identified during the pre-startup safety review will be immediately documented and brought to the attention of the site maintenance supervisor. Corrective actions for these deficiencies must be completed prior to the introduction of ammonia into the refrigeration system.
ABDOO102902
5 4.0 PRE-STARTUP SAFETY REVIEW DOCUMENTATION
The report contained in Appendix A will be completed as part of the pre-startup safety review. This report includes:
An identification of the safety review team members; A list of the questions addressed during the safety review; and A list of deficiencies in the Process Safety Management Program identified during
the safety review and corrective actions taken.
ABDOO102903
i i i
i
ABDOO102904
Prim atech Inc
W orksheet
>.
u 0
co
>. c
--0a>
aa u oc
ma
i "E
>c. *>-<.
n --
un
AUDIT-PC 1.52
ABDOO102905
System: Page:
Company: S m ith 's Company
F a c ilit y : Ammonia R e frig e ra tio n F a c ilit y
4>1 341 ee -->
3?
--~ o KUO!
ItAllAV w4)
a "o
-- 4)
Ot ^<0
6o> 3Cl
4) U *>
J (A
ot-
>.
>.
tn
CL t-
c
4) O 4J U> -- -- W
~ E re
41 a> M
(A *> o
W3O alO.l *u-< z^ clo-oi
a 4i n s
/> T) ~ C ~U
i/i 4> O
3L 1 L
<j o <- c
o --> o O 4> l_ O
Q..Z _TJ --> </*>>* ~
41 OU ^'O--*v--' --C
DTI-> -- TO QE 44)17
4J Q. 41
mo> t- 3 rEe (A 34i CE
z 'v c + -- 3
"D 4) </> > --.
C 41
41O
<nj re .Q v> --' u
CE
5 *- 4)
>.</>
"H JlTi.S
a aoi v *-< *o
pi --
o )
C t> OZ 3
re 4>
a-- 4 M 41 s
~ u C t-
41 O
O --.
O
O
fc 4C) -**re* M O
U *Q U E v> > 3 4i-- a j*
a l -<*.(_ t_
wa: ** "rbe*--o erre> Ere
n - 5 I r l
IV V
41 "O --
4) *4(D1* *O->
5CI*83.1
O ti k 3V) *U>
4C1 --4)
--o
O 4> r-
3 -O ?
u tA C
4v> e g M O
_ ca
o m re c -<
3
1?
C
'5.
mre
3re
*c5
So.
*t/i1 40
**
4) > re
sre kre.
c
tn rae
AUDIT-PC T.52
Worksheet
Primatech Inc
ABDOO102906
wa
M CL
>s
a ac oc -- o
>-- aw ee a
va ac --o>
uo oac ifi a jz E
ua
a
(w/) iO/il
C a -- - * a. a
XX
cw a--
tz
g*t
-- w o
(A
1U/1
W(xA wOa)
</>
a aw
wo
-- XW
v> a o
x -- --a
cag
= ic-- c a o -- a
aUa ----0.*w0j
a? a
o a
g-TJ a a a -- o
o 1f W
w `n a
C TJ
a a a.
aw
xcc
a a (A CA
o
O..Q
X-- (A --'
2oTa
-
2- --a p~ a a*- co
i. --
5C o Wa
alr o
iA 3 e
IA "O
oc> a(Awa
-- ua w o *b 2 &.-
&Xc
o a a IA
.* a
JaZ L. .o
a
g
w O h- a
a --> > in ji
*a w --a
E l. -- a
a-- >
cu
a r-- CA _>- c --ao C *" w
^aoa
a o *o < -- a --
a w w *o
.~e afca i6
in 0)3 E
a--
a
re i_ C w
w a <a
aa x
O- L ^ VI
w -- f*.
<A (A xa c (A L. O
'a "2 '>w ia w --
ms*
wa c2
i.aw
a a a (A a o .a x
*
i i
I I I I I I I r i r
I
( t
ABDOO102907
Prim atech Inc.
W orksheet
>4) 34)
DC --
Of 41 O a.
2*8
l. a
4. --' O a
--(<4AA> (>/A. oO41)
3<0 4>
410".C
*D
<0
U
f*`
co
<(J0
"4D .<Ou0
Q IC/) >.
o(0 A4c411
"4C3/ 4Cc^A
</> (4A/ oC uc3 ^ "O
T-~[i3C&a(43Cn_3s.)..xTrH*4i0C44~-nJi1>>) OO (4A1
UOuH"CRD
A 4>
.a3O* .~Co AQl
T*S<2c4r>>a0J'-ir.--h**o<14a-->J>>-*
vco*(A-
o a? .4W3Ouo. A41
41
OTJ U
tl Q '
AUDIT-PC 1.52
Company: S m ith 's Company
System:
Company: S m ith 's Company
F a c ility : Amnonia R e frig e ra tio n f a c ilit y
System: Page:
ABDUU1Q29Q9
ABD00102910 14
D-2 Pre-startup Safety Review Procedures - Petroleum Refinery The following example contains a pr^-startup safety review program for a refinery. The program includes safety review procedures, a pre-startup safety review index, a saiety review findings summary report and a checklist used for new or modified facilities.
ABDOO102911
PROCESS SAFETY MANAGEMENT POLICIES & PROCEDURES
NO. Page 1 of 27 Revised November 23, 1993
PRE-STARTUP SAFETY REVIEW
I. POLICY:
It is the policy
to conduct Pre-Startup Safety
Reviews of all newly constructed process units and equipment
and all unit and equipment modifications where the modifi
cation is significant enough to require a change in the
process safety information. These reviews will be performed
to insure that new and modified equipment are ready and safe
for startup.
II. SCOPE:
This policy applies to all new
Processes and modifica
tions to existing Process Equipment significant enough to
require a change in the Process Safety Information.
III. PURPOSE:
The purpose of the Pre-Startup Safety Review is sevenfold:
1. To confirm that construction and equipment have been
installed in accordance with design specifications and in
accordance with applicable Federal, Territorial Codes and
Standards and
Engineering Standards and Safety
Policies;
2. To confirm that Safety, Operating, Maintenance and Emergency Procedures are in place and are adequate;
3. To confirm that a Process Hazard Analysis has been done for new facilities and that recommendations from the PHA have been resolved-or implemented before Startup;
4. To confirm that modified facilities meet the requirements in the Management of Change Policy;5
5. To confirm that the training on operating procedures for each employee involved in operating the Process has been completed;
ABD00102912
NO. Page 2 of 27 Revised November 23, 1993
6. To confirm that all Maintenance and Contractor Personnel affected by the new installation or modified facilities have received the required training.
7. To insure that all warnings, markings, labels, signs and required safety equipment (i.e., fire extinguishers, flange shields, safety showers, Scott Air Paks, etc.) are installed; and
8. To insure that the equipment is safe for startup and continued operation.
IV. PROCEDURE:
1. The Pre-Startup Safety Review is mandatory on all new installations or on modifications requiring Management of Change Procedures (MOC) where there is a change in the process safety information.
2. The Equipment Owner (Operations/Terminal/Powerhouse/Area Manager) is responsible to ensure that a Pre-Startup Safety Review is conducted. The completed PSSR must be reviewed by the Area Manager and then approved prior to operation of the equipment.
3. Pre-Startup Safety Reviews should not be conducted until the new facility or modification is mechanically com plete. The Pre-Startup Safety Review is not intended to be used to obtain a final punch list of items for mechan ical completion of the job.4
4. The review for small projects and minor modifications may be conducted by two persons, an "A" or "BM Operator and an Operations' Supervisor. For large projects the review should be conducted by * team of three or four people. The Operations/Terminal ; owerhouse Manager will determine the team members required. Normally for large projects the team will consist of the Area Manager or Superin tendent, an "A" or "B" Operator who will be operating the equipment, the Maintenance/Construction Supervisor assigned to the .job, and a representative from the Technical Services Department (generally the Project Engineer).
ABD00102913
NO. Page 3 of 27 Revised November 23, 1993
All Pre-Startup Safety Reviews should be conducted using the attached checklist for new or modified facilities. This checklist has been prepared to organize and simplify the review. In conducting the review, you may have to check items not on the list. In many cases there will be items on the list not pertinent to the project under review. An index page has been provided so that items which do not apply can be checked off without going through the entire review checklist.
The Pre-Startup Safety Review Checklist has been divided into eighteen (18) separate lists. The first three (3) lists shall be completed for all reviews. Only the lists from four to eighteen (4 - 18) marked off on the index page as applicable to this particular project need be completed.
All checklist items marked as "NO" shall be identified on, and have the intended or corrective action entered onto the PSSR Findings Summary Report (Attachment "C").
If a Pre-Startup Safety Review with incomplete or un resolved items is approved by the Safety Manager, which may be the case if the nature of the open items are such that operations can proceed, a copy of the deficiencies will remain in the Safety Department.
The Equipment Owner/Area manager will be responsible fcr any follow-up indicated by the review. Tracking will be by the PSM Automated Tracking System.
Monthly updates on unresolved recommendations will be completed by the Area Manager and submitted to the Safety Department.
The original copy of the Pre-Startup Safety Review will be maintained in the Process Safety Management Library with the project file. A Xerox copy will be maintained by the Equipment Owner.
PSSR #___________________
(Assigned by Safety Dept.)
"WR " __________________________
WORK REQUEST #
ABD00102914
NO. Page 4 of 27
"
Attachment "A"
Project # ________
November 23. 1993
PRE-STARTUP SAFETY REVIEW
UNIT: _______________________________________________________ TITLE: _______________________________________________________ BRIEF DESCRIPTION: (Include Process Description Changes)
INSPECTION TEAM
Operations/Terrmnai Area Superintendent or Manager Mecnamcal Supervisor Project Engineer
Operator
DATE: DATE: LATE:
SUBMITTED BY: REVIEWED BY: APPROVED BY:
(learn i-caaer; (Operations Mg:.; gaiety .vigr.j
NOTE:
Start-up of this equipment is approved prior to completion of the open items, except as noted with an * on the summary sheet.
ALL OPEN ITEMS HAVE BEEN COMPLETED:
Ooerauons/Terxnmai Manager
Date
cc: PSM Central Files (original) Area Manager
ABD00102915
NO.
Page 5 of 27 "
Attachment "B" November 23. 1993
PRE-STARTUP SAFETY REVIEW INDEX
YES
NO
Operating and Emergency Procedures and Training Fire Protection and Safety Equipment General Piping and Piping Supports Vessels and Exchangers Safety Valves Blowdown. Flare and Pumpout Systems Machinery - Pumps, Compressors, etc. Electrical Instrumentation Structural Access Ways Furnaces Tank Farms and Pump Slabs Sewers and Separators Cooling Towers Materials Handling Manlifts. Passenger and Freight Elevators Other Safety Hazards (to be added by Team if necessary):
2c x X
!
ABD00102916
Project Unit #: __ Team Leaden ___Date:
Pre-Startup Safety Review Findings Summary Report
NO. Page 6 of27T Attachment "C" November 23, 1993
Each item identified on the PSSR as a "No" is a deficiency item that must be listed on the table below. Please enter in all the requested information in each cell of the table. The Package and Item numbers will come from the PSSR checklist used for the review. The deficiency statements and recommendations will be numbered sequentially by the PSSR Team in the order they determine. The Team Leader is responsible to have this form completed prior to the team sign-off on the PSSR cover sheet.
Def. Pkg Item # ##
Deficiency Statement
Recomm. Prior To Startup
Item Item Complete OK (Date)
Checked By
(Name)
1
2
3
4
5
6
7
8
9
10
11
|
12
13
14
sbkl56
Project Unit#: Team Leaden Date:
ABD00102917
Page 2
Pre-Startup Safety Review Findings Summary Report
NO. Page 7 o2T Attachment "C" November 23, 1993
Def. Pkg Item U ##
15
16
17
18 19 1
! 20
21
22
23 i
24
25 i
26 !
27
28
29
30
Deficiency Statement
Recomnu Prior To Startup
Item Item Complete OK (Date)
Checked By
(Name)
sbkl56
Project Unit#: Team Leader:
Date: (Initials)
ABD00102918
NO.
'
Page 8 of 2/~
Attachment "D" November 23. 1993
PACKAGE NO. 1 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
This checklist has been prepared as a convenience for those performing safety reviews of new or
modified equipment. It is not intended to be a list that will catch all possible safety hazards.
Therefore, those using it should be on the alert for other safety deficiencies. It is anticipated
that this checklist could be improved upon, and each user is encouraged to make recommendations
for its improvement.
PSM CHECKLIST
YES
NO
N/A
1. Operating and Emergency Procedures and Training:
a. Have operating procedures been developed, distributed and communicated to all affected Operations' personnel?
b. ` Have all affected operators been trained on these procedures?
1| j
:
.j ._______ ;
c. Has appropriate training been conducted on the new equipment fcr all unit qualified operators?
I| j________ i
d. Have revisions/updates been made to the master copies of the operating manual?
j I j_______ ____
e. Do these procedures include start-up, shutdown, and emergency procedures as well as procedures for normal operations.
Ij 1_______ ____
f. Have criticial instruments been identified and have inspection, testing and preventive maintenance schedules been set u: for said instruments?
lj i_______ ___
g. Comments:2 3 4
i
i
i i
i i
i
*
i
i
1
2. Has equipment been installed in accordance with design specifications?
3. Has all the required Process Hazard Analysis work been completed?
a. Have all recommendations from the PHA been resolved?
b. Have all the recommendations required prior to startup of the process equipment been implemented?
4. For modified facilities, have all actions required by Management of Change Procedure been followed?
i
ir
i
i
i
ABD00102919
Project Unit #: Team Leader:
____________________
NO.
Page 9 of 27~
Date:Attachment "D"
(Initials)
"
November 23. 1993
PACKAGE NO. 2
CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Fire Protection and Safety Equipment
YES
NO
N/A
a. Are an adequate number (as designated by the Fire
Department) of the proper type of fire extinguishers located throughout the unit?
|| |j !
b. Are fire extinguisher stations properly noted with red paint and extinguisher identification numbers?
_______ |
| j____
c. Are Scott Air Paks located throughout the unit in accordance with design specifications?
_______ ! |
I____
d. Are monitor nozzles strategically located throughout the unit? Do they work?
_______ |
e. Are fire hydrants positioned strategically around the edge of the unit?
| Ij ____
f. Has the Fire Chief inspected all new fire fighting equipment installations?
_______ Ij '
g. Have new fire water lines been hvdrotested and are they currently in service?
|________ jI
h. Have start-up and shutdown utilities been provided?
_______ | |
1 ___
i. Is installation complete on any utility station which is required?
jj |I !
j. Are there an adequate number of safety showers and
| \ |1
eye wash stations located in the unit, and are they
properly identified? Are safety showers and eye wash
stations in good working order? Is access to all safety
showers and eye wash stations unobstructed?
k. Are adequate warning signs posted for noise. H2S, thermal expansion, hand traps, etc.?
_______ j i
1i
l. Have sprinkler and deluge systems been tested and found to be operational? Have these systems been approved by the Fire Chief?
|j
m. Have H2S and Hydrocarbon detectors been calibrated, tested and operational?
_______ ij j
n. Has all miscellaneous debris and construction material been cleaned up and removed?
_______ jj I
Project Unit it: Team Leader:
Date: (Initials)
ABDOO102920
NO. Page 10 of 2T^ Attachment "D" November 23. 1993
PACKAGE NO. 3 CHECEI.IST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
General
a. Are valve boxes properly guarded, and have valves rising out of the ground been avoided?
b. Have sewer gratings been properly fitted in catch basins and trenches?
c. Have sewers been flushed and commissioned?
d. Is drainage adequate in all areas?
e. Have adequate steps been taken to avoid slipping hazards, such as water flowing across walking surfaces which could cause algae growth?
f. Have adequate precautions been taken to avoid stumbling hazards, such as pipelines running along the ground or slabs?
g. Have abandoned foundations and supports been removed to avoid stumbling hazards?
h. Is equipment identified by name or number?
i. Has equipment been properly painted to protect from corrosion and/or to identify piping?
j. Has the area been cleared of litter such as bottles, cans, other trash, etc.?
k. Have all leftover materials su::- as scaffolds, tools, nuts, bolts, gaskets, pipe, instruments, etc., been removed from the job site?
l. Have all gas cylinders either been removed or properly stored if left on-r:e?
m. Are all MSDS documents available for all chemicals, products and materials handled, stored or processed at the unit. Have all new chemicals, products and materials been approved per the Introduction of New Chemicals Procedure and Form.
YES |j
NO |
________ j |
|j i| ;'
| | 1
|i |
j! j i |1 j ji i I|
ill _______ | [
Project Unit #: Team Leader:
Date: (Initials)
NO. Page H of 27"** Attachment "D" November 23, 1993
PACKAGE NO. 4 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Piping and Piping Supports
a. Has piping been adequately protected for external corrosion (cathodic protection, wrapped, etc.)?
b. Is piping free of excessive wind sway?
c. Has insulation been properly applied for personnel protection from contact thermal bums?
d. Have pipe supports been securely attached with allowance for pipe movement where needed?
e. Have adequate provisions been made to avoid venting or draining flammable materials?
f. Do steam lines discharging into process equipment contain at least a check valve for back flow protection?
g. Are valve wheels and valve stems oriented properly to prevent obstruction and provide adequate access for operation?
h. Are control valve manifold drain valves adequately provided?i.
i. Are all flange bolts long enough (threads extend outside the nuts)?
j. Have flange ratings been checked?
k. Have unnecessary drains and vents been avoided?
1. Have all drain and vent valves been properly equipped with bull plugs or thread protection nipples or blind flanges as applicable?
YES _______
NO N/A ||
_______
_______ | |
| | " j[
| || |( | ]| || I I I l|
Project Unit tt:
Team Leader:
________________ (Initials)
ABDOO102922 Dale:
NO. Page 12 of 2" Attachment "D November 22.
PACKAGE NO. 4 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Piping and Piping Supports fCont'd.l
m. Has piping been hydrostatically tested?
n. Have alloy and stainless lines been 100% x-rayed as required?
o. Have alloy lines been stress relieved as required?
p. Are all gaskets of proper size and type?
q. Have all small piping connections in potential vibrating service been gusseted as required to provide adequate strength?
r. Are small piping connections in process service seal welded to the first block valve?
s. Have sample points been provided where necessary?
t. Is steam tracing properly "trapped" andinsulated?
u. Have blinding lists been prepared and included with procedures to .afelv isolating ecuioment for maintenance?
YES
NO
[ \___ _______ I___ j'
Project Unit Team Leader:
ABD00102923-
(Initials)
Date:
NO. Page 13 of 2 r Attachment "D" November 23. 1993
PACKAGE NO. 5 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Vessels and Exchangers
a. Have both the exterior and interior of vessel skirts been fireproofed whenever applicable?
b. Has insulation for personnel protection been installed?
c. Are all vessel small piping connections in accordance with engineering standards?
d. Do vessel skirts have adequate ventilation?
e. Is there a high point vent to remove air and a low spot drain to remove water during start-up? Are they seal welded?
f Have small piping "Christmas Trees" been avoided?
g. Have small piping connections been properly gusseted, and are all 3/4" in size or larger?
h. Is there sufficient access for maintenance and removal of exchanger for heds and channels?
i. Is there sufficient access for maintenance and removal of exchanger for heads and channels?
j. Have permanent gaskets been checked on nozzles, manways, and bridles of towers, drums, and strippers?
k. Have permanent gaskets been checked on exchangers and fin fan nozzles?l.
l. Has all hydrotesting been completed?
YES
NO
N/A
Project Unit #: Team Leader:
(initials)
ABDOO102924 Date:
NO. Page 14 o: 2" Attachmer.: "C" November 22. 1993
PACKAGE NO. 6 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Safety Valves
a. Are safety valves identified with a safety valve # , set pressure, and test date?
b. Have existing safety valves been checked to ensure they are adequate for any changes in service or operating conditions?
c. Can the valve be reached without the use of a crane and personnel lift-basket for checking of tags and seals?
d. Can the valve be readily lowered to grade safely with either portable or permanent rigging equipment?
e. Does the inlet line appear adequate to avoid restricung flow to the safety valve?
f. Have inlet and outlet block valves of PSV's been chain locked open? (a checklist should be on hand)
Oo ' Is safety valve inlet and outlet piping properly supported to avoid undue stresses on the safety valve?
h. When applicable, have snuffing steam ...nes been provided for safety valve stacks?
i. Are block valves -.riented to prevent gates from dropping in the lice?
j- Have drain and vent valves been installed to depressure for safety valve removal?
k. Do safety valve stacks have drains to remove water or liquid accumulation?
1. Are bellows safety valve vents piped to a location where the vent does not impinge on a flange, bolting, personnel, or pipeline?
YES
NO
i
ii I'
i i
>i
i i |
N/A 1
Project Unit #: Team Leader:
ABDOO102925
(Initials)
Date:
NO. Page 15 of 2/ * Attachment "C" November 23, 1993
PACKAGE NO. 6 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Safety Valves (Cont'd.)
m. Are all bleeders and small connections on lines to and from SVs seal welded?
n. For safety valves in heavy oil service: Is the inlet line stream traced and insulated, and if so, is the valve body steam traced and blanketed?
o. Have Operations PSV carlock checklists been modified or generated for this unit or equipment?
Comments:
YES
NO
N/A
Project Unit *: Team Leader:
(initials)
ABDOO102926 Date:
NO. Page 16 of 27 ' Attachment "D" November 23, 1993
PACKAGE NO. 7 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Blowdown. Flare and Pumpout Systems
a. Are headers free of trapped sections?
b. Are all valves chain locked open as necessary? (Lists should be on hand)
c. Have block valves in pressure relieving systems been installed with stems in horizontal position to guard against a dropping gate into the line, or has consideration been given to using x-rays for same?
d. Has pumpout been designed for emergency, as well as routing shutdown conditions?
Comments:
YES
NO
N/A
Proiect Unit Team Leader:
(Initials)
ABDOO102927 Date:
NO. Page 17 of 27 ' Attachment "C" November 23. 1993
PACKAGE NO. 8 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Rotating Equipment
a. Are small piping connections in process service seal welded and gusseted?
b. Have "Christmas Trees" been avoided in small piping connections?
c. Is piping adequately supported to equipment and can it be removed for maintenance without undue piping stresses being developed?
d. Have coupling guards been installed and are they adequate for personnel protection?
e. Have general equipment guards been provided?
f. Are all flange bolts long enough (threads extend outside the nuts)?
Has personnel protection insulation been installed as required?
h. Have warning signs (noise, hand trap, toxic, chemicals, etc.), been properly posted?
Comments:
YES
NO
N/A
|_______
I| j -
_______ I]
!
Project Unit #: Team Leader:
ABDOO102928 _______________
NO.
Page 18 of
Date:___________________________________
(Initials)
November;:'.
i Attachment "
PACKAGE NO. 9 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Electrical a. Is conduit properly supported?
YES
NO
NA
b. Are guards, lighting fixtures, etc., properly supported?
c. Are local start-stop switches properly marked for On/Off and have been equipped with proper identification for the equipment they control?
d. Are local switch handles equipped with proper identification and on/off markings?
e. Are disconnect switches properly identified in the substation?
f. Is lighting adequate in all areas?
g. Is emergency lighting provided? Operational? h. Is all electrical equipment grounded?
i
i. Are established electrical classifications complied with (conduit sealed and conduit covers installed)?
j. Is permanent equipment hooked up with proper electrical cable rather than cords?
k. Are above ground cable runs or trays and conduit fire-proofed as required?
l. Are automatic control and isolation valves properly identified?
m. Can emergency automatic isolation valves be activated without exposing personnel to hazardous atmospheres in an emergency involving the equipment they are installed to isolate?
m. Are automatic control and isolation valve switches properly identified?
n. Are aircraft warning lights operable?
Comments:
i
Project Unit
I
Team Leader:
!
(Initials)
ABDOO102929 Date:
NO. Page 19 of 2T"^~ Attachment "D" November 23. 1993
PACKAGE NO. 10
1 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Instrumentation
YES
NO
N/A
a. , Is there proper access to all instruments so necessary maintenance can be performed?
b. Have bleeder valves been installed as required in control valve manifolds?
c. Are drain and depressuring valves installed on instrument installations for maintenance work?
d. Have control valves been properly identified?
|| 1i
|i
L^__ ________j j
'
_______ _______i 1j
_______ Ii !
!
e. Have switches, transmitters and instrument controls been identified?
j j1 jj
f. Are the spare taps on orifice flanges plugged and seal welded?
g. Does each control valve have a bypass?
h. Are instrument air lines and process tubing properly supported?
i. Are instruments fireproofed as necessary?
j. Is steam tracing on instrument leads properly trapped?
k. Do all process temperature measuring devices have thermowells?
l. Have instruments been checked for fail-safe?
m. Have "critical instrument" procedures been identified, tested and placed in a preventive inspection and maintenance program?
n. Have DCS and PLC shutdown systems been tested and found operational?
o. Have all panel arms been checked?
p. Have all ASD's been checked?
1 ij |1
| jI I! _______ I| !j
_______ | !j j|
_______ jj |I
| || I
I
_______ 1
} |j
_______ 1 I| |j
| 1_______ j
j
|| IJ I I i1 I
________ | ~
Project Unit #:
Team Leader:
"
(Initials)
ABDOO102930 Date:__________________
NO. Page 20 of 2"
Attachment "0 November 23.
PACKAGE NO. 11 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Structural
a. Have structural members been fireproofed as required by engineering standard?
b. Have drain holes been drilled in floor plates as necessary to prevent corrosion and water accumulation?
c. Are openings in floor (plate, grating or slab) for piping vessels, etc., in accordance with OSHA standards?
d. Are ladders installed in such a manner that adequate toe clearance exists between the backside of ladder rings and the nearest objects?
e. Have safety chains or gates been installed across the top entrances to all escape ladders?
Are handrails, ladder rails, etc., free of any abrupt "finger-catchers"?
Do guy wires have equal tension, and are they free from sagging?
h. Are guys protected from corrosion with a grease coating or other suitable protection?i.
i. Are guys, cables and tumbuckle rods properly marked as necessary to warn vehicular and pedestrian traffic of their presence?
YES
NO
'Project Unit Team Leader:
(Initials)
ABDOO102931 Date:
NO. Page 21 of 27~ Attachment "D" November 23, 1993
PACKAGE NO. 12 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Access Wavs
a. Is there more than one route of escape for any sizeable work area and/or platform?
b. Do ladders extend not more than 30 feet in height and have a break or offset as required?
c. Are access routes clear of piping, valves, head knockers (less than seven feet vertical clearance), or tripping hazards?
d. Are access routes free from debris, construction material, hoses, etc.?
e. Are ladders caged when extending over 20 feet in height, or when a person might fall more than 20 feet from a ladder to some other platform, or to the ground?
f. Are areas directly under stairways, ladders or catwalks free of catch basins or sewer manways?
Comments:
YES
NO
N/A
_______ ___________ j_______
_______ _______ j____
_______ ______ J
Project Unit #:
Team Leader:
Date: (Initials)
ABDOO102932
NO. Page 22 o: 2" Attachment "I November 2^
PACKAGE NO. 13 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Heaters
a. Are all peepholes and access doors in good condition and capable of being closed properly?
b. Are purging steam connections adequate with valves located remote from the furnace?
c. If purging steam is controlled by an automatic control valve, is its location remote and manual block present to permit testing of the automatic control valve?
d. Can fuel gas be blocked from a remote location?
e. Have proper design standards been followed with respect to pressure letdown and control of fuel flow?
f. Is access to pass balancing valves satisfactory?
g. Is platforming adequate for servicing instrumentation, air preheater equipment, etc.?
h. If applicable, are noise signs posted to warn that proper hearing protection must be worn?
YES _______
NO |
_______ |
[ I [__
* Project Unit Team Leader:
(initials)
ABDOO102933 Date:
NO. Page 23 of 27^ Attachment "D" November 23. 1993
PACKAGE NO. 14 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Tank Farms and Pump Slabs
a. Axe pumps and tanks properly numbered? b. Are "remote operated" signs posted whenever
appropriate? c. Are fire walls in good condition?
d. Have ramps and steps been provided over fire walls?
e. Have fire wall drain valves been provided along with safe access to the drain valve?
f. Is the catch basin inside the fire wall properly located?
g. Has the surface inside the fire wall been properly graded toward the catch basin?
h. Does the tank water drawoff and drain extend to the catch basin?
i. Is the stairway firewalk access in good condition?
j. Are safety signs prominently displayed and legible regarding N2 blanketing or the possible presence of H2S. or other hazardous materials in the vapor space?
k. Are fire fighting facilities in place, tested and fully operational? Have new fire fighting facilities been approved by the Fire Chief?
Comments:
YES
NO
_______ 1
_______ \
N/A
j|
Project Unit Team Leader:
(Initials)
ABDOO102934 Date:
NO. Page 24 of 2 -' ~ Attachment November 23. 1993
PACKAGE NO. 15 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Sewers and Separators
a. Have sewers been flushed and checked for pluggage?
b. Are manhole covers of adequate strength to support, and is its fit sufficient to prevent excessive vapor leakages?
c. A.re catch basin drain and trench covers of adequate strength without being a stumbling hazard? Are all covers in place?
d. Are manholes vented when at the high point in a lateral?
e. Have flame arrestors h-i-ea checked for pluggage?
f. Is the separator cover of adequate strength?
g. Is the separator cover sealed if toxic vapors are expected to be present in the separator?
h. Has a simplified sewer map been provided for use by operating personnel?
Comments:
YES
NO
N/A
_______ _______ ____
| _______ ____
1 | |_______ ____
Project Unit #: Team Leader:
(initials)
Date:
NO. Page 25 of 27 ' Attachment "D" November 23. 1993
PACKAGE NO. 16 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Cooling Towers
a. Does the casing appear to be structurally sound?
b. Are stairwavs stable and free of debris? c. Is decking free of holes that could cause stumbling?
d. Are fan stacks free of vibration?
e. Can fan assemblies be safely operated and maintained?
f. Are fire protection facilities for the cooling tower adequate?
Can chemical injection equipment be safely operated and maintained?
h. Is control of basin water level adequate, and is there an adequate warning system for impending low level?
Comments:
YES
NO
N/A
[ _______ | j
_______ _______ | |
_______ f______
ji ||
Project Unit Team Leader:
(Initials)
ABD00102936 Date:
NO. Page 26 of 27"" Attachment "D November 22.
PACKAGE NO. 17 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Materials Handling
a. Have davits been installed as required for handling manways, trays, ziz \
b. Do chain hoists have properly posted load limit signs?
c. Is the area clear of obstructions that prevent safe use of hoists, davits, rigging machines, etc.?
d. Have personnel been properly instructed in the use of forklift trucks (if used in the operations)?
Comments:
YES
NO |
N/A (
Project Unit #: Team Leader:
Date: (Initials)
NO. Page 27 of 27"- ^ Attachment "D" November 23, 1993
PACKAGE NO. 18 CHECKLIST FOR NEW OR MODIFIED FACILITIES
PRE-STARTUP SAFETY REVIEW
Manlifts. Passenger and Freight Elevators
a. Have procedures been set up for routine maintenance, inspection and recordkeeping?
b. Are warning signs and operating instructions properly posted?
c. Are trip devices operable?
Comments:
YRS
KO n/A I!