Request For Capital xExpendltures/Retirements DIVISION OR COMPART Organic Chemicals LOCATION ] Chicago Plant Dept. J.o. CONTROL POINT 097 JOB Tine 1 Purchase and install lead carbonate pump REPORTING CLASSIFICATION Cl OAT APPROVED 12/11/79 JOB ORDER NO. OC-4886 SUMMARY OF AMOUNTS DESCRI PTtON LOCAL CURRENCY ESTIMATED PROJECT COST d is ma n t l e me n t e x p e n s e *utsn`U-*BS 500-- ------------- TRANSFER: EQUIPMENT GROSS AMOUNT FOR APPROVAL $356 ~ LESS TRANSFER EQUIPMENT L ESS SALVAGE P R TR ADS-IN ALLO WANCE NET CASH REQUIRED (g o f -3027) $5356 RETIREMENT DATA DISMANTLEMENT LESS SALVAGE 1,600 500 TOTAL - CHARGE RESERVE 2,100 DESCRIPTION AND REASONS REQUIRED ECONOMICS as called for in General Procedure Memo #3 Attachment C. (Attach calculations) ECONOMICS PERIOD net sal es NAT {p r o f it /s a v in g s ) .TOTAL INVESTMENT % ROI (o n t o t a l in v e s t .) INTERNAL RATE OF RETURN PAYOUT OF NEW FIXED CAPITAL REV*# 1 REVISION DETAIL (GROSS AMOUNTS) CUM. AUTHORIZATION Funds of -------------------------------------------- -------- ------------------- ------- --$5356 are requested to purchase and Install an air operated lead carbonate pump. O-' o 6-77 NA 3006 REV, 6-77 OC-4886------12/11/79 Page 2 of 4 DESCRIPTION AND REASONS REQUIRED Proposed Work and Cost Funds of............. .. . .. ............... .. . ................................................ $5,356 are requested to purchase arid install an air operated lead carbonate pump. Present Situation and Justification Basic lead carbonate is made in two carbonating tanks and pumped into a holding tank above the drum dryer. It is then dried, ground and further processed as required. The pumping operation to the holding tank above the drum dryer is accomplished by the use of a steam pump installed in 1966. The pump is badly worn. It leaks carbonate slurry on the floor and into the sewer system, aggravating the plant's effluent problems. An overhaul will cost $2,618. The resultant repair is judged to be short-lived. This pump is near the end of its useful life and the plant has no other pump to use as a replacement in case of failure. ' A trial, air-operated diaphragm pump, the same as will be purchased, was tested recently with success in lead carbonate service. Also, the plant uses a similar design air pump in lead phthalate-sulfate processing. Its design is far more economical to maintain than the old steam pump. Commercial Factors This order supports a plant budget for lead stabilizers as follows: Sales (k lb./$) 1979 Budget Pounds Dollars P.O.S. 9 Months 1979 Pounds Dollars P.O.S. 8,650 4,512 1,548 (34%) 6,419 4,405 1,195 (27.1%) r. YWT 34-0006335 C 1TA IV A JV*- Z X> 004886 12/11/79 Page 3 of 4 Details; of Proposal The plant will purchase one Wilden Model M-15-S air operated double diaphr'am pump, with spare parts and necessary three inch plumbing to install. Present steam pump will be scraped. \ Contingent Future Commitments This proposal will not require additional funds to complete. Alternatives Considered Repair phe present steam pulftp. This was rejected because of the high cost of parts, labor, and limited useful life. The new pump will be more economical to maintain. Risks No operating risks are involved. Summary This is a replacement of a physically exhausted pump with a better pump. CYWI 24-0006336 iOF- 30*7 REV. 7/62 u'*^ 7/62 DETAIL SHEET SHEET NO. JOB ORDER NO. COMPANY American Cyanamid Company ITEM OR CODE NO. DESCRIPTION OC-488612/11/79 Page 4 of 4 11-20-79 LOCATION Chicago,111,, EQUIPMENT OR MATERIALS ENG. MECH. SVC. 1 Ailr operated pump 2 Piping 3 Spare parts 4 Dismantlement 5 Shipping charges 6 Illinois state and use tax 3190 500 197 50 219 500 500 200 3390 1000 197 500 50 219 4156 1000 200 $5356 Dismantlements Carbonate Pump Acq. Date Acq.Cost Disposition 6/71 1,600 Scrap CYWT 24-0006337