Document e58pwRXoxBdg3km0wx887vXq4
/ f TO; `
0>ratif
APPROVED sr
Page 1 of 8
Asarco Construction or Repairs Contract Form PD-19 Under $100,000.00 Revised 5/75
RETURN TO PURCHASING DEPARTMENT
CONTRACT FOR
USED CONVERTER DISMANTLING, LOADING & SHIPPING
(Insert name of job)
ASARCO Incorporated's
EL PASO
at EL PASO, TEXAS____________________________ (Insert town and state)
Plant
THIS AGREEMENT- made the 12th
day of DECEMBER , 19 83,
by and between JAMES & LUTHER INC., whose address is P. O. Box 13224, EL PASO, TEXAS 79912 (hereinafter called the
"Contractor") and ASARCO Incorporated, a corporation of the State of
New Jersey, whose address is 120 Broadway, New York, N.Y. 10271 and
EL PASO PLANT, P.O. BOX 1111, EL PASO, TX 79999(hereinafter called the) (Insert address of plant or unit)
"Owner").
WITNESSETH:
The Contractor and Owner agree as follows:
Article 1. Scope of the Work
The Contractor shall furnish all shop drawings^ field engineering, labor, tools, equipment, transportation, materials and other facilities, except such items as are hereinafter listed as being furnished or furnished and installed by
the Owner, for CONVERTER DISMANTLING,IOADING & SHIPPING (hereinafter called the "wo (Insert name of job)
at the ANACONDA SMELTERat ANACONDA, MONTANA (Insert town & state)
in accordance with the drawings and specifications listed below, all of which are incorporated herein by reference and made a part hereof:
SPECIFICATIONS FOR CONVERTER DISMANTLING fi IOADING, DATED OCTOBER 19, 1983
REV. 1 Dated December 12, 1983, entitled:
(List Specifications and Drawings
SPECIFICATIONS FOR USED CONVERTER DISMANTLING, LOADING & SHIPPING (which supercedes original specifications dated Oct. 19, 1983)
ASARCO ELP 0007761
Page 2 of 8 ,
Article 2. Time of Cocapletion dz'Qau&zi ,\^82 ///(^- 't 5/
The work shall be coanenced______W__tf_lU__A_I_U_f__0__i __1_9_&__4____ _______V_-__ _____ and
0J1H&ohall be substantially completed
V
j1
*04/&VArticle 3. Payment (to be deleted if progress payments are to'be maBe)
The Owner shall pay the Contractor for the performance of this Contract,
the sum of THIRTY-THOUSAND DOLLARS PLUS FREIGHT (SEE ARTICLE 25)dollars,
($ 30,000.00__), lawful money of the United States of America within
_____ 30 days
days after satIs factory completion of the work and submission
by the Contractor of evidence (including, if requested, complete releases of all liens arising out of or in connection with the work by all persons, firms or corpora tions on whose behalf such liens could be or were filed) satisfactory to the Owner that all charges for labor and material incorporated in the work and all other indebt edness connected with the work for which Liens could be filed have been paid and that the work is free of all liens and encumbrances.
Article 3. Payments (to be deleted if progress payments are not to be made)
TheN^wner shall pay the Contractor for the performance of this contract,
the sum of
dollars, ($_
On or about the
percent (
19
), lawful money of the United States, as follows:
^ /_day of each calendar xibnth, commencing
I^Ate Owner shall pay/the Contractor
&.<V
%) baaed oiNfhe contact prices, of the labor and materialj^/
incorporated in the work and of materials spft^bly stored at the site thereof up to the end of the next preceding calendar mjwith, asx^stimated by the Owner, leB* the
aggregate of previous payments; and unpn completiorNof the entire work,, a sum suff
icient to increase the total paymentsto___________
percent (
%)
.of the contract price. Final payment of the remaining (_
%) of the
contract price shall be dup^_days after cc >letion of the work.
Before each sudh payment is due, the Contractor shall submit evidence satis factory to the Ownep^Cincluding, if requested, partial waivers, or in theN^Be of final payment, cosfplete releases, ot all liens arising out of or in connection with the work by al)/persons, forms or corporations on whose behalf such liens couliKbe or were filed) laat all charges for labor and material incorporated in the work and all other indebtedness (except, in the case of payments other than final payment, indebt* edness ndt then due) connected with the work for which liens could be filed have been paid .and that work is free of all liens and encumbrances.
ASARCO ELP 0007762
Page 3 of 8
Article 4. Payments Withheld
The Owner may withhold all or part of any payment to the extent necessary to protect the Owner from loss or damage on account of (a) damaged or defective work not remedied, (b) claims filed or reasonable evidence indicating probable filing of claims by other parties against the Contractor or the Owner (c) failure of the Contractor to make payments properly to Subcontractors or for material or labor, (d) a reasonable doubt that this contract can be completed for the balance then unpaid, or (e) damage to the Owner's property or the work of another contractor.
Article 5. Liens
If any lien remains unsatisfied after payment of the full contract price has been made, the Contractor shall refund to the Owner all moneys that the latter may be compelled to pay in discharging such lien, including all costs and a reason able attorney's fee. If the Owner has so requested prior to the signing of this Contract, the Contractor, at the option of the Owner, agrees to furnish or permit the owner to secure bonds in the full amount of the contract written by a surety company designated by, or otherwise satisfactory to, the owner, guaranteeing and conditioned for the full, complete and faithful performance of this contract by the contractor and for the payment of claims for labor performed or materials furnished in connection herewith, all in accordance with the terms of the bonds. The premium for the bonds will be paid by the Owner and must not be included by the Contractor in the contract price. In the event the owner elects to secure such bonds, the contractor agrees to sign the required application, to furnish necessary financial statements and financial guarantees, and to otherwise cooperate with the owner, in securing the bonds.
Article 6. Title to the Work
Title to all work completed or in the course of construction shall be in the Owner and title to all machinery, equipment and materials to be in- corporated in the work shall be in the Owner as soon as they are delivered on the site of the job.
Article 7. Inspection and Repair
. .
The Contractor shall provide safe and proper facilities at all times for the inspection of the work by the Owner, and shall as soon as practicable after written notice from the Owner, at the Contractor's expense, replace and repair any materials or portions of the work which'the Owner shall deem defective and make good all work damaged or destroyed thereby, whether or not there shall be a dispute with respect to any of the foregoing. Any such dispute shall be settled by arbitration.
-
Article 8. Protection by Contractor
. The Contractor at all times shall maintain adequate -protection of the work from damage and shall protect the Owner's property and all persons thereon from injury, damage or loss by reason of any act or omission of the Contractor or any Subcontractor. The Contractor shall be responsible, and reimburse the Owner, for any loss or expense to the Owner arising from damage to the work or other property of the Owner caused by the wrongful act or neglect of the Con tractor, any Subcontractor or the employees of the Contractor or any Subcon tractor. Where such damage includes damage to the work it shall be repaired at the expense of the Contractor.
ASARCO ELP 0007763
Page 4 of 8
The Contractor shall use its best judgement and skill in dealing with labor matters, and take all reasonable steps to avoid labor dispute. In the event of any strike or-threat of strike, slowdowns, featherbedding,, or other like practices, the Contractor shall apprise the Owner of all relevant facts and implications of the particular labor problem involved, and shall consult in good faith with the Owner in an endeavor to reach a mutually satisfactory solu- tion to such labor problem and, so far a's reasonably possible, to protect the Owner against delays affecting the work or damage or losses to its other oper ations.
Article 9. Contractor's Liability "hisurance
The Contractor shall maintain such insurance as will indemnify it against claims under Workmen's Compensation Acts and against any other claims for damages for personal injury, including death, which may arise from opera tions under this contract, whether such operations be by the Contractor or any Subcontractor or anyone directly or indirectly employed by either of them.
Prior to commencement of this work the Contractor shall file with the Owner completed certificates of insurance in form of "Insurance Certificate" attached and shall provide insurance coverage in amounts not less than those stated therein.
Article 10. Indemnity by Contractor
The Contractor shall save harmless and indemnify the Owner from and against any expense, loss or damage on account of any claim, demand or suit made by any person whomsoever, including any employee of the Owner, which is in any way caused by or connected with, or grows out of the execution and performance of this Contract by the Contractor or any Subcontractor; provided, however, that the Contractor shall not be required to indemnify the Owner against any loss caused solely by the negligence of willful fault of the Owner or its employees. The Contractor accepts all risk of injury or damage and all responsibility for any claims for damages what soever resulting from the use, misuse, or failure .of any hoist, rigging, blocking, scaffolding, or otherlike or unlike equipment used by the Contractor or any Subcontracto even -though such equipment be furnished or loaned to the Contractor or any such Subcontractor by the Owner, and shall indemnify the Owner'against all such claims
Article 11. Owner's Responsibility for Certain Casualties
The Owner shall be responsible for all damage to the work, and to material, temporary structures, and equipment (excluding construction equipment not owned by the Owner) at the site of the job, which is caused by fire, windstorm, smoke, hail aircraft, explosion, vehicles, riot or civil commotion.
Article 12. Compliance with Laws and Ordinances
The Contractor shall give all notices and comply with all laws, ordinances, rules, and regulations, bearing on the conduct of the work as drawn and specified. If the Contractor performs any work contrary to any such law, ordinance, rule or regulations, he shall bear all costs arising therefrom, in particular, but without limiting the scope of the foregoing, the Contractor shall, and shall cause any Subcontractor to, comply with the terms and provisions of the Occupational Safety and Health Act of 1970 and all appliable rules, regulations, orders and occupational Safety and health standards promulgated under and issued pursuant to such Act in th discharge of its duties and obligations hereunder.
ASARCO ELP 0007764
Page 5 of 8
If for any reason the Contractor's or any Subcontractor's employees or agents acquire a status imposing liability on the Owner for employer's con tributions or taxes under the Federal Insurance Contributions Act, the Federal Unemployment Tax Act, any State Unemployment Tax Act, or any other Act, the Contractor shall be exclusively liable for, and shall indemnify the Owner against, the same and agrees to comply with all such laws and regulations so as to relieve the Owner from any and all liability therefor and from the re sponsibility of making reports or keeping records with respect thereto.
Article 13. Patents
The Contractor shall indemnify and save harmless the Owner against and from any and all claims, losses, costs, damages, expenses, actions or other proceedings, growing out of or resulting from infrigement of any patent by the Contractor or any Subcontractor in the performance of this contract, except that this provision shall not apply to patented articles or processes specified in drawing or specifications furnished by the Owner.
Article 14. Changes in the Work
The Owner, without invalidating this contract, may at any time order extra work or make changes by altering, adding to or deducting from the work. Such order may be made by the Owner on its own behalf or at the request of the Contractor, upon discovery by the Contractor of any discrepancy between the plans and the physical conditions encountered. If such extra work or changes involve a change in cost, the contract price shall be increased or decreased by the fair value thereof. The Owner will Itemize the changes to be made and upon receipt of written notice of same, the Contractor will submit promptly to the Owner, in triplicate,- an itemized statement of his calculations of the adjustment in the contract price resulting from the changes or extra work. This must be done before work on the change is begun unless the Owner gives written order to proceed immediately. No work or change shall be made, except by written order of the Owner and no claim for an add ition to the contract price shall be valid unless the additional work was so ordered. Any dispute under this Article shall be subject to arbitration.
Article 15. Owner's Right to Terminate Contract
.
If the Contractor should be adjudged a bankrupt, or make an assignment for the benefit of creditors, or if a receiver of the Contractor's property should be appointed or if the Contractor files a petition or if a trustee of the Contractor's property should be appointed under the reorganization or readjustment provisions of the Bankruptcy Act, or if the Contractor at any time should refuse or neglect to supply enough properly skilled workmen or proper materials, or if he should fail or make prompt payments to Subcontractors or for material or labor, or disregard laws, ordinances or the instructions of the Owner, or otherwise be guilty of a substantial violation of any provision of the contract which he shall have failed to correct promptly after service or written notice thereof by the Owner, then the Owner may, without prejudice to any other right or remedy, terminate the employment of the Con tract for the Contractor's default and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method the Owner may deem expedient. In such case, the Contractor shall not be entitled to receive any further payment until the work is finished. If the unpaid balance of the Contract price shall exceed all the general damages of the Owner caused by the Con tractor's default, including the expense of finishing the work and compensation of the Owner for the Owner's managerial and administrative service, such excess shall be paid to the Contractor.
ASARCO ELP 0007765
Page 6 of 8
-If such damages shall exceed such unpaid balance, the Contractor shall pay the difference to the Owner. In the. event the Contractor and the Owner are unable to agree upon the amount to be paid or reimbursed the dispute shall be settled by arbitration.
Article 16. Correction of Work after Payment
Neither payment nor any provision in this contract shall relieve the Contractor of responsibility for faulty materials or workmanship and the Contractor shall remedy any defects due thereto and pay for any damage to other work resulting therefrom which shall appear within one year from the date of completion of the Contractor's work hereunder. The Owner shall give notice of observed defects with reasonable promptness. Any dispute under this Article, shall be subject to arbitration.
Article 17. Arbitration.
All disputes which are herein stated to be subject to arbitration shall be submitted to and determined by arbitration. Except as. and to the extent otherwise provided by the controlling state law, no party may have recourse to legal proceedings (other than to enforce this arbitration Article) unless and until an arbitration award has been made. There shall be one arbitrator who shall be chosen by the American Arbitration Association, whose arbitration rules shall be followed.
Article 18. Subcontracts
The Contractor will not employ any Subcontractor without the prior written approval of the Owner and the Contrator shall require each Subcontractor to execute a contract in writing containing provisions similiar to all provisions of this con tract which are in any way applicable to such Subcontractor and which will obligate such Subcontractor to comply with and perform all such provisions herein. Nothing herein shall create a contractual relationship between any Subcontractor and the
Owner.
Article 19. Assignment
The Contractor shall not assign nor subcontract this contract in whole or in part nor shall the Contractor assign any moneys due or to become due Contractor here under without the prior written consent of the Owner.
ArtieTe~~Q^--Coordination of Work
The Contractor shall c
the workJierettnd'Sf^so as to cause a minimum of
interference with the Owner's ogers
terference with the Owner's operations
become absolutely
permission shall be reques
Contractor not less
than seventy^two'TTS) hours in advance.
Article 21. Undertakings by the Owner
The Owner agrees to obtain and pay for any permits, licenses and easements
required/-for permanent structures or changes, and,-to--fche-cxtent-practicablc-without
intor-fcronco w-i-th operations, to furnish--t-hc Contractor, fr-ce of charge, for-i-fcs-
ug-e- during the -conat-guetion, electricity, water,-a team and compressed -air- required-for
construction purposes,-at--the voltage and-pressure currently available at Owner's- |
-aaid plant, to-e point adjacent--to or within
feet of the site-? but--the-
Contractor wil-lr bo required' to make the neeeccary -connections, provide approved shut-off
end-safety devices and furnish-andinstall all--temporary-14-neB-required to bring them
to the point of' uoo--
ASARCO ELP 0007766
Article 22. Applicable Law
Page 7 of 8
This contract shall be construed and enforced in accordance with the laws of the state where the work hereunder is to be performed.
Article 23. Entirety Clause
This contract constitutes the entire agreement between the parties, and
except as may be specifically set forth herein no changes can be made herein except
by an agreement in writing duly executed by the parties or their duly authorized
agents.
.
Article 24. Technical Information
The Term "technical information" as used in this agreement includes but is not limited to technical data, reports, models, drawings, specifications, operating manuals, designs, computations, formulas, apparatus, processes, pat entable or unpatentable inventions and other engineering data. You agree to accept Asarco's decisions as to whether any particular information is technical information or is technical information which has been made or conceived under this agreement.
It is understood that in the course of your performance hereunder you may learn or have access to technical information of Asarco. You agree that you and your personnel will keep in confidence all such technical information of Asarco and that you and your personnel will not use or disclose the same without Asarco's written consent, either during the term of this agreement or at any time thereafter.
You agree to disclose to Asarco all technical information made or conceived by you or your personnel in performance, or resulting from performance, under this agreement. You agree that all such technical information made or conceived by you or your personnel shall become and remain the free and unrestricted property of Asarco and that you shall assign or cause the same to be assigned to Asarco. You agree that you and your personnel will keep in confidence all such technical information made or conceived by you or your personnel and that you and your personnel will not use or disclose the same without Asarco's written consent, either during the term of this agreement or at any time thereafter.
You agree, upon the request and at the expense of Asarco, to make or cause your personnel to make applications for Letters Patent in such countries as Asarco may designate on those of the aforesaid assigned inventions which Asarco believes to'be patentable; and to assign all such applications to Asarco or its order; and to give Asarco, its attorneys and solicitors all reasonable assistance in preparing such applications, and in prosecuting such applications in the patent office or offices involved and in defending and enforcing any patent that may be issued upon any such applications; and to execute all papers that may be reasonably required in the prosecution of such applications or to vest in Asarco or its assigns said inventions, applications and Letters Patent.
Article 25, Additional Provisions
(add such additional provisions, if any, as the particular job requires).
Freight shall be paid as follows: Primary load (converter shell) Secondary load (based on use of 40 ft.
t $11,250.00
1,625.00 per load
float, 40,000# load maximum, no overages)
ASARCO ELP 0007767
Page 8 of 8 IN WITNESS WHEREOF- the parties have executed this contract the day and year first above written.
JAMES AND LUTHER, INC.
ASARCO Incorporated Owner
*
By
[purchasing Agent
ASARCO ELP 0007768
fORM * INSURANCE* 1 B*icd
ASAHCO.Incorporated :s
INSURANCE-CERTIFICATE
ASAHCO, Incorporated RE0U1REMENTS FOR CONTRACTORS AND SUBCONTRACTORS.
THIS IS TO CERT I FT THAT THE POLICIES OF INSURANCE DESCRIBED BELOW HAVE BEEN ISSUED TO
____________ James S Luther, Inc.____________________ ;_______________ '
THESE POLICIES AHE NOW IN FORCE. COVERING WORK BY THE ASSURED FOR ASARCO,Incorported
on contract Converter Replacement Study CE 83-EP-14 AT Anaconda. Montana____________________________________________________________
IF THESE POLICIES AM CANCELLED OR CHANGED IN ANY WAV THAT WILL AFFECT THIS CERTIFICATE. TEN DAYS'
PRIOR WRITTEN NOTICE WILL BE GIVEN BY THIS COMPANY TO ASARCO, Incorporated.-
itt*-' Mr. Dale T,. Bern------------------------------ plant manager.
KIND OF INSURANCE
NUMBER
DESCRIPTION OF POLICY
EXPIRES
LIMITS OF LIABILITY
REOUIRED M j N1 MUM
CONTRACTOR'S PUBLIC LIABILITY (COMPREHENSIVE
5LA190887
INCLUDING CONTRACTUAL)*
07
BOOILY.INJURY
9-4-84
PROPERTY, ruw^r.t CONTRACTOR`S PROTECTIVE LIABILITY
BOO 1L y-INJURY
same
same
5LA190887 07 9-4-84
PROPERTY.DAMAGE
same
same
f.AI II OIXI KHENCF 5 500,000 EAC.H orc-1 RRENT.t: J 250,000
EACH OCI'.l RRENCF. J 500,000
EAI.I, OCCLHHtNCE l 250>000
AUTOMOBILE BODILY-INJURY
PROPERTY.damage workmen's COMPENSATION
AND fA^LOVCR'S LIABILITY
jLA190887 07 9-4-84
same
same
EACH PERSON
$ 250,000
EACH OCCURRENCE i 500,000
EACH OCCURRENCE * 100}000
WC116320i -same
9-4-84
same
EACH OlTIRRENCE 1 1QO,000
$300,000 , $ 25.000
$300,000 $ 25.000
$100,000 $300,000' $ 25.000 COMPLY WITH
applicable
STATE LAW $25,000
date
12-12-83
Transamerica Insurance Company
INSURANCE COMPANY
'El Paso c ITY
Texas
STATE
AUTHORIZED REPRESENTATIVE
GOLDFARB INSURANCE AGENCY mg
*Th Contractor akall asra karaloaa and itdantufv tka Ovnaf frow and aftiaat aay aipaata* 1M or dtaaft ea account of aay
dtoand or twit oada ky inv ptraon wkeoaotvor. including any ooplovoa of tka O-raar, vkick ia ia uy oay eauaod by or
connactatf itk or gro*a out of tk aaacutien and pttforanca of thta contract ky tka Contractor or aay Subcontractor; pro*
ytdad, be*t#r tkat tka Contractor akall aot ba ro^utrod to sndonnify tka Chmar tgaiaat aay lota aauaad aolaiy by
|anca or atllful fault of tka Onr ar ita toploytoa. Tka Contractor aceapta albriak of injury or
all raapoa*
aibility for any elaiaa for daoagaa kataoa*ar rnaulting froa tka uaa, aiauaa, or fatlura / aay kniatt rigging, bleckiag,
caffoliiof. or otka/ Ilk* or vnWka agutpaaat uaad by tka Coatractor r aay Subenntraetar. aan tkougk aick a^iipoait ka
fwratakad or leanad ta tka Contract*' *r tay auck Subeoatractor ky tka Oarr** **d akall iadooaify tka Ooaar afaiatt all
auch claiaia.
ASARCO ELP 0007769
SPECIFICATIONS' FOR
USED CONVERTER DISMANTLING, LOADING & SHIPPING
TO THE EL PASO PLANT
Prepared by:
ASARCO Incorporated Central Engineering Department
Design Section Salt Lake City, Utah
Job :
Pit. N.Y. Req.
EA-63-EP
706 5834 CE 83-EP-14
Date: October 19, 1983 Rev. 1, December 12, 1983
ASARCO ELP 0007770
USED CONVERTER DISMANTLING, LOADING & SHIPPING
1.0 GENERAL
This specification covers the furnishing of supplies, equip ment and labor to dismantle, load and deliver a used 13 ft. dia. by 35 ft. long converter with ancillary equipment, as furnshied by ASARCO Inc. at Anaconda, Montana, to the El Paso Plant at El Paso, Texas. The converter'is presently in the possession of Cleveland Wrecking Co.
2.0 DESCRIPTION OF WORK
2.1 The Contractor will provide the following services:
2.1.1 Remove all brick from inside the converter shell.
2.1.2
Remove any or all parts that may be required to dismantle,* load and ship the converter and ancil lary equipment.
The ancillary equipment shall be, but not limited to, the following: jack shaft with bevel gears, gear reducer, electric motor, couplings, controls trunnions, tuyeres, bussell pipe, covers and con trol panels.
2.1.3
The loading of equipment shall include wood block ing, tie-downs, boxes, bracing, etc., required to stabilize the load for shipment to El Paso, TX.
All small and or loose pieces of equipment shall be boxed in totally enclosed wood crates. Gear reducers and electric motors shall be mounted on wood skids.
If the ends are removed from the converter, inter nal bracing will be required at two (minimum) places to keep the shell round. Tie-downs will only be allowed where internal bracing is located
ASARCO ELP 0007771
Used Converter Dismantling, Loading & Shipping El Paso Plant, cont.
Rev. 1, Dec. 12 , 1983
2.
2.1.4
After the converter and ancillary equipment have been removed, the area shall be cleaned up to suit Cleveland Wrecking Co.
3.0 JOB SITE
3.1
The converter and ancillary equipment may be inspected
by contacting
Mr. Larry Huff Cleveland Wrecking Co. P. O. Box 1110' Anaconda Smelter Anaconda, Montana 59711 Phone: (406) 563-3464
3.2
Two existing overhead electric cranes (75T) may be used inside the converter building for dismantling and loading the converter onto trucks. See Mr. Larry Huff of Cleve land Wrecking Co. for their use.
4.0 BID PROPOSAL
The bidder shall provide a detailed description of the ship ping pieces proposed, the method of handling of the pieces -and the method of crating for each of the pieces (boxed, skids, blocked, etc.) for each of two alternatives.
All pieces dismantled shall be match-marked for ease in re assembly of unit.
The bidding shall be lump sum with all taxes, permits, duties, etc., included. The bidder may propose alternatives, but any must be bid in addition to the following:
4.1 Shipping by Railroad Car
The following shall be included in the proposal:
ASARCO ELP 0007772
Used Converter Dismantling, Loading & Shipping El Paso Plant, cont.
Rev. 1, Dec. 12 , 1983
3.
a) Dismantling of converter and equipment. Converter to be shipped assembled with riding rings, bull gear, ends and bussell pipe.
b) Transferring of shipping pieces to the Butte Anaconda and Pacific railway siding.
c) Loading of shipping pieces onto the railroad car(s) furnished by ASARCO.
4.2 Shipping by Truck
The following shall be included in the proposal:
a) Dismantling of converter and equipment. b) Removal of riding rings. c) Removal of bull gear. a) Removal of converter ends. e) Removal of bussell piping. f) Removal of tuyeres. g) Loading of shipping pieces. h) Furnishing of trucks and drivers to ship the converter
and ancillary equipment to the El Paso Plant at El Paso, Texas.
ASARCO ELP 0007773
Used Converter Dismantling, Loading & Shipping El Paso Plant, cont. Rev. 1, Dec. 12, 1983
4.3 Proposal Data Sheet Bidders Name & Address:
4.
Bid Date:
Bid No.
Bid:
Bv Railroad Car
Lump Sum
$
Start dismantling
Dismantle & load
By Truck Lump Sum Start dismantling Dismantle & load
$
Days ARO Days
Days ARO Days
ASARCO ELP 0007774.
CLEVELAND WRECKING, CO.
*/
P. O. BOX 1110
INVOICE
ANACONDA, MT. 59711 406-563-3464
(eeveland/W **__________
____
V,vi L'*
^
''to ~.s\s\ i \
P.O. BOX 23427 3170 E. WASHINGTON BLVD. LOS ANGELES, CALIFORNIA 90023
OFFICES COAST TO COAST
to, ASARCO, INCORPORATED P.O. Box 1111 El Paso, Texas 79999
Phone (213 ) 269-0633
date 8 November 1983
INVOICE NO. BILLED BY YOUR
ORDER NO. PO 13H1202*
ASARCO ELP 0007775