Document dawNGg2Nmz8MKwa8nGQmYzNB0
COMPANY CONFIDENTIAL
Sauget, Illinois March 26, 1978
Progress Report
Aroclor Expansion (CEA 1800) W. G.Krummrich Plant Department 246
Distribution:
t>. C. Armstrong WGK
T. W. Dalton
- WGK
M. S. Feld
- WGK
T. E. Greenman - WGK
W. A. Kuhn
- G.O.
J. R. McClain - WGK
ITT S.
R. P.
Report Objective
To communicate to Organic Management the Aroclor Expansion project/start-up status and timing and the status/plans of the Aroclor Quality Improvement Program.
Report Scope
This report is a brief resume' of major events through 3/25/68.
Prepared By: H. F. Ray Manufacturing Representative
Approved By: T. W. Dalton General Superintendent
0164746
TOWOLDMONOQ45248
1
Phase I - Aroelor Finished Product Storage
F7/ie1/ld68c. onstruction proceeding on schedule. EDC r.emains at
The five (5) new aluminum, 22,000 gallon storage tanks along
with the associated transfer pumps and filters have been
mounted on their respective'foundations. Piping fabrication
is underway.
'
The track 10-A extension has been completed and the founda tions for the new Spot 5 and 6 Biphenyl unloading docks are poured. Field erection of the 100,000 gallon biphenyl storage has not commenced.
In conjunction with Phase I of the expansion, WGK project
No. 2844 - "Provide Facilities To Increase Capacity And Quality Of Transformer Blends To Meet Sales Requirements" is being installed. About 85$ of this project will be completed by the start-up of Phase I with the remaining 15# completed by 8/1/68. The delay is due to the availability of the existing Aroelor 1260 storage tank as a result of the sold-out status of the Aroelor Department.
The new foreman's office and the necessary parts of the new
motor control center will both be completed by start-up of
Phase I.
-
No scope changes for Phase I of this project are anticipated at present.
Phase II - 40 H #/Yr. Aroelor Manufacturing Facilities
Design and drafting are proceeding on schedule. All equipment
except for some instrumentation and electrical hardware is on
order. Providing the structural steel is delivered on the
current schedule, project start-up will probably be moved
up from 12/2/68 to ll/l/68.
'
The only scope change for Phase II anticipated at present is the purchase and installation of a spare vacuum ejector for the two new 25 H #/yr. stills. Anticipated installed cost is $3000. This spare unit is necessary to avoid costly repair outages on the stills. The existing #1 and #2 stills have an installed spare which has more than Justified its
original cost.
I .
018*7*7
TOWOLDMONOQ45249
- 2Aroelor Quality Improvement Program The operating conditions for the new Aroelor Plant have been finalized. These conditions have been set to achieve with known technology the Aroelor Quality Goals established at the Corporate Aroelor Meeting in May, 1967. The major items of concern are power Factor, Resistivity and Stability (Thermal Chemical Chlorides). Up until the present there has been no work directed towards duplication of products, as measured by GLC and IR analyses, at WGK, Anniston and MCL as the need for this duplication was not included in the original Quality Goals. Future Work includes (1) identification of the Biphenyl quality problem (EDO 10/1/68) (2) evaluation of a new type chlorination catalyst (EDC 10/1/68), and (3) identifi cation of differences in Aroelor production at the three manufacturing locations and method of controlling these differences (EDC 4/1/69).
H. F. RaSy Manufacturing Representative