Document daQNw9gmXgZg9Y5g9kwa8G6n5
mfCi^A/COMPAA/y
TO
w.
FROM
A.
SUBJECT
C. Fultz M. Matvaer
FiaD POINT OR DEPT. & BLDG. NO.
Pedricktown
FIELD POINT OR DEPT. Be BLDG. NO.
Pedricktown
GASKET FAILURE- -VINYL CHLORIDE RELEASE
DATE YOUR LETTER
OATE THIS LETTER
9/23/93
Summary
On September 14, 1993 a gasket in the charge line to Poly 22 failed
during the charge step. A total of approximately 20 pounds of vinyl
chloride monomer was released through this gasket failure.
No
exposures, injuries or damage to equipment occurred.
Board of Review
A Board of Review was held on 9/15 with the following in attendance:
A. Lehman E. Henson J. Houston A. Matyger M. Munyan
Shift Lead Technician Charge Technician Console Technician Area Manager Ogden Utilityman
Conclusion
Three bolts on the top of a 4" Keystone wafer valve were not properly torqued causing the gasket to fail during the charge sequence.
Narrative
At 1523 on 9/14/93 Poly 24 began its charging step.
Charge
ingredients (premix) were being pumped into this poly as per normal
procedure.
The equipment and piping was visually checked for
problems at the start of this charging step. M. Munyan performed
this check and>there were no problems.
At approximately 1525 Maintenance mechanic, " `
, heard a
pop and saw what he thought was sope coming from the charge line.
Charles Robinson notified Mike Munyan who was still on the first
floor and Mike Munyan immediately instructed the Console Technician,
Jim Houston, to fail the premix which requires the computer to close
all the charge valves and turn off the pumps. The unit was failed
and the valves closed at 1526.
During this time
also called Ed Henson using the
terryphone.
He told Ed Henson what he saw and Ed sounded the gas
alarm and instructed
to leave the area.
All shift personnel reported to the south stairwell to deal with the
spill.
The console technician opened the valves to the transfer line
and recovery tank to pull a vacuum on the line with the bad gasket.
This was completed by 1528 and the line was under vacuum. The leak was now stopped.
redacted
NGC 13654
Page 2
The gas maximum it was ppm.
chromatograph
400 ppm reading
sampled.
On
point nearest the failed gasket registered a then dropped to less than 5 ppm the next time the following sample cycle it was less than 1
The outside of the building was monitored for vinyl chloride (VCM) and when none was detected the all clear was sounded.
The line was left on recovery until the recovery system pressure increased indicating air was being pulled in through the failed gasket. The area was thoroughly hosed down and the gasket replaced.
Facts Surrounding the Incident
1. The LEL detection system was tripped at 1527 hours. Point 5 was the sample point in alarm.
2. The charge being made was a 137 charge so the premix had acrylic acid in it.
3. The highest GC reading at Point 2 for vinyl chloride was 400
ppm.
The next sample cycle at this point was less than 5 ppm and
the following cycle at this point was less than 1 ppm.
4. The header at the point of the failed gasket should not have had premix in it during the charging of Poly 24. A block valve upstream was leaking through.
Management Systems Investigation
1. Emergency notification was done properly and in the correct time frame.
2. The top three bolts on the valve where the leak occurred were not properly torqued. The gasket was in three pieces. The valve had been in service for 3 months and was installed by an outside contractor.
3. The non asbestos containing replacement gaskets currently used weaken and tear easily.
4. The gasket and line had only been in service for 3 months.
5. Shift response to the emergency was excellent. The leak was quickly brought under control from the remote console location. Exposure to this leak was not necessary.
6. Valve 2339, the charge line block valve, was found no be broken.
The pin holding the wafer to the shaft was broken allowing the
wafer to 1 open.
Neither the computer nor the operator could
detect this failure.
NGC 13655
Page 3
Action Items
1. Repair 2339 to make sure it functions properly and does not leak, through.
Complete
2. Check all bolts on charge header and tighten any loose bolts that are not properly torqued.
Complete
3. Replace the current gaskets with asbestos contain
ing gaskets. These lines cannot accept flexitallic
gaskets without modifications.
10/30/93 JM
A. M. Matyger AMM/jeb
NGC 13656
IPGoodrich
INTER-ORGANIZATION CORRESPONDENCE
TO
Distribution
FROM
A. M. Matvoer
SUBJECT
VCM OVEREXPOSURE
j FIELD POINT OR DEPT. & BLDG. NO.
DATE YOUR LETTS
1 FIELD POINT OR DEPT. & BLDG. NO.
DATE THIS LETTER
' Pedricktown ----------------------.---------------------- ..10/4/93 .
REDACTED
Summary
On 6/17/93,
Ogden Poly Breaker, was monitored for VCM
exposure.
The results of the test was a 1.22 ppm reading. Mike did
not wear a respirator during the monitoring period.
Board of Review
D. O'Keefe A. Matyger
Ogden Poly Breaker Safety Manager Dispersion Manuf. Manager
Conclusion
did no tasks that day to explain the cause of the high
readings.
The test results from the Laboratory used at this time
were suspect. This Lab is no longer used for the analysis.
Narrative
The tasks performed by
on 6/7 were reviewed. He did not clean
any polys or open equipment in vinyl service. The building light
readings for his shift indicate only 11 yellow lights (concentration
between 1 and 5 ppm).
There were no lights due to concentrations
greater than 5 ppm.
brought supplies up to a crew opening the recovery condenser on
the roof.
was approximately 10-15 feet away from the condenser
for 5 minutes while he coiled up a hose. He did not smell vinyl
while performing this task.
Management Systems Investigation
1. Receipt of lab results was delayed because vendor was sending results along with the invoice to CDT.
2. was properly trained in respirator use and the tasks requiring respirator use.
3. The recovery condenser was properly steam swept prior to opening.
4 Some of the lab's expected results, analysis.
Corrective Action
results have not been consistent with our A different lab is being used for this
NGC 13657
1. MDS Laboratory is not to be used for analysis work.
Complete
2.
arc iost.
Review incident with all shifts in the Paste Poly Blda.
11-. - , ia
*
Complete