Developing a societal acceptable remedial action plan for an important PFAS hotspot in Flanders : challenges and lessons learned?
Presented by: Senior Partner ERM
October 21st, 2022
Copyright 2022 by The ERM International Group Limited and/or its affiliates (`ERM'). All Rights Reserved. No part of this work may be reproduced or transmitted in any form or by any means, without prior written permission of ERM.
The business of sustainability
Content
1. The `Project' 2. Developing a societal acceptable remedial action plan 3. Lessons learned to date 4. Q&A
www.erm.com
ENSOr Presentation
25/10/2022
2
The `Project'
The `Project'
PFAS manufacturing plant situated in the Antwerp harbour cluster, a major mobility infrastructure project called `Oosterweel' underway in its direct vicinity;
Historical C8-PFAS production (mainly PFOS) thru Electrofluorination (ECF) process, stopped in 2002;
Onsite remediation ongoing since 2010 thru pump & treat, after the completion of the regulatory site investigation studies and remedial action plan, approved by the environmental agencies;
Recent new scientific insights and stakeholder observations made generated a catalyst effect pushing for new offsite sampling and risk assessment with a initial focus on human health;
The `project' went thru a media and political storm in the last 18 months; and
Within this complex and rapidly evolving context a 1st offsite remedial action plan (RAP) upon completion of a descriptive site investigation (DSI, done within 6 months), addressing the (potential) human risk via soil, has been developed for the area of concern with the highest priority.
www.erm.com
ENSOr Presentation
25/10/2022
4
Key findings of the initial offsite DSI - soil (including human health risk assessment or HHRA)
7 km impacted area
Around 200kg PFAS
Residential & Agricultural land use
Risk driven by free-range chicken egg
consumption
`No regret' measures In place
DSI HHRA
Phased remediation to be considered
Further study required
Over 4500 cadastral parcels
www.erm.com
ENSOr Presentation
Main impact observed
<1,5 km from manufacturing plant
Biomonitoring elevated PFOS
blood levels
Commingling with other external PFAS
sources
25/10/2022
5
PFOS distribution topsoil
www.erm.com
Source ERM DSI, Jan 2022
ENSOr Presentation
25/10/2022
6
Need for an integrated holistic PFAS approach needed
Basis for pragmatic PFAS management in
Flanders
Creating a more eco-friendly
neighbourhood
Reduce exposure
Sustainable and reasonable remedial actions
www.erm.com
ENSOr Presentation
25/10/2022
7
RAP zoning (zones 1A & B, and 2)
www.erm.com
ENSOr Presentation
25/10/2022
8
Developing a societal acceptable remedial action plan
Challenges to overcome
1. Evolving policy & regulatory framework 2. Biomonitoring results (blood serum) had to be integrated 3. EFSA opinion 2020 4. Human risk mainly driven by consumption of free-range
chicken eggs 5. Extremely short RAP development time imposed <6
months 6. Remedial works will be intrusive for the involved people 7. Many stakeholders involved with different interests
www.erm.com
ENSOr Presentation
25/10/2022
10
Seeking societal approval : What the stakeholders were saying when starting the RAP development
We want a more sustainable environment for our children
PFAS exposure should be minimized as much as possible
Integrated plan needed covering manufacturing plant and its surroundings within regulations
Synergies should be developed with Oosterweel,project
The reference frameworks need to be revisited based on the actual knowledge
Compensation for property value loss and business impacts
www.erm.com
ENSOr Presentation
25/10/2022
11
Final Proposed Remedial Plan - main actions
(currently subject to approval process)
1. 70 cm soil exchange residential/agricultural area;
2. Treatment/disposal of the excavated PFAS containing soils;
3. Backfill with good quality soils, fertile top layer;
4. Restoration of the residential gardens; and
5. Anticipated duration of the works 3 to 4 yrs, subject to backfill material/treatment capacity and agreements with the property owners.
www.erm.com
ENSOr Presentation
25/10/2022
12
Lessons learned to date
Co-creation is the only way to go
Responding to and managing
societal expectations
Collaboration will be the key success factor
Integrated and multifacetted solution needed
Pragmatic Framework & implemenation
Proportional, fair and prioritized solution
Building remedial capacity
www.erm.com
ENSOr Presentation
25/10/2022
14
The PFAS problem is far more complex!
Widespread use of AFFF and other PFAS containing products & applications Comingling of PFAS sources Background elevation
www.erm.com
ENSOr Presentation
25/10/2022
Source website PFAS verkenner
15
Questions & Answers