Document dQQ64VLvR5YEG4od0q4KNJoq6

TO: G. D. Bevis SUBJECT: Monthly Report September. 1078 FROM : J. C. Dalinsky LOCATED AT: Leominster, Ma. DATE: October 12, 1973 HIGHLIGHTS 1. ADT has completed all work related to fire alarm system except a curb box reset indicating device. 2. Northeast Sprinkler will replace the cooling tower valve when it becomes available. The valve has been ordered. 3. Special physical monitoring of vinyl chloride has been reinsti- tuted now that the manpower distributed to the EPA project has returned to their normal duties. 4. The trackmobile is still under repair. The plant is currently awaiting rebuilding of the engine. An October availability is expected. 5. EPA punch list work was affected by problems related to. new equipment ''start-up" and the necessary revisions to mainly the vent condenser and waste water transfer tank discharge. V.'ork continues on glycol tracing and insulation. 6. The Bendix area monitoring system was down for three days in September due to a short causing backfeed through the DMTJX boards in the computer. CIS was called to repair the unit. 7. The Safety Engineer recommended through advice by the EPA Coordinator the purchase of an oscilloscope to help oinpoint Bendix problems and lessen the need for CIS repairs and the cost involved. 8. CIS initiated the "start-up" of a new chromatograph in the in cinerator area. 9. Hnu status remains one of three works and of the three, one is out for repair. Two Century O.V.A. units were sent out for re pair (EPA). 10. The fork truck training orogran was completed during September 6, 7. and 8. This was accomplished by actual driving on all three shifts for the three days involved. 11. Seven material safety data sheets were submitted to R. Latham. C T I VINYL CHLORIDE CONTPOL I. Monitoring Summaries (Personnel) A. Monthly Monitoring Tests 1. Personnel on Regulated Roster 2. Personnel Tested 3. Personnel Tests 4. Invalid Tests 5. Repeat Tests 6. Area Tests 7. Contractor Tests 8. Total Tests September 190 176 176 3 3 36 0 215 Monthly Averages By General Job Categories 1. PVC Operators 2. PVC Helpers 3. Dryer Building 4. PVC Supv. and Engineers 6.0 5.1 1.0 1.4 BOR 013614 G. D. Bevis Monthly Report - September, October 12, 1978 Page - 2 1978 VINYL CHLORIDE CONTROL B. Monthly Avg. By General 5. Polyco 6. Shipping 7. Maintenance 8. Development 9. Oper. and Admin. 10. Total Site Job Categories (con't) Sept. 0.8 0.3 0.7 0.1 0.5 2.0 II. Area Monitoring A. MAC Room Status 1 - Bendix Monitoring System a. System #1, monitoring 16 points recorded alarms listed below. High Level Alarms Low Level Alarms % of Time System A1 in Alarm b. System #2, monitoring 16 points recorded alarms listed below: High Level Alarms Low Level Alarms % of Time System #2 in Alarm c. System *3, monitoring 9 points recorded alarms listed below: High Level Alarms Low Level Alarms % of Time System "3 in Alarm d. Total number of alarms for month e. Total alarm duration in minutes f. of time all points in alarm 14*3 777 20.3% 98 679 1.3% 10 152 3.6% 1.865 163,008 9.2% Bendix Monitoring Equipment Downtime Minutes a. System *1 b. System #2 c. System *3 d. Total e. % Time Down 3 Days for Repair by CIS or 10% of Total 3. Hnu Unit Status a. Two units need repairs of some nature, one unit is out for repair; upon return the other unit will be sent back for repair as well. 4. Monitoring Equipment Expenses a. September - $2,030.00 5. Air Intake Monitoring a. No. of tests b. Range ppm 21 0.1-1.7 6. Special Monitoring a. No. of tests b. Range ppm (Poof ^oly co)(Control Lab/Polyco) 11 3 0.1-0.6 0.1-0.7 BOR 013615 G. D. Bevis Monthly Report - September, October 12, 1978 Page - 3 1978 NOISE CONTROL Monitoring Summaries A. Monthly Monitoring Tests 1. Personnel Tested B. Monthly Average Plantwide (8 hr. TWA) 1. No. Invalid Tests 2. No. Tests 3. Average dBA 4. Range dBA Area Monitoring A. Monthly Monitoring Tests 1. Areas Tested 2. Area Tests B Monthly Average by Work Area (8 hr. TWA) No. Tests Avg. dBA 1. Bldg. #1-M 00 2. Bldg. #70 0 Noise testing will resume in November. Sept 0 0 0 0 0 .0 0 Range dBA 0 0 FUTURE ACTIVITIES I. Projects A. Vinyl Chloride Exposure 1. Special area testing will continue. 2. Continued education on when and where to use respiratory equipment. B. Noise Surveys 1. Both dosimeter and area monitoring will resume on a limited basis in November. C. Housekeeping 1. A program will be devised by November. D. Vinyl Acetate & TCE 1. A gas chromatograph will be installed during October to monitor VAc and TCE levels in F-209 St F-210 recovered monomer. SUMMARY I. Portions of the data contained in this report is extracted from reports by R. Slocumb, C. Snyder, and K. Landry to J. C. Palinsky and were only summarized for convenience. JCP/ltxs // - -*'A ' ' - tcc.-MVy.-- J. C. Palinsky' Safety Engineer BOR 013616 DIVISION MANAGER'S PF^pESS REPORT EMPLOYEE INJUR."AND ILLNESSES RECORD TYPE Q STATISTIC CONTROL (DIVISION USE ONLYI Chemical PLANT or BRANCH _ Thermoplastics Leominster MONTH_7 ORIGINAL REVISION 9 DIVISION CODE g_ ESIS LOCATION CODE September 1978 __ YEAR to rf TOTAL TOTAL TOTAL NUMBER OF LOST FIRST AIO RECORDABLE RECORDABLE LOST LOST WORKDAY WORKDAY CASE M aN HOURS CASES INC! DENTS INC! DENT RATE WORKDAYS CASES RATE 12 2113 ' " * " "7 20 23 24 24 27 _ 29 30_________________ 32 A JWSMONTH _ 55,404 17 4 14.4__________ 0 0 0 r TH/S YEAR TO DA 7T_ LAST YEAR TODA TE 662,076 198 * Data Not Available From 1977 For September. 34 ____10.3 ___ _______ 107_______ 2 0.60 ------------------1------------------- INCLUDE ONL Y LOST WORKDAYS AND LOST WORKDAY CASES UNDE fi COLUMN 9A OF THE LOG. L-100 CURRENT YEAR GOAL . 92 RECORDABLE INCIDENTS U> O3d TRAINING, JOB ANALYSES & COMMITTEE ACTIVITIES u> ot MAIL TO DIVISION SAFETY OFFICE NO LATER THAN THt 2ndWOBK1NG Di Y OF THE MONTH COVEBING THE PRIOR MONTH RESULTS. J. Heller / M. W. Kline / -------------- _ October 2, 1978 H. R. Jepsen, Jr. / N. M. Blackman -t , ~ MANAGER OATE TOTAL RECORDABLE INCIDENT RATE NO. OF RECORDABLE INCIDENTS X 200.000 " MANHOURS WORKED LOST WORKDAY NO. OF LOST WORKDAY CASES X 200.000 CASE RATE " MANHOURS WORKED FORM L-680 10/7 71 MANAGER'S PROGRESS REPORT VEHICLE ACCIDENTS RECORD TYPE ^STATISTIC CONTROL (DIVISION USE ONLY) ORIGINAL REVISION a DIVISION CODE esis location code 1 DIVISION Chemical 12 A THIS MONTH YEAR TO DATE r" B LAST YEAR TO DATE NUMBu A OF -- VEHICLES 29 29 Thermoplastics PLANT or BRANCH_ Leominster September MONTH 7 1978 YEAR. 9 10 11 VEHICLE | NilLGS 33 - number of CHARGEABLE ACCIDENTS 40 41 43 83,987 0 1,007,844 5 CHARGEABLE FREQUENCY RATE 0 NUMBE R OF PREVENTABLE ___ ACCIDENTS 44 - m PREVENTABLE FREQUENCY rate 00 _______ 2 2.2 ----- f------ 1 m VEHICLE ACCIDENTS CURRENT YEAR GOAL 1.6 MAI L TO DIVISION SAFETY OFFICE NO LATER THAN THE 2ndV*(0RKING DAY OF THE MONTH COVERING THE PRIOR MONTH RESULTS. THIS MONTH YEAR-TO-DATE DRIVER TRAINING 1 NUMBE R OF SMITH SYSTEM INSTRUCTORS number of smith SYSTE M DRIVE RS 1 : NUMBE R OF DDC INSTRUCTORS 0 0 !0 1 0 i .. _.i_ 0 ! NUMBE R OF DDC , DRIVERS 1 o 0 COMMENTS ON DEFENSIVE DRIVER TRAINING (e.g., DDC, SMITH SYSTEM, etc.) ___ ~ MANAGER _________ ~~ ___October 2, 1978 ~~ _ DATE CHARGEABLE VEHICLE FREQUENCY RATE = NO OF CHARGEABLE ACCIDENTS X 1,000.000 VEHICLE MILES PREVENTABLE VEHICLE FREQUENCY Rate NO, OF PREVENTA' l VEh ' UENTS X 1.000 000 ILES BOR 013618