ESCAMBIA PLANT INTEROFFICE MEMORANDUM To: Distribution From: D. C. Fee Ra; Amines Vent Gas Burning Process Hazards Review Dote; 6 November 1980 Copies: R- L- Duggan R. E. Jones T. J. Regan Please attend a Process Hazards Review on Amines Vent Gas Burning in the B&cW Boiler, held on Wednesday, November 12 at 9:30 a.m. in the Old Administration Building, upstairs con ference room. Attached is an updated PID for your review be fore the meeting. A DCFjdl '^Attached drawings D. C. Fee Distribution: J. Adams R. B. Chandler * D. R. Emert* J. R. Evers* D. W, Henn* W. T. Johnson* J. R. Walsh * AP00036320 A c^c^T^oe&ietl and G^e^mca&- ESCAM8IA PLANT INTEROFFICE MEMORANDUM To: Distribution from 0- C' Fec Re: No. 1 Nitric Acid Process Hazards Review Date: 26 November 1980 Copies: R. B. Chandler G. D. Cooper R. L. Duggan R. E. Jones T. J. Regan Please attend a Process Hazards Review on No. ] Nitric Acid, held December 3, 4 and 5 from 8:00 a.m. - 4:00 p.m. in the Old Adminis tration Building, upstairs conference room. DCF :dl Distribution: J. Adams W. M. Brown J. R. Evers D. W, Henn W. D. Henry H. H. Newsom D. C, Fee AP00036321 To From INTEROFFICE MEMORANDUM Distribution M. R. Chmura DISTRIBUTION; R. R. Baker R. L. Duggan L. S. Forrester J. W. Gentile A. K. McMillan R. W. Ormsby G. E. Pareja Subject Date THR Teams 3 October 1980 (Location, Oranlcationt or Department) Chem Hfo - Trexlertown (Location, organization, or Department) Please consider attached memo from J. Sykes when you are assembling PHR Teams for reviews scheduled at your faclltly. MRC/na Attachment m7 R. Chmura (320) AP00036322 INTEROFFICE MEMORANDUM Date 30 September 1980 Subject Process Hazards Reviews j ToM. R. Chmura__________________________________ From______J. A. Sykes__________________________ cc: ICT Management Chemicals Manufacturing (Location, Oroinuation, or Dtpjrtmont) Ind. Chetn. Technology (Location, Orpareintlon, or Oapartmcnt) Using Table 1 of your 25 September memo on "Schedule-Process Hazards Reviews Chemicals Group - Existing Facilities", I have recommended staff or contacts within Industrial Chemicals Technology for providing technical representation to the PHR teams. Please keep me informed of the teams and technical staff needs to carry out these PHRs. JAS/st Attachment fe. A. Sykes i> (320) AP00036323 SCHEDULE FOR PROCESS HAZARDS REVIEWS CHEMICALS GROUP - EXISTING FACILITIES 25 SEPTEMBER 1980 Fad 11ty/Process/Product Escambia - Area MB" (AN, Urea, etc.) South Brunswick - Ethylene Handling, Raw Material Handling, Balance of Plant Escambia - Methanol Project Escambia - Higher Amines, Amines Storage and Handling Calvert City - Pipeline Systems Escambia - Nitric Acid #1 (1) Escambia - Methanol (existing) (2) Calvert City - PVOH Escambia - Amnonia (2) Paulsboro - Catalyst Plant, Utilities and Waste Treatment Escambia - Nitric Acid #2 (1) Escambia - Ammonia Recovery and Storage Calvert City - Emulsions (Remainder of Plant = A.F. #1 and #2) Escambia - Boilers and Utilities Pasadena Nitric Acid (1) Escambia - Waste Treatment Pasadena - Pipelines, Strippers and Utilities Calvert City - Boilers and Utilities Cleveland - RP, Methanol Handling, Utilities and Storage Pasadena TDA Dates Scheduled 17 Oct. 80 27 - 31 Oct. 80 28 - 31 Oct, 80 * ffjJL VVuyyifv* . if JiC 10 - 14 NOV. 80 10 - 14 Nov. 80 1-5 Dec. 80 8-12 Dec. 80 12 - 16 Jan. 81 2-6 Feb. 81 Uvr^ 13a ^ * Plift TiHWHUor ^ GAL Hi JG 2-6 Feb. 81 2-6 Mar. 81 4 - 8 May 81 Vh'cr Ttawpis'Joe 15 - 19 Jun. 81 6-10 Jul. 81 13 - 17 Jul. 81 13 - 17 Jul. 81 TfrVstfrues1 4- Jexrw^ 10 - 14 Aug. 81 10 - 14 Aug. 81 24 - 28 Aug. 81 7-11 Sep. 81 a?- \U flr AP00036324 (2) ' Facl Hty/Process/Product Calvert City - Catalyst Plant Escambia - Methyl amines City of Industry - Total Plant Dates Scheduled 7 - 11 Sept. 81 7-11 Sept. 81 14 - 18 Sept. 81 w On Hold: Calvert City - PVC Escambia - PVC Notes: (1) Use common team members (2) Use common team members AP00036325 A&$k7%odic& cutei C&emicti$- ESCAMftIA PLANT IftlC. INTEROFFICE MEMORANDUM To: R. E. Jones From: Re: D. D. Hurder Process Hazards Review No. 2 Amines Plant Dote: 4 December 1980 Copies: G. D. Cooper WO/A L. S. Forester WO/A Attached is a copy of the recommendation section of the process hazards review. Please review the recommendations and relay any questions or comments you may have so they can be addressed by the hazards review committee. A formal transmittal of the recommendation will be made after your comments have been addressed. The recommendations are rated on a priority basis of 1 to 5 with 1 being items of highest priority. The severity of a hazard has been rated as high, medium or low, where: High Severity Medium Severity A hazard which may cause a lost time accident or an excessive property loss. A hazard which may cause damage to equipment or an injury other than lost time. Low Severity A hazard which may cause minimal property damage. The probability of a hazard has also been rated as high, medium or low, where: High Probability A hazard which has occurred in the past or requires only one primary cause. Medium Probability A hazard which requires a combination of two primary causes. Low Probability A hazard which requires a combination of three or more primary causes, or one or more secondary causes. DDH:ms D. D. Hurder AP00036326 > V oo U4 On W K5 Category: f ^Equipment Changes I ^Procedural Changes, Inspection & PM rterns f (Eng Studfes I /Rejected Status as offlecaaber 1, 19___ SO Page 1 of___ ^Pages Management Action Needed Action Items from Hazard Review ZO Hazard >. Responsi bility Recommendations ee oo Tc- ooOE.n+aJJ u4So_- E5. -0nM> q 1 Chemical release resulting from M H 1 incomplete combustion of an un controlled surge to the flare. 2 Vehicles driving over the flare line could cause the line to rupture. H M1 3 High temperatures in the gas fired heater could cause coil failure. H H1 4 The vent line on storage tanks 68202, 205, and 206 can be booked in, eliminating any means for pressure relief. H M1 5 Vessel rupture of the low pressure absorber. HM1 6 The recirculation line between H L 2 the low pressire absorber cooler and its absorber can be blocked in causing overpressure in the cooler. 7 600 psi steam can be added to the separation column reboiler causing vessel rupture. HM2 Emert Emert Emert Emert Emert Emert Emert Install a properly designed flare with adequate safety controls. Barricade the make shift road passing over the flare line. Upgrade the heater controls to meet minimun requirements. Remove the block valve between the tank and the seal pot. 12/81 3/81 12/81 5/81 Pressure rate the low pressure 12/81 absorber and install a relief vldlve. Remove the block valve between f'e cooler and the low pressure absorber. 6/81 Remove the 600 psi jumper line : r 12/81 rerate the reboiler to 600 psi. Action Status Remarks (Include Estimated Costs) $50,000 No cost $20,000 No cost $2,000 No cost A new reboiler rated at 600 psi is on order. Category: fx jEquipment Changes [~ lProcedural Changes, Inspection 1 PH Items | |Eng Studies 1 [Rejected Action Items from Hazard Review ^ ^December Status as of;1, HT P9C of j Pages , BO Action Status Management A c tio n Needed Hazard 41 ^ o >a1i POu. XDu-. ** < Response btltty Recommendations u MM U41 m+c*J- uoQe.qn*O Lp*-uQeo.a*a*/ 8 Cooling water on exchangers can H L 2 be blocked in causing over pressure and possible rupture of the lines and/or exchangers. Emert A relief valve should be placed on the cooling water lines for all exchangers. 12/81 9 Loss of ttie nitrogen blanket on the 116 tanks could cause a vessel to collapse from vacuum. 10 Vacuum can cause collapse of tank 68213. 11 Uncontrolled fire in the gas fired heater. 12 A flame can back up the vent of the product storage tanks. H M2 H M3 H H3 K L3 Emert Emert Emert Emert Provide vacuum relief for all 116 tanks. L2/82 Provide vacuum relief for tank 213. 12/82 Install a steam.snuffer in the gas fired heater. 12/81 Install flame arresters on all 12/SI storage tank vents to the atmospherje 13 Purap/motor failure can cause overheating and possible fire in process lines. H L3 Emert Install discharge pressure gauges L2/81 on all pumps. 14 Vehicles in the area could strike equipment located adjacent to the roadway. 15 Inadequate dykes may not restrain a liquid spill. M L3 Emert M L4 Emert Install an access gate on the road 5/81 by the converter. All dykes that are not in good repair should be upgraded. 12/82 16 Employee,'exposure to hazardous process chemicals. KH4 'Emert All sight glases should have drain: 12/82 and all pressure gauges should hav< bleeds. Remarks (Include Estimated Costs) $5,000 $30,000 $2,000 $20,000 $25,000 $10,000 No cost $50",000 + on-going major maintenance. $10,000 AP00036328 Category: | X (Equipment Changes | [Procedural Changes, Inspection & PH Items j " " ^ ng Studies I (Rejected `Status as ofjfecsnber-- Pftgo 3 o f 3 Pages papN uo^ov ^usuraBeueN uo}}3 |,dtuoo qSEOaJOJ s;bq uoj4a[duioo imiui T"3 8J .3Oc 3 ** 4Voi-.> ><uoU. a. 3 3fO i--0 ** <UcWr'*H*-*3 A->uT* uc>n3V I /^UOLJtJ | I Q. QJ 2i- fli AP00036329 Category: 1 jEgulpment Changes 1 x" |Procedural Changes, Inspection & PM Iteas I ^Eng Studies l'~~]ReJected Action Items from Hazard Review -Status as of___j2ecsnbL_J > Page 2 of____ j^Pages Action Status Management A c tio n Needed H^zard >, r- > i- ja i- ** 3 Responsf* Wtty Recommendations 0 41 4fOA 4? --4vc--vJ*oI--t6Sldcov>/ WOt0o-1 fOQeo* .D+4t*a3> Chemical release due to incom plete maintenance MM3 Emert All work permits should be 1/81 signed by production personnel after visual Inspection and approv . of the work. 2 Lack of operator knowledge about the fire water system could delay efforts to control a fire or chemical spills. MM2 Emert A diagram of the fire water pro-' tection system should be posted In the control room and covered in shift safety meetings. 3/81 3 A chemical release can result fron poor welds on pipes and equipment. MM3 Emert A small percentage of all new main 1/81 tenance welds should be x-rayed. A hydrogen leak in the area of the gas fired heater could cause an explosion. HL 3 Emert All flanges in the immediate vicinity of the gas fired heater should be bubble tested for leaks while on nitrogen during start-up. 1/81 Chemical spills or unwanted MLS chemical mixing could occur from an Incorrectly turned blind. Emert A blind list should be prepared an 6/81 a systematic method of changing lines during turnaround should be studied. 6 The dirt and sand that is cover- L M 4 ing the sleeper racks by the 10 track loading rack can accelerate corrosion and cause a chemical spill. Emert The sleeper racks should be kept clpan of'dirt and sand. 6/81 Remarks (Include Estimated Costs) No cost No cost S5,000/year No cost No cost No cost AP00036330 > HB OO O 0o>4 04 04 Category: j (Equipment Changes I 1 Procedural Changes, Inspection 4 PH Items | x |ng Studies 1 IRejected Status as of December Pago 1 of____ 3_Pages I,' ISM Action Itens from Hazard Review O Hazard ResponsfHI tty Recommendations c o ia <u u o. oi -- E +- meuoon uo v +> 3* a a. (- e+- iokuoQsi 1 Overpressure in vessels causing rupture. HH1 Forester The relief valve slzfng verifi 12/82 cation program should be institute^ This should include checks of reli valve piping supports, outlet pipiji and valve sizes. It may be possible for process chemicals to back up Into the nitrogen system. HM2 Emert A hazards review should be perforn - 12/81 ed on the nitrogen system. It was not known if the dis tillation columns are vacuum rated. HL3 Cooper All columns should be checked for 6/81 vacuum rating. , Uncontrolled fire In the area. H L 4 Henry Review the fire water protection for the area. 3/81 Internal vessel fire from a static charge HL4 Cooper a) Determine if all top loading storage tanks are equipped with dip tubes and install vrtiere needed. 6/81 b) The grounding system in the plant should be checked to Insure that all equipment is , properly grounded. c) Determine the conductivity for the major No. 2 plant chemical 6 A hydrogen release from the recycle compressor could be ignited by an internal com bustion engine in the area. HL3 Emert The procedure for allowing internal 6/81 combustion engines in the area should be reviewed. Action Status Remarks (Include Estimated Costs) No cost No cost No cost No cost No cost No cost Management A c tio n Heeded M-1 \Category: 1 [Equipment Changes {Procedural Changes, Inspection & PM Items | X |Eng Studies I Rejected 'Status as of December Pgc 7 of____ 3j>ages 1 IS Action Items from Hazard Review so e0/ Hazard => z0>) *.OQ3 iOof afc.. Response htltty Recommendations: co v1t-9a--9) n f- E *- COM MOO <t-u ae aj iOi.uO aJ 7 The high pressure absorber knockout pot is rated at a lower pressure than the high pressure absorber and must be pressure relieved through the high pressure absorber. HL3 Cooper Upgrade the knock out pot to the same pressure rating as the high pressure absorber. 3/81 8 The lines in the vicinity of ML4 the high pressure absorber can be overpressured if during shut down the lines were closed and the caustic feed left on. Cooper Insure that the caustic line 6/81 pressure does not exceed 330 psi. 9 The pressure rating of the ammonia column preheater bonnet, and channel cover was not known. ML4 Cooper Oetermine the pressure rating of the channel and bonnet. 6/81 10 The alkyl preheater must be vented through the alkyl vaporizer in the event of an overpressure. HL4 Cooper Determine if a relief valve is 3/81 required for the alkyl preheater. 11 Imbrittlement of the coil in the gas fired heater can cause a line rupture; HL4 12 The compressor can overheat and bind up from a loss of cooling water. Ml 4 Eroert/ Dean Cooper Investigate the possibility of 6/81 hydrogen imbrittlement. For IBN production determine if there is any possibility of zinc imbrittl en: it being caused by the zinc oxide cat lilyst. Investigate a cooling water failure for the compressor. 6/81 Action Status Remarks (Include Estimated Costs) No cost No cost No cost No cost $5,000 NO COSt APOO Oi 04 a. 04 04 Category: | ^Equipment Changes | |Procedural Changes, Inspection A PM Items j X )cng Studies {Rejected Action Items from Hazard Review status as of December Page _of____ j_Pages 1, ISO Action Status Management A c tio n Needed Hazard 4X*-"> 1jrC-- +*>Jr*, C U JO i- O a jo o v* 5 2 r t; V, a. o. cC _. ;*fP2nslv htltty Recommendations a ti g ai + a u u a ai *----COoEWo4J .utO-. oeO o+tt>t 13 An overpressure may occur in the vessels due to the heat of mixing of two chemicals. HL5 14 A flaauiafale atmosphere could Ht5 occur in the equilization tanks after a dehydration column upset. IS Catalyst dust during converter H L 5 charging could be toxic or cause an explosive atmosphere. Cooper Cooper Cooper Quantify the heat of mixing for the major chemicals used in the Mo. 2 plant. 6/81 Quantify the possibility of a 12/81 flammable atmosphere being formed. Investigate the toxicity of the catalyst dust and the possibility of a dust explosion. 12/81 Remarks (Include Estimated Costs) No cost No cost No cost AP00036333