Document byG58rqaJbeBpBa8YMwbvGa9D

1003 REV. 8-80 ESTAIUSWEO 1802 JE. J. d u Po n t d e Ne mo u r s & Co mp a n y INCORPORATED WILMINGTON, DELAWARE 19898 CHEMICALS AND PIGMENTS DEPARTMENT JACKSON LABORATORY TO: FROM: R. S. WEIS, J, L, A. MAC LACHLAN, B-17208 P. A. WRIEDE, J. L. COLORED PIGMENTS cc; L, G. Del Signore T. R. Hart A. W. Bauer, B-16235 April 15, 1981 1981 1st QUARTERLY TECHNICAL REPORT MONITORING Number Technical Reports Scheduled to issue Past Quarter Number Technical Reports Actually Issued Past Quarter m Reasons for Delinquent Technical Reports 15 __ 9 G. E. Crow - Limited secretarial help at Newarfc R. D. Nelson has delayed typing L. Kilmurry - Submitted too late to issue in first quarter - now being typed E. F. McBride - Not written - delayed to IIQ M. Toji - Submitted in February - issuing report at J.L. takes 3 months. Currently being typed. J. Neumer - Still Proofreading report originally due IQ-*80. N 27510