Document ba3DK6gj3xbMbXL1Oko1N51My
conoco)
Interoffice Communication
to R. D. Gamblin
From
J. H. Brunson
Date December 10, 1979
Subject
Explanation of Variances - August, 1979
During the month of August the plant produced 58,453,572 pounds of VCM and 93,575,506 pounds of EDC. The variances from standard costs were as follows:
August Efficiency Price
Total
______ Year-to-Date_____________
Efficiency
Price
Total
EDC VCM Incinerator Subtotal Fixed Costs Total
$(203,245) ( 28,771) ( 15,603)
$(247,619)
$( 993,866) $(1,197,111)
( 47,452) ( 76,223)
( 9011
16,504)
$`(1,042,219) $(1 ,289,838)
(88,737)
$1,378,575)
$ 163,742 $(2,159,423)
(255,741) ( 223,121)
(223,899)
7,595)
$"(315,898) $"("2,390,1397
$(1 ,995,681 ( 478,862 231,494
$'(2,706,037 74,590
$1276317447
FIXED COSTS VARIANCE
The unfavorable variance of $88,737 was due primarily to Moving, Home Assistance $11.2M, Maintenance Materials - $40.3M, and Maintenance Contract Costs - $106.9M. The above variances were partially offset by favorable variances for Ad Valorem Taxes - $13.4M, and Depreciation - $55.4M. Smaller variances account for the remaining differences between budget and actual costs. The major variances are explained in detail below.
Moving, Home Assistance - $11,153 Unfavorable
The unfavorable variance was due to the cost of transferring the Process Superin tendent from Oklahoma City to Lake Charles clearing in August and the budget amount being spread throughout the year.
Maintenance Materials - $40,347 Unfavorable
The unfavorable variance was due to incinerator costs greater than the budget $13.6M; and to the following ordinary items greater than budget - Warehouse $7.7M, Agitators - $4.5M, Pipe $3.8M, Instruments - $3.2M, Compressor - $2.4M, Reactors - $2.2M, Safety - $1.5M, Fired Heaters - $1.4M, Hose - $1.4M, and Electrical - $1.2M. This was partially offset by no expenditures in the extra ordinary budget - 2.2M.
CCR 000008812
Maintenance Contract Costs - $106,929 Unfavorable
The unfavorable variance was due to incinerator costs greater than budget $32.4M, extraordinary costs greater than budget - $42.1M, and to the following
ordinary items greater than budget - Air Conditioning - $1.2M, Agitators - $1.4M,
R. D. Gamblin
Page 2 December 10, 1979
Miscellaneous Structures - $2.3M, Piping and Valves - $16.7M, Safety - $5.9M, Towers - $3.3M, and Railroads - $1.8M.
Ad Valorem Taxes - $13,417 Favorable
The favorable variance was due to the revised estimated taxes for 1979 being less than the estimate at time of budget.
Depreciation - $55,414 Favorable
The favorable variance was due to the incinerator projects not being completed as soon as anticipated - $12.1M, the 1979 depreciation rate being 1% less than the rate used for budget purposes - $33.1M, and to plant capital invest ments being approximately $1 ,800M less than anticipated due to projects not completed as soon as expected - $10.3M. Major projects not completed as soon as expected were VCM Exposure Reduction - $248.2M, EDC Exposure Reduction $421.0M, and Stand-by Waste Water Steam Stripper - $392.0M.
VARIABLE COST VARIANCE
The total variable cost variance for August (including incinerator IPA variances) was $1,289,838 unfavorable. This unfavorable variance consisted of:
August, 1979
EDC/VCM
Incinerator
Raw Materials & By-Products Processing Supplies Utilities By-Products Handlinq
_
$(1,119,242) ( 10,670) (159,131) 15,709
$(1 ,273,334)
$ 6,557 ( 467) (22,594)
$0 6,504)
In the explanations which follow, the incinerator variances are discussed as a separate topic.
EDC/VCM
Raw Materials and By-Products - $1,119,242 Unfavorable
The chlorine price variance for August was $62.3M unfavorable and the ethylene price variance for the month was $920.5M unfavorable. The chlorine plus HC1 efficiency variance for August was $101.7M unfavorable. The ethylene efficiency variance is $34.7M unfavorable. This leads to a total raw material efficiency variance of $136,376 unfavorable. The cause of this unfavorable variance is direct EDC and HC1 losses as follows:
000008813 CCR
R. D. Gamblin Page 3 December 10, 1979
1) Direct EDC losses due to heavy ends colunn overhead condensing problems resulting in high vent rates of EDC to the incinerator.
2) Direct EDC losses from T-101 due to the malfunction and repair of BL-502 refrigeration system.
3) Direct HC1 losses due to poor conversion in oxy leading to high acid strength in the primary separator.
Estimates of these losses indicate that a vast majority (approximately 70%) are due to EDC losses. Five oxy shutdowns occurred in August. HC1 and ethylene venting during oxy shutdown and start-up also contributed to the above raw material variances.
Processing Supplies - $10,670 Unfavorable
The net price variance for processing supplies in August was $41.8 favorable. Significant price variances occurred with respect to caustic ($15.6M favorable), nitrogen ($7.0M unfavorable) and limestone ($27,OM favorable). The net efficiency variance for processing supplies was $53.1M unfavorable. Significant efficiency variances occurred with respect to oxychlorination catalyst, caustic solution, and limestone. Oxychlorination reactor R-304 was not re charged in February, 1979, and led to a favorable catalyst efficiency. HC1 conversion in oxy continues to deteriorate as the November turnaround approaches, leading to increased demand for caustic and limestone ($9.1M unfavorable and $5.2M unfavorable, respectively) for effluent neutralization.
Utilities - $159,131 Unfavorable
Price variances for electricity and steam were unfavorable in August at $14.8M and $42.OM, respectively. Waste heat steam generation in oxy was below budget in August, leading to an unfavorable efficiency variance in this area of $20.OM Natural gas usage led to an unfavorable efficiency variance of $4.2M due to the above-budget injection of methane into the R-101 vent for flammability control.
By-Product Handling - $15,709 Favorable
The price variance for tars disposal was $7.2M favorable in August. Light ends to sales ($2.0M favorable) increased in lieu of light ends transfer to the incinerator ($8.7M favorable) since light ends burning on a routine basis has not been instituted.
Incinerator - $16,504 Unfavorable
Routine light ends burning has not been instituted at the incinerator and caused a $3.9M unfavorable efficiency variance in the consumption of light ends. This
0000881^ OCR 0
R. D. Gamblin Page 4. December 10, 1979
lack of light ends burning has required an above-budget consumption of natural gas, leading to an unfavorable efficiency variance of $17.1M. The concentra tion unit was budgeted to be on stream in August and since this unit is still under construction, no anhydrous HC1 for dilute acid concentration was utilized. This resulted in a $10.3M favorable efficiency variance in anhydrous HC1 consumption. An unfavorable efficiency variance with respect to limestone occurred ($5.4M) due to the fact that all HC1 production continued to be neutralized. Increased caustic usage has been required at the incinerator for flue gas scrubbing ($5.1M unfavorable efficiency variance) due to increased vent rates and experimental light ends burning in August.
J. H. Brunson
APPROVED: is CC: JAD-JRH-HDG-TRC
CCR 000008815