Document bO1kyzDLzXormO0n7k0ve8Gk

Interoffice Communication To R. D. Gamblin - Houston From J. A. DeBernardi Oate June 12, 1981 Subject Maintenance AFE for Fireproofing Repairs The following criteria have been met for the subject AFE. 1) The project cost of $160,000 is based on a definitive estimate and includes an escalation allowance. 2) Funds will be committed for this project immediately after approval. 3) The entire project will be expensed. 4) Project completion is estimated to be four months after AFE approval. 5) This project will not change plant operating costs. br CC: JRH-JHB-GLF-JWW CCR 000067179