Document bBNw2ZprbpvVM0gVz6d1D6x8o
Georgia-Racific
intracompany memo
to Mr. H. W. Scharf
from G. W. Green
subject
AIRBORNE ASBESTOS SURVEY OF MILFORD. VIRGINIA JOINT CEMENT PLANT
cc: Mr. J. R. Hurd - Portland Mr. H. W. Peele - Wilmington Mr. G. F. Fowler - Marietta
location location date
Milford Tigard March 29
On November 25, 1975, the Milford joint cement plant waa monitored for asbestos dust by George Fowler. The filter cassettes were then sent to Tigard for counting. All the individual samples, thus all the time weighted averages, were below the 5.0 fibers/ml maximum currently in effect.
Five representative workers were sampled during an entire work shift and, in addition, area samples were taken at various locations throughout the plant. As at all the joint cement plants surveyed, the dry mixer man recorded the highest time weighted average and the highest individual count. This,is the only position which is over the 2.0 fibers/ml maximum which will be in effect in July, 1976.
A summary of the data as well as individual records and count worksheets are attached.
. ULOQ.
GWG/gvp Attachments
G. W. G.
MILFORD JOINT CEMENT PLANT AIRBORNE ASBESTOS DUST SURVEY
Date Sampled: November 25, 1975