Document b5Ln6gMGXrE1mvygVjg01MY56
To: D. L. Davis Houston
Faxed 12-9-85 3:32 pm
BJR
Interoffice Communication
hrom: Date:
Subject:
p. e. Markey December 9, 1985
1985 Cost Reduction Items LCVCM Plant
VISTA
As requested in your IOC dated November 15, 1985, we have prepared the following list of cost reduction items for the LCVCM operation.
I. Raw Materials and By-Products
A. Olin HC1 as an Oxvchlorination Feedstock
Estimated Annual Savings: $200M - $600M
Description: Piping and Instrumentation modifications were completed in June 1985 to permit import of Olin HC1 as an Oxychlorination Unit feedstock. The net effect of the project is to back out a portion of the more expensive chlorine used in the Direct Chlorination Area.
B. Waste Muriatic Acid Sales to Texas United
Estimated Annual Savings: $100M - $140M
Description: In November 1985 we began to sell low grade acid off the Incinerators to Texas United. The major thrust of the savings is attributable to reduced limestone and caustic neutralization costs.
C. Use of LCVCM Plant Muriatic Acid for Exchanger Cleaning
Estimated Savings in 1985 - $6M
Description: LCVCM Muriatic Acid was used in chemical cleaning activities at the LAB Plant and LCVCM during the 1985 turnarounds.
CUH OQOQO-5683
D. L. Davis Page 2
D. Exercising Contractual Take-or-Pav Relief on Oxvaen Purchases from Big 3
Estimated Savings: $52.5M in 1985
Description: The oxygen contract with Big 3
specifies a 15-day Take-or-Pay relief period if advance written notice of the outage is provided. Verbal notice was made prior to the 1984 turnaround and relief was not granted. Conoco was notified for possible recourse. It is important that the plants participate in contract preparation and that they have on file an executed copy. Line operation approval of invoices is desirable.
E. LCVCM Operation of Ethvlene Storage Terminal
Estimated Annual Savings: $500M - $600M
Description: In December 1984 the VCM Plant assumed operating responsibility for the Ethylene Storage Terminal in Sulphur, LA. The Terminal was formerly operated by Union Texas Petroleum. The Terminal is now under a 10 year lease to Vista.
II. Processing Supplies and Operating Supplies
A. Nitrogen Cost Reduction
Estimated Annual Savings: $170M
Description: i\ number of steps have been taken in this area:
Competitive bidding for ship and equipment purging results in nitrogen
costs of approximately 50 <t/100 SCF vs. $1.30/100 SCF list price.
Pipeline Leak Checks of lines and
associated
equipment
and
instrumentation.
Optimizing pipeline nitrogen usage. The contract with Liquid Air provides a double tiered price structure with the unit price increasing by a factor of 8 at 40,000 SCFH. Purging activities are structured to stay under the higher tier pricing level.
CUM 000005684
D. L. Davis Page 3
Nitrogen invoices are checked monthly by operating personnel for accuracy. (See comments under C>2 contract)
A backup liquid nitrogen tank was eliminated as redundant since existing gas bottles and compressor could provide the same service.
B. Polymer Optimization at Secondary Waste Water Treatment
Estimated Annual Savings: $15M
Description: Prompted by a vendor recently shutting down an area distribution terminal
the plant was faced with higher inventory and transportation costs. To avert these costs the plant screened polymers of competitive vendors and found lower dosages of lower priced polymers could be used
without adversely affecting the effluent water quality.
C. Modification of the Caustic Decanter# S-206
Estimated Annual Savings: $40M - $80M
Description: Engineering evaluations of this
vessel
determined
inefficient
phase
separation was occurring which resulted in
increased Flake Caustic consumption in the
downstream dryers. A cross sectional baffle
and redundant level instrumentation were
installed to improve the decanter's
operation. The primary driving force for
the study was to reduce monomer alkalinity
and thereby improve product quality. The
Flake Caustic savings were an added benefit.
D. Cooling Water Treatment Improvements
Estimated Annual Savings: Not Quantified
Description: In December 1985 the plant
switched cooling water treatment vendors,
the treatment system (phosphate to zinc) and
reassigned sampling from the lab to
operations. Results to date have been
favorable with reduced corrosion, reduced
fouling and better overall system control.
The improved cooling water treatment was a
contributing factor of the extended run
leng* th recently achieved.
CWH O00010Ab(r6/8Qvtrj
D. L. Davis Page 4
III. Utilities and Energy Conservation
A. Air compressor Control Scheme Revisions. BL--302
Estimated Annual Savings: $73M
Description: Based on Engineering studies of the plant air compressor it was determined a closed control scheme with modified load and unload set points could save energy* The changes were made in October 1985 with no surge problems encountered. The change will save an estimated 1,350,000 KWH annually.
B. EDC Purification Reflux Pump Replacement
Estimated Annual Savings: ?28M (Capital Cost: $33M)
Description: Operational changes and lower by-product production associated with the new oxygen-based process have reduced tower reflux rates on the purification columns to the point the pumps were operating well under their rated capacity. To energy optimize the system, two smaller reflux pumps were purchased and installed and two pumps were relocated on the 1985 turnaround.
C. Exercising Contractual Take-or-Pav Relief on Electricity Purchases from GSU during 1985 Turnaround
1985 Turnaround Savings: $10M
Description: During summer months the LCCC contract with GSU provides for electrical Take-or-Pay relief provided GSU is notified of the Megawatt reduction 30-days in advance in writing.
D* Cracking Furnace Efficiency Improvements
Estimated Annual Savings: Not Quantified
Description: Cracking Furnace improvements were a key factor contributing to the Fiscal 1985 Production and Energy Conservation Records. The improvements included:
CWH 000005686
Replaced bad order refractory in both heaters with new fiber type refractory.
Replacement of all burner tips
Revised decoke procedure
Increased use of cracking promoter to maximize production rates.
A1 Thomas was brought in during the 1985 Turnaround to assist in evaluating and inspecting the cracking furnaces.
A number of improvement areas were identified.
Maintenance Cost Reduction Projects
A. Acid Circulation Pump Replacement
Estimated Annual Savings: $11M Cost: $33M)
(Capital
Description: Eight (8) high maintenance lined steel pumps were replaced with fiberglass pumps in the Incinerator Area.
B. EDC Tar Stills Pump Replacement
Estimated Annual Savings: $15M (Capital Cost: $6M Miscellaneous Funds)
Description: A high maintenance diaphragm pump in heavy ends service was replaced with a surplus centrifugal pump with a double mechanical seal and flush system in October 1985. The replacement pump has performed very well to date eliminating a chronic maintenance and potential safety problem. An alternate capital project was being considered to install a Pressure Pot Transfer System at a cost of $80M. Based on the pump's performance to date the higher cost capital project will not be needed.
C. In-plant Railcar Relief Valve Maintenance
Estimated Annual Savings: $20M - $30M
Description: VCM railcars are required to have their relief valves changed every 5 years. The work is now performed at the plant vs. an outside shop.
CWH 000005687
D. L. Davis Page 6
D. Utilization of Transportation Terminal for LCVCM Road Vehicle Maintenance
Estimated Annual Savings: $5M
Description: During Fiscal 1985 the VCM Plant phased out the use of contract road vehicle maintenance and now utilizes the S&T Terminal to perform routine maintenance on road vehicles.
E. Identification of Improved Oil Seal for Ethylene Recycle Compressor. BL-307
Estimated Annual Savings: Not Quantified Seal Cost: $33M
Description: Based on discussions with LCCP they were able to reduce oil leakage substantially by utilization of the new "G" Seal in their Elliott 29M Compressor. LCVCM has budgeted the purchase of a "G" Seal for the Ethylene Recycle Compressor, BL-307. Oil leakage into the Ethylene may be a contributing cause to pressure drop in the lead Oxychlorination reactor which is the primary limitation on plant run length between turnarounds.
F. Phase Out of Loose Teflon Lined Vessels in Corrosive Service
Estimated Annual Savings: Not Quantified
Description: The VCM Plant has had poor success using loose teflon lined vessels. The loose liners are prone to leaks and difficult to repair. All of the plant's three (3) loose lined vessels were replaced with bonded lined vessels in 1985.
G. Redesigned Reboiler Bundles
Estimated Annual Savings: Not Quantified
Description: The plant has experienced high cleaning cost on the Light Ends and Heavy Ends column monel reboilers. A new design with a rectangular pitch vs. a tight square pitch made of carbon steel is being
CWH 00000568B
D. L. Davis Page 7
evaluated along with the use of carbon steel metallurgy. The changes should result in lower initial cost and reduced cleaning costs.
V. Miscellaneous
A. Use of Personal Computers
Estimated Annual Savings: $7M
Description:
Personal
computers
were
utilized to reduce use of the more expensive
EDS system.
If there are any questions, please advise.
P. E. Markey VCM Plant Superintendent
br CC: RTF-RAC-GEH
CWH 00000568?