BUSINESS PLAN FOR REPLACEMENT OF
PCB DIELECTRICS
1) Capacitors a) Selection of MCS 1238: properties, advantages, vulnerability.
b)\ Site selection issues.
c) Events chart
d) Alternatives and fail-back positions
e) Approach to economic evaluation.
2) Transformers a) Selection of a candidate: possibility of a franchise position. _ IaP --1;
c) Retrofit opportunity. 3) Impact on other polyphenyls derivatives
a) Economic dependence. b) Areas for further study.
Sw 185160
STLCOPCB4051406
TIMING Jan. 1976
ACTIONS
CONTINGENCIES/CHECK POINTS
Feb..1976
1/31 1/31
Analyze Federal testing protocol if required.
Research geared to 40M pounds/month production.
2/2
2/9 2/15 2/16
Decision on location for interim MIPB & TXS.
Complete pricing study for both short and long term.
Decision on sites for in house manufacture of MIPB and TXS.
PED for TXS by TSC1 route from Research to CED.
Visit to GE on pricing.
Visit to Westinghouse on transformer blend grade change.
1/21 AR approval of WGK interim blending project.
2/2 AR approval for MIPB flashing
V9VS8V I* s a
TIMING March 1976
ACTIONS
3/1
CONTINGENCIES/CHECK POINTS
Feedback from GE able response.
Need favor-
April 1976 May 1976
3/15
PED for MIPB from Research to CED.
3/15
Complete business/economic review for go/no go recommenda tion to CAC.
Vl Customer commitment to interim manufacture program.
4/15 Results of various acute toxicity-
tests.
'
Final shipments of 100-42 to Westinghouse.
DSW 185162
TIMING ' June 1976
ACTIONS
CONTINGENCIES/CHECK POIl^o
PIR approval on project for In-house manufacture of MIPB and TXS.
-
.
6/15 *
Decontamination of used equipment for MCS 1238 blending complete.
July 1976
Results of various feeding studies.
AR approval for debottlenecking of blending system.
DSW 185163
TIMING August 1976
ACTIONS
CONTINGENCIES/CHECK POINTS
Sept. 1976
8/15
Release tank cars from Aroclor 1016 service for decontamination and con version to MCS 1238 service.
9/1 Start up WGK blending
9/1 90 day feeding test results on MIPB and TXS.
9/15
Demonstration of rate and quality at WGK.
DSW 185164
TEk. .G October 1976
10/1
ACTIONS Begin shipments from WGK.
CONTINGENCIES/CHECK POINTS
10/15 ARDT from CED to Roger Beal.
AR grade sales forecast to Roger Beal.
Customer long-term commitment to 1238.
November 1976
STLCOPCB4051411
11/15 Final draft AR complete.
COO' O
(Jt
TIMIhwr December 1976
ACTIONS',CONTINGENCIES/CHECK POIluS
AR approval for in-house manufacture of MIPB and TXS.
1st Qtr, 1977
CED begin Project Definition Report.
i
DSW 185166
TIk. .to 2nd Qtr., 1977
ACTIONS
CONTINGENCIES^ CHECK POINTS
,8/77 Begin field construction of MIPB and TXS Facility.
6/77
90-day results from chlorine
feeding study.
3rd Qtr., 1977
DSW 185167
TIMING 4th Qtr., 1977
ACTIONS
CONTINGENCIES/CHECK POIN.o
12/77 Pinal shipments of Aroclor - 1016.
Begin decontamination of equip ment and tank cars.
1st Qtr., 1978
1/78 - 6 month inhalative study results.
Decontamination work complete.
DSW 185168
TIMING 2nd Qtr., 1978
ACTIONS
CONTINGENCY/CHECK POINTS
3rd Qtr., 1978
4/78
Results of 2 year chronic studies on MIPB & TXS.
4th Qtr.a 1978
Startup in-house manufacture of MIPB & TXS.
Demonstrate rate and quality.
DSW 185169