Document aDe21Oym3Zx6b9Dv0VxbjND6e
^iwrANY CONFIDENTIAL
* Monsanto
Anniston Plant
TECHNICAL SERVICES DEPARTMENT
MONTHLY REPORT
Anniston
Summary
C. K. Eastman A. G. Hill L. C. Lahman J. C. Landwehr G. W. Miller W. B. Papageorge W. F. Taffee H. L. Williams
Month
September, 1969
Cost Improvement Results
Est, Act. ______ Target
$63,120
$66,285
% of Target 95.2%
General Offices
YTD
$430,976
$438,570
98.3%
H. S. Bergen H. C. Carder D. Danna (5) P. B. Hodges D. B. Hosraer (2) W. A. Kuhn J. A. Morgan W. R. Robirds J. E. Smith J. A. Stephens R. J. Stratmeyer H. S. Trail
Organic Division
The Solid Aroclor 5460 yield increase instrumentation has been installed. Calibration and start-up will begin when 5460 is produced in early October.
The Sandvik belt test on Montar 5 was successfully completed. Installation costs will be estimated in October.
Muriatic Acid - MIP was reviewed in plant on 9/10. Necessary revisions to be completed during October.
Agricultural Division
The Acetone Recovery project was verbally approved 9/29 for $32,125 capital and $28,600 expense. Expected savings are $40,000/yr.
OTHER LOCATIONS
A. H. Forsten Alvin, Texas
D. W. Jackson WGK
C.E.D. has suspended scoping and estimating activities on original Sulfur Recovery Project and will evaluate alternates to obtain the major yield savings at a lower capital cost.
Niran - Tentative Process Amendments are being prepared for plant trials of Freon-21 replacing Freon-11 as chlorinator coolant and HCl replacing nitrogen as chlorination sparge gas.
T. M. Patrick So. 2nd St.
DSW 551246
>4-306 REV. 11/1/196
COMPANY CONFIDENTIAL INFORMATION
"This document contains confidential information which is the property of Monsanto Company. Only those portions of the document relevant
to a duly authorized individual's need to know may be exerpted for him. The report must not be sent outside the Company without written
pnnrm/dl anrl Iho i
iant ic -irmiinloMa fnr itc coffl l/aanlnrr nvomflnn flr ntknrminn <4 i fI/. o I n nf I f r.
-,^,4 frtr If o
A I r> r. n e- *5 I "
STLCOPCB4089663
.Company Confidential 2
Utilities
Evaluation of Central Air Compressor system started, with December report target.
Design & Drafting
Data being gathered for electrical protective device study which will lead to recommendations to improve reliability of overload protective devices in important feeders.
Construction drawings forwarded for Biphenyl Pilot Unit building and Parathion emergency generators.
Pollution Control
HC1 neutralization pit continues to successfully treat all waste acid.
Construction 957. complete on test unit for removal of solids in Waste Treatment Plant effluent. Start-up targeted for early October,
Quality Control
The Plant Quality Score was 86.1, down 7.6 from August with a YTD score of 88,1 against a 1969 target of 95.0 minimum. Unfavorable trends continue in Aroclor 5460 solubility, Aroclor 1242 low dis tillation and TC Chlorides. Raw material benzol remain at low distillation level, with intermittent high toluene.
1
DSW 551247
STLCOPCB4089664
ORGANIC DIVISION 1969 TSD COST IMPROVEMENT
ANNUAL JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Sol.Aro.Level TAR
.Ind.& -Still SpG EST
AFE 3015
ACT
Solid Aro.
TAR
Lower 5060 Soft. Point
EST.' ACT
2250 2250 2p50 2250 250 50 2250 2250 2250
--
---
~
--
2600 2600 600. 2$00 600 6oo 600 600 ?6oo 1500 5490 4090 215C 467 C 8000 4230 773CP 3475 1500 5490 48 90 2150 467 C 800C 4^U 7730
-
--
Sol.Aro.-Still Coolant temp.
AFE 3015
TAR EST. ACT
160 170 160 I.7O 160 170 160 170 160 -"
Sol.Aro. -Chlortcc TAR
Batch End
EST;
AFE 3015
ACT
390 390 390 390 390 390 390 390 390 - - - -- '-
". ** .
Sol.Aro. Yield TAR
SW/R Composition EST.
AFE 3016
ACT
Solid Aro.
TAR
Montar 5 Flake EST;
AFE P949
ACT
2750 750 2750 2750 2750 2750 2750 750 -"
1080 1080 1080 1080 1080 1080 1080 1080 - --- -"
Sol.Aro. Blend 4465
TAR EST :
ACT
2500 2500 2500 2500 500 2500 2500 2500 2500 2500 500 2500 1690 1920 1600 1490 710 1180 990 22U 1690 1920 1630 14 9 C 710 1180 990 220
Sol.Aro.-Verti- TAR
cal Still Cond. EST'
AFE 2324
ACT
70 80 70 80 70 70 90 90 9 0 90 - . 70 90 90 90 90
--
"
Sol .Aro.Cl2 T/C Dock AFE 2342
TAR EST, ACT
940 940 950 00 "-
Sol.Aro.-New Cl2 TAR
Unload - No Delay EST'
CED 1851
ACT
Solid Aro.-Flake TAR
& Drum
EST.
CED 1450
ACT
Liq.Aro.
TAR
48-53 M #/yr. EST
AFE 2545
ACT
O'
OOro;
950 940 950 940 950 940 950 900 2330 5050 232O 1650 900 2 350 2050 2320
5000 3000 5000 5000 5000 5000 5000 5000 5000 5000 5000 5000 0 0 1000 2000 2000 2000 300C 3000 3000 0 0 1000 2000 200C 3000 300C 3000
3000 - - - - - - - - - -
0 550C 0 550C -
--
--
"
Liq.Aro.-No.2
TAR
3000 3000
Still Entrain Sep. EST;
AFE 5095
ACT
Liq.Aro. -Montar TAR
Disposal
es.t;
AFE 2952
ACT
1080 1080 1080 1080 1080 1080 1080 1080 1080 1080
0 00
00 0 -
0 00
00
"
Warehouse
TAR
Reduce Manpower EST;
CEA 1452
ACT
2000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 2000 2000 200C 3000 3000 3OOO 300Q 300C 300C 2000 200C 20 CO 3000 3000 3000 3000 3000
Liq.Aro.New
TAR
Burners #3 Still 'EST
ACT
1500 1500 1500 1500 1500 1500 1500 1500 1500 1500 0 0 1500 3000 900 0 0 0 1500 3000 900 -
Biphenyl Relocate TAR
No. 1 Preheat EST
CEA 1892
ACT
500 500 500 500 500 500 500 500 500 500 500 500
1500 0 1560 1870 . 0
0 TSTJU 0
-
150C 0 6 10 1370 0
0 1500
HB-40
2nd Autoclave AFE 5102
TAR
EST ACT
3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
2230 2580 0 3490 242C 0
600 600
9000 10,400
6000 8600
5600 4200 7450 6950
500
DSW 551248
STLCOPCB4089665
ORGANIC DIVISION 1969 TSD COST IMPROVEMENT
4
ANNUAL JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Bi0 Improve Tower Treat. AFE ^155 Improve Pit. Power Factor
TAR
EST ACT TAR EST ACT
450 450 450 450 450 450 450 450
0- U
0,, 584 645
00
0 585
900 900 900 900 900 900 900 900 0 500 900 900" 900 0 500 83O 990
Central Air System
TAR EST ACT
1000 1000 1000 1000 -
Optimize Rx Time PNP
TAR EST ACT
2500 2500 2500 2500 2500 2500 2500 2500 2500 2500 2500
0 3420 0
0 0 2940 1260" 0
0 3420 0
0 0 2940 2370
Reduce Mole Ratio NaOH/PNCB PNP
TAR EST ACT
4000 AOOO 4000 4000 4000 4000 4000 4000 4000
0
00
0u0
0 00 0 0
New Wash Water Pump ~ PNP AFE 2998 Automatic pH Control PNP
TAR EST ACT TAR EST ACT
50 50 50 50 50 50 50 50 25 50 50 50 50 50 50 50 25 50 50 50 50 50 50
500 500 500
HC1 Filter Pump
TAR 33 330 340 EST 530 330 340 ACT 330 33O 340
New Blow Tank HC1
TAR 200 200 200 200 200 200 EST 200 200 200 200 500 200 ACT 200 200 200 200 200 200
150,000 Gal.-HCl Storage Tank AFE 2468
TAR EST ACT
1760 1760 1780 1760 1760 1780 1760 1760 1780
-
u -
0 2640 3290 2990 0 2830 343O
Produce Staley Grade Acid AFE 5076 Cla Plt, Shutdown
CEA 1851
TAR EST ACT
TAR EST ACT
790 7$0 7?Q 780 780 790
--
8880 8880 8880 8880 8880 8880 8880
8880,
+2885 L9900 k'1990C
223C 6655 k2855 19900
Hg Recover from Residue
TAR EST ACT
250 f?30 250 250
3910 0
00
3910 0 0 0
Hg Wash Tank
AFE 2802 Biphenyl Productivity
TAR EST
ACT TAR EST ACT
250 250 250 250
o0 00
0u 00
5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600 5600
0 9U0U 15,OCX. 0
0
0 3(573$ [2700 0
1800 5900 13503 0
0
0 3078C 2700
Total Organic By Month M $
Total Organic YTD M $
TAR
EST ACT TAR EST ACT
230 26". 3 29.3 37.5 42.P 51.1 51.6 51.6 51.6 52.7 53,5 50f6
27.1 30.2 11.5 36.3 395o5 107.4 153.844 ,49.41C 16.5 23.3 27.3 11.4 25.75 45.9 110.22 958.16
23.3 50.1 79.4 116.9 159.? 210.3 2615
365.1 417.8 471.31 521.9
46.9 78.8 79.6 1159 144.4 |253.5 315JL5L 368.86 5 16.5 40.3 68.1 79.5 105.2 151.1126I.2S 319.45 2
* $2^955 adjustment included for May & June.
** $27,780 adjustment included for months
January thru June.
DSW 551249
STLCOPCB4089666
>
'
.
AG DIVISION 1969 TSD COST IMPROVEMENT
ANNUAL
Cooling Tower
TAR
Repiping AFE 2598 Optimize N2 &
EST ..-ACT
TAR
Cl2 Levels
EST
ACT
Increase Waste
TAR
Acid Sales
EST.-
ACT
Chlorinator R.I.
TAR
EST
AFE 2244
ACT
EVOP Condensation TAR
Rx. EST'
ACT
Cl2 Unloading
TAR
ES.T
CEA 1851
ACT
Recycle Wash
TAR
Water
EST
AFE 2960
ACT
Parathion Recovery TAR
EST
AFE 2655
ACT.
Reduce Acetone
TAR
Losses
EST
ACT
Formulations
TAR
EST
AFE 2897
ACT
Change Cooling
TAR
H^O Item 737
EST
AFE 5067
ACT
Well HgO to Jets
TAR
EST
Ag. Division by Month
ACT TAR
EST
ACT
Ag. Division YTD
TAR EST
Ag. Division
ACT TAR
untargeted-R .M.
EST
Charges optimizatii rACT
Organic Div.
TAR
Untargated,.- HC1 EST
Catch Tank& Coale; eACT
Ag Div.-Untargeted TAR
EST
^3 Cl2 change out ACT
JAN
750 0 0
750 0
750 0
FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
4?0 420 410 410 420 420 410 420 420
0 00
00
0
0 00
00
6600 6700 6700 6600 6700 67 00
0 00
00
0
0 00
00
400 500 300 400 300 3OO 400 500 400 00 0 0 00 00 0 0 0
250 250 250 250 250 250
00
0
00
750 500
500 750 750
0 12,615 0 12,615
5000 5000 5000 1200% 2000 2000'
0 0 1580 00
290 290 290 290 290 290
00
0
0. 0
580015800 5800 j i
43OO 4500 4500
1600 1600 1600 1600 1600 1600 3000 6600 lOjCa 4570 2000 3950 5300 10,400 9285 4570 1205
125 125 125 125 125 125 125 125 125 120 130 155 272 333 310 120 ISO 171 272 333
500 500 500
750 50C 9145 9145 9155 14fv5 1A68 5
14575 .1 AA3 5 14485 .
1215 3,12C 6,780 10,155 4842 4033 13,710
0 1215 '+,420 10,580 9459 484: l 6488
1500 POOC 131*5 2029 0 29k2i A41 no 58785 7347 a 8 8 045 1025 117015 12,65 15,735 25,815 37,770 41,936 Wi' 6^114
0 12,65[17,035 27,615 57.07441,916 48,4%
0
1700 369C
1700
0 00 0
5000 6250 596C 4690 133OC 0 935C 6817 4920
4180 3250
DSW 551250
STLCOPCB4089667
AROCLOR
' Company confidential 3.
E. E. Bowles, C. R. Mcllwain, J. W. Mattern, (V. R. Haupt)
Evaluate Quaterphenyl-
Polyphenyl Effects on
1969 Savings $63>200 TSD Objective
Solid Aroclor YieldsNFC __________ $14.000B - 8(a)
Radioactive source for level alarm installed. Representative from Ohmart Corp. conducted radiation survey and instrument checkout. Start up delayed because of department downtime and producing Solid Aroclors other than 5460. Expect to start mid October.
Montar Use and Disposal
Savings $13,000
Project 2952 ____________________ NFC
$10.000B - 8(e)
TSD Objective
Request to change route of piping to avoid going through the Chlorine plant has delayed installation of project. Necessary equipment delivery date is estimated at 4-6 weeks.
Sandvik Belt Cooler for
Solid Aroclor Expan-
TSD Objective
Montar 5 Solidificationsion EvaluationB - 8( i)
The Pilot Unit Testing has been successfully completed with good results. Price and size estimations have not been finalized. However, preliminary "ball park" figures show that a belt to handle 8000$/hr. requires a cooling width of 4 ft. x 55 ft. long. The purchase price of this size unit is in the 35 M dollar range.
Porocel Columns
Assist
CEP 2152___________ __________ _______ ProductionTSD Job No. 950
North Porocel columns to treat chlorobenzenes were started up on September 19, 1969. Results of first trial were inconclusive. Further quality improvement tests are planned.
The start-up of the South columns has been delayed by the Aroclor fire. Start-up is now planned for the week of October 6, 1969.
BIPHENYL-SANTOWAX
W. G. Niemeyer, D. A. Self, J. M. Jones, (V. R. Haupt)
Debottleneck Biphenyl-
Santowax Distillation Area
Capacity
TSD Objective
to 87.6 M lbs./yr. BiphenylIncreaseB - 7(a)
Installation of by-pass loops with blow-out connections for the two Santowax C flow meters was scheduled for 9/10/69. However, only about one fourth of the planned work was completed. The problem was that the operators were not able to unplug the recycle line and it was not safe to cut and weld on the line. Maintenance is now scheduled to unplug the line. A capacity/performance test run will be conducted on the Santowax distillation column after the meters are re-installed and calibrated.
j DSW 551251
STLCOPCB4089668
)
BIPH5NYL-SANT0WAX - (continued)
Company confidential 4.
Low Biphenyl Santowax
Sales
for FDA 5460
________________ Support
TSD Objective B - 7(b)
A tower water loop study is in progress to try to increase the cooling water flow to the Biphenyl/Santowax distillation area. Increased cool ing water flow to the distillation area is required to produce low biphenyl Santowax.
Prediction and Control of Dust Explosion Potential in Biphenyl Flaker Packaging System;SafetyTSD Job No. 931
At our last plant meeting on this problem, we decided to convert the biphenyl packer from fluidizing with air to fluidizing with nitrogen. However, the estimated operating expense for nitrogen is much higher than originally thought. The estimated operating cost for nitrogen will be $13,000 to $14,000 per year compared to $1500 that was originally esti mated. We plan to proceed with this conversion, in spite of the high cost, to eliminate a hazardous situation. Inert gas generation equipment will be evaluated to compare operating costs and most economical method used long term.
Designed Experiment Run on
Process
TSD Objective
No. 1 Biphenyl Furnace_____________ StudyB - 7(e)
All the samples have been analyzed. Preparation of a progress report is in progress. Test results will be used to update math model of this process.
Install Knockout Tank on Santowax Jet Vent _________________
SafetyTSD Job No. 862
Complete design package was transmitted to Maintenance for construction on September 9, 1969.
Natural Gas Safety Shut-off Interlock Switch SafetyTSD Job No. 948
Complete design package was transmitted to Maintenance for construction on September 25, 1969.
DSW 551252
STLCOPCB4089669
> HC1
Company confidential 5.
G. L. Moore, L. 0. Chambers, K. G. Hale, (A. G. McCarty)
Production of Staley Grade Acid - AFE-5076 _________
New Earnings $288 M
TSD Objective
Potential Savings $71.000 B - 10(c)
Savings of $13,300 resulted from the Coalescer and Catch Tank project during September. Spare elements of a modified design are being completed by the vendor.
Plant pilot carbon treatment studies are scheduled to be run in November. The objectives are; 1) Accumulate design data necessary to expand the carbon treatment area, and 2) determine the carbon treatment and condi tions necessary to produce "Staley" acid. An experimental project for pilot test facilities is being issued ($700 experimental expense).
' TSD Objective Issue HC1 MIPPlanningB - 1(b)
Plant review was held on 9/10/69. Revisions are being made to several sections as a result of plant review. Revised copies will be submitted for final review by IO/3I.
Reduce High Free Cl2 in Muriatic Acid Quality
TSD Job No. 950
An expense project is being issued to install necessary piping to air blow a second storage tank and provide a temporary air supply until the cause and/or cure to the high Cl2 problem can be found.
PNP L. 0. Chambers, K. G. Hale, (A. G. McCarty)
Debottleneck to 1.8 M
Capacity Savings
TSD Objective
$27.500________ B - 9(a)
Process changes targeted at reducing PNCB usage resulted in let-down problems during September. No savings resulted in September. Additional changes will be made and monitored by P. & Q.A. to attempt PNCB usage optimization.
NIRAN
K, G. Hale, D. W. Dudley, T. W. Lawrence, (A. G. McCarty)
Demonstrate Parathion
Savings $17,400
Recovery10-15% Reduced COD;B - 5(a)
TSD Objective
No change in status. Construction in progress on test facilities.
DSW 551253
STLCOPCB4089670
)
Company confidential 6.
NIRAN - (continued)
Acetone Recovery
Savings $12,900 20% Reduced COD
TSD Objective ____________ B 5(i)
Recovery tests on #3 condensation reactor indicate a 30% reduction in acetone loss. Gross savings (ethyl and methyl) from increasing acetone recovery is $40,000 per year plus a 207 reduction in COD load. Project 3340 was verbally approved 9/29 for $32,125 capital and $28,600 expense. Manpower evaluations are presently underway to determine what parts of the project will be installed during the '69 fall turn-around.
Central Chlorine Unloading for Niran
Savings $21,000 ,B - 6(a)
TSD Objective
Evaluation of rebuilding 12 year old compressor vs. purchasing new com pressor favors the new compressor. Compressor will not be purchased or installed until late winter to prove worth of air pad on "cold chlorine cars" during winter.
Sulfur Recovery
$271,000/yr. Net Sevings
from Residue53% Reduction in S0oB - 5(d)
TSD Objective
C.E D. has suspended work on the Sulfur Recovery scope and will evaluate alternates to obtain yield savings at a lower capital cost.
The new objective would be to remove sulfur and recycle organics, but not clean-up sulfur for re-use.
. Profit New Sales and Productivity
Improve Chlorinator
Savings $48,000/mo. per 0.5 Hour TSD Objective
Cooling SystemReduction in Chlorination TimeB - 5(g)
A Tentative Process Amendment is being prepared to cover plant trial of Freon-21. If approval is given, expect to begin trial approximately one month prior to the end of the 1969-1970 Ethyl run and extend approximately one month into the 1970 Methyl run.
Improve Intermediate Distillation CapacityCapacity
_________ TSD Job No. 972
Possibilities are remote for obtaining significant increases in inter mediate distillation capacity with existing equipment. It is felt that thin-film or wiped-film equipment may be suitable for processing this type of material rapidly. Contacts will be made with thin-film vendors to explore the possibility of application to this problem.
DSW 551254
STLCOPCB4089671
-
)
'
NIRAN - (continued)
.
.. Company confidential
7.
Replace Nitrogen with HC1 for Chlorination Sparge
Savings $60.000
TSD Job No. 605
Anniston PR&D has shown that HC1 sparge produces no adverse effects during chlorination compared to nitrogen sparge. Since HC1 is produced during chlorination/ it could possible be recovered for use as sparge gas replacing nitrogen. A tentative Process Amendment will be prepared covering a plant trial of sparging with cylinder HC1.
' "%
.
PROCESS AND QUALITY ANALYSIS
J. L. Murphree, Allen Hale, (W. B. Dunlap)
Process Surveillance
An 18 month downward trend in distillation level of raw material benzol was revealed, culminating in 6 tank cars out of specifications. Toluene in benzol was found to be out of spec. These factors may be related to a documented increase in Aroclor 1242 TC Chlorides over the last 5 months.
PNP-Identification of
Potential Savings
Critical Variables$60.000.TSD Job No. 8^9
TSD Objective C - 3
A final report on yield study was written. Reactor settings will be ad justed and controlled experimentally to verify the statistical prediction of the study.
Niran Still Control
Potential Savings _____________ $79.000TSD Job No. 964
An AFE was approved to obtain and install control equipment. Design and drafting is scheduled for the 4th quarter. Installation EDC is 3/1/70.
ENGINEERING DESIGN AND SERVICES
Mechanical/Electrical/lnstrument Design and Drafting
J. C. Price, J. A. Veazey, J. 0. House, G. W. Richey, B. D. Morgan, R. V, Carlisle, R. L. Brewer, J. K. Rennie, (W. F. Taffee)
Design was completed on Project 3161 - $3.8 M, Automatic Temperature Control of Thio Acid Reactors #1 & 2. Review drawings were transmitted with con struction drawings to follow in October.
Design is in progress on Project 3II8 - $9.7'M, Modify Agitator Interlocks on all critical vessels in the Niran department. Transmittal is expected in October.
DSW 551255
STLCOPCB4089672
)
ENGINEERING DESIGN AND SERVICES - (continued)
.Company confidential 8
The following project safety reviews were held or attended: Fire Pump Capacity Check Equipment (AFE 3227 - $4.1 M), Install Pressure Control Valves in Fire Protection System (AFE 3211 - $5.7 M), Biphenyl Pilot Unit (AFE 3297 - $13 M).
A program is underway to gather data necessary for preparation of a short circuit coordination study of the electrical portion of the Niran department. The results of this study will lead to the compilation of a program for testing switches, circuit breakers, protective relays and, in general, all major electrical equipment that could cause prolonged downtime due to its failure.
Training and supervisory time remained at a high level this month because of time necessary due to three recent manpower additions to the department. One E & I Technician is on loan to the Maintenance department to instruct maintenance employes in an electrical instrument course.
Premises were prepared and forwarded for the following projects: Niran Intermediate Tank-Car Cleaning, Building 27 Dismantling, Eliminate "Head Knocker" at Aroclor.
Drafting
Review drawings were completed for the following projects:
Install 4" Heat Exchanger in Biphenyl (AFE 3282 - $1.4 M), Final Wash Tank-
PNP (AFE 3342 - $2.0 M), Automatic Temperature Control of Thio Acid Reactors (AFE 3161 - $3.8 M), Dual Chlorine Relief Valves - Niran (AFE 3310 " $3*5 M),
Acetone Recovery (Electrical) (AFE 33^0 - $50.7 M).
Construction drawings were completed for the following projects:
Replacement of Water Loop-HCl (AFE 3240 - $8.4 M), Biphenyl Pilot Unit (AFE 3297 - $13 M), Debottleneck Solid Aroclor (AFE 2897 - $20 M), Replace Niran Generators (AFE 3305 - $41.9 M), Install Nash Compressor at Eimco Filter-Waste Treatment (AFE 2820 - $4.6 M), Acetone Recovery - (Piping) (AFE 3340 - $50.7 M).
UTILITIES ENGINEERING
J. C. Price, J. 0. House, M. L. Marcum, (W. F. Taffee)
Transmitted review drawings for Test Heat Exchanger (AFE 3282 - $1.4M) on Biphenyl Cooling Water. The design package will be transmitted in October. Started preparation of Utilities Improvement Items for inclusion in the Aroclor MIP. Started evaluations of projects to replace existing air com pressors with a Central Plant Air Compressor (estimated gross savings $12.0 M 16.0 M per year) and to Improve Plant Power Factor (estimated gross savings $5.0 M - $9.0 M). The premise for the power factor project is expected to be forwarded in October and for the compressor project in late November or early December. Continued work on Steam Plant MIP with completion scheduled for December 15.
DSW 551256
i
STLCOPCB4089673
> -
Company confidential 9.
PLANT IMPROVEMENT
G. C. Goodwin, (W. F. Taffee)
A premise was prepared and forwarded for Renovating Niran Control Room and Lunchroom. Design package was forwarded for: Up-grading Fire Pro tection System (AFE 5293 " $7.1 M).
Messrs. K. B. Davis and J. Harrison of the Alabama State Highway Depart ment visited the plant on September 26, to discuss the relocation of Highway 202 across Monsanto property. They presented two schemes for the connection of old Highway 202 to the new 202 on the southeast side of the plant.
POLLUTION CONTROL
E. G. Wright, (W. F. Taffee)
Air & H20 Pollution
Community and
TSD Objective
Complaints
________ Governmental RelationsB - 2
No air or water pollution complaints were received at the Anniston Plant during September.
P.C.B. in Choccolocco Creek__________
Pollution Abatement
TSD Objective F-^
The first set of samples taken from Choccolocco Creek show levels of P.C.B. from 2 to 8 PPB. These levels will be checked at periodic inter vals beginning in October with another set of samples from the creek.
HC. Neutralization Pit
' TSD Objective Production AssistanceF - 4_____________
The pit continued to neutralize all of the acid sewered this month. No un-neutralized HC1 has left the plant since August 8. The pit is showing no signs of reaching a break-through point at the present time. Plans are to continue to extensively monitor the pit until it has reached the break-through point.
Choccolocco Creek Wildlife Studies Pollution AbatementF - 4
TSD Objective
Requested Drs. Gunning and Suttkus to do another study of Choccolocco during the fall season. This study will probably be conducted during late October. Samples of the fish and other wildlife from the creek will be collected, frozen, and sent to Organic Research for P.C.B. analysis. This will provide some base data for evaluating the magnitude of the P.C.B. problem in Choccolocco.
DSW 551257
STLCOPCB4089674
>
Company confidential 10.
POLLUTION CONTROL = (continued)
Eimco Filter at Waste Treatment______
TSD Objective F - 4 Production AssistanceTSD Job No. 808
Construction is 95% complete. Start-up is scheduled for the first or second week in October.
Waste Treatment
All wastes were effectively treated during September. High solids continue to be a problem. Successful operation of the Eimco filter should eliminate the problem. Average daily values for Monsanto's effluent are as follows:
PNP COD Parathion BOD
Specifications 5 PPM
-<1200 PPM -=^1.0 PPM (max.)
^200 PPM
DSW 551258
STLCOPCB4089675
)
PLANT LABORATORIES G. W. Miller
Company confidential 11.
PROCESS RESEARCH AND DEVELOPMENT J. T. Bell
Of the 105 PR&D mandays available in September, 63 were expended on projects outlined in the 1969 PR&D Program. The use of the remaining mandays were divided among vacation, supervision, illness, and miscellaneous.
Blend Scavenger
Improved Aroclor
Refinement (Aroclor) _______ Electrical PropertiesJ. L. Brown
Evaluation of Type 4A Molecular Sieve as an absorbant for column refinement of Aroclor-Scavenger mixes was begun on 9/24 with completion targeted for 10/15/69.
HB-40 Process Studies _______ __ ___________
Determine Process VariablesW. H. Howard
Equipment failure has temporarily suspended attempts to prepare HB-40 via a continuous process. This aspect of the study is to be continued on 10/3. The effect of quaterphenyl level on reaction times and catalyst requirements has been determined by a batch process. Santowax C has been hydrogenated to HB-40 with an extended reaction period.
Biphenyl Tubular Pilot Studies
Obtain Desired ___________ Biphenyl/Terphenyl Ratio
___________ J. L. Brown
Plans for the Biphenyl Pilot Laboratory were completed on 9/9 and trans mitted to maintenance. The plans were issued for bids on 9/10. A delay of 15 days caused by failure of contractors to bid promptly has been encountered with construction now targeted to begin on 10/15.
Low Color Aroclor 5460
Develop Alternate Process G. L. Arnett
The distillation of Aroclor 5060 and 5460 over a combination of lime and NaOH is effective in reducing color. DTA studies indicate thermal stability of the combination of Aroclor 5060, NaOH, and lime up to 400C. Samples have been forwarded to St. Louis for corrosion studies. A PR&D report is being prepared.
Parathion Isomer Reduction;Increased Yields'_________________________________________________ G. L. Arnett
This project has been delayed by illness but will resume by 10/6.
DSW 551259
STLCOPCB4089676
)
PLANT LABORATORIES -(Cont'd)
Company confidential 12.
PROCESS RESEARCH AND DEVELOPMENT -(Cont'd)
Parathion Condensation Reaction StudiesIncreased Yields
______________
I. Ransaw
The project work plan has been interrupted to derive a method for determining the actual 7, conversion in the condensation reaction. The reliability of the method is to be determined by 10/3 with the study, as written in the work plan, to resume on 10/6.
Acetone Recovery (Parathion)Reduce COD Load
_____________________ G. L. Arnett
Sample analyses have been made to support a plant demonstration of increased acetone removal in the condensation step. This study has been terminated.
ANALYTICAL AND QUALITY CONTROL
S. 0. Kemp
Complaint Report
Quality
Number
Material
Customer
12-A-69 13-A-69 14-A-69
Aroclor 5460 HB-40 Aroclor 1268
Swift Addyston Plant Central Solvents
YTD Quality Complaints/100 Shipments 0.24
Reason
Organic Matter Color High Melt Point
Target 0.20
DSW 551260
STLCOPCB4089677
)
' Company confidential
COMMUNITY RELATIONS. PERSONNEL. RECRUITING. AND DEVELOPMENT
13.
Community Relations
1. J. C. Landwehr, W. F. Taffee and E. G. Wright attended a talk by Dr. Roy Ledbetter, Alabama State Extension Entomologist, on the positive benefits of DDT at the September meeting of the Decatur, Ala. Kiwanis Club, September 11.
Personnel
1. Brode D. Morgan, BSEE from the University of Arkansas, reported to work on September 2 as Electrical-Instrument Engineer I.
2. Ralph Noel, D.O. student, Cobb High School, started to work in ED&S September 18, 1969.
3. G. L. Moore, Co-Op from Ga. Tech, has returned to school to complete studies to obtain degree in Chemical Engineering.
4. All members of TSD attended a seminar on Parathion Poisoning Symptoms conducted by Ishmeal Ransaw, September 16, 1969.
5. All members of TSD attended Job Holders meeting conducted by W. B. Papageorge, September 24, 1969.
Recruiting
1. Summer employes reported to school September 15: P. D. Kinnear to the University of Chicago, M. L. Marcum to the University of Tennessee, J. L. Gaines to Auburn University, and A. I. Hale to the University of Mississippi.
Development
1. J. C. Landwehr participated in Innovation Exchange Program at Bridgeview Plant (Chicago), September 25-26.
2. V. R. Haupt visited the Newport England Plant to assist with Biphenyl problems, September 4-20.
3. G. L. Arnett held a seminar at the Luling Plant, Luling, La., to train decontamination team, September 25.
Visitors
1. Bob McCutchan visited the laboratory September 17 concerning Aroclor.
2. W. A. Kuhn visited September 3-4 and was special guest at the seminar and barbecue for new employes.
3. George Hunt from S&PP section of CED visited the plant on September 30 concerning the electrical failure in the Aroclor department on September 27.
DSW 551261
STLCOPCB4089678
PROCESS IMPROVEMENT
DISTRIBUTION OF TIMS BY TECHNICAL SERVICE Jan. Feb. Mar. Apr. May June July Aug. Sept. Oct. Nov. Dec.
NEW PRODUCTS
PLANT IMPROVEMENT
M Ms
ASSIST OPERATIONS
SPECIAL ENGINEERING SERVICES
oH U-i o
ofcj td
TECHNICAL MANPOWER
MISCELLANEOUS ACTIVITIES
AND ABSENCES
STLCOPCB4089679
)
IN MAINTENANCE
FOR CONSTRUCTION
uuiu^cm^ Kj uiijl jLUdic iai
.
^
TSD PROJECT SUMMARY
IN MAINTENANCE COMPLETED
NOT CLOSED
PROJECTS SUBMITTED
FOR APPROVAL
cCoi
J Oa
o CQO <cooo H
APPROVED PROJECTS IN TSD
DSW 551263
STLCOPCB4089680
LABORATORY ADMINISTRATION
ANALYTICAL SAMPLES
60 1967 1968 J F M A M j j A - S 0 N D
]
156 j______
52 ______
i
48 . haiMiflwJ f*.
mi44 1 "V L/1 1
40 __
ANALYTICAL MANPOWER
Manpower/sample
$/Manhours
% Total Plant Operating Cost
2.0 rgiMEftWMa)
|
1.5
1.0 N2nE=an=l
0.5
| OrsL____
-------- i-------1
Overtime 7>
STLCOPCB4089681
STLCOPCB4089682