T. H. Huffman IWT9rDflK9 CoamnunicaHon From: Dote: Subject: D. C. Skokna October 26, 1992 ABERDEEN MONTHLY PROGRESS REPORT SEPTEMBER, 1992 * * || VIS1A * Safety There were three first aid cases reported during September. For FY1992, there were four OSHA recordable (2 MTO and 2 RWC) cases reported; the best fiscal year ever for the plant. At month end, the plant's employees had worked 4836 days (6,485,734 employee hours) since the last lost time injury. FY1992 Rev Statistical Information tent. Y.T.D. PVC Production, MM Lbs. Reactor Stream Factor, % Resin Quality, % Prime VCM Efficiency, Lbs./Lb. Flexible Compound Production, MM Lbs. Flexible Compound Quality, % Prime Rigid Compound Production, MM Lbs. Rigid Compound Quality, % Prime Plasticizer Production, MM Lbs. Plasticizer Quality, % Prime Energy Use, (EUI, %) Fixed Cost Variance, $M Variable Cost Efficiency Variance, $M 38.8 93.9 96.0 1 0471 6.5 97.6 1.4 98.7 1.7 81.8 < 6.7> < 13.3> 0.8 447.2 87.3 97.1 1.0353 67.5 96.8 22.6 97.6 18.0 81.7 < 12.1> <418.1> <654.6> Operations transformer downtime The Vinyl Department was reduction in work force effective October 1. A power failure Compound rates were good during the month, but orders were lower than the previous month. Production of two compounds was moved from Line III to Line V which will provide additional capacity. The rigid compound unit shut down on September 21, 1992. commissioning is in progress. De VAB.0001189105 T. H. Huffman 10/26/92 Aberdeen Monthly Progress Report - September, 1992 Page 2 Costs Both fixed and variable costs were near budget for the month. Fixed costs included a $38.5M charge for the elimination of rigid compound line spare parts. Xntex Plastics, a resin customer, visited .the plant for a tour and to review quality testing procedures. Northwire, a flexible compound customer, visited the plant. They made a presentation of their operation and Vista's key role as a supplier. We agreed to work with them to improve our products so they can increase their production The Senior Process Engineer's Team recommended a re duced reactor cleaning frequency based on heat trans fer data. The Security Natural Team completed a procedures manual covering their job responsibilities. OSHA Process Safety m Policies were developed for Employee Participation, Process Safety Information Development, Process Hazards Analysis, Operating Procedures, Training, PreStartup Safety Review, Mechanical Integrity, and Man agement of Change. m Management of Change procedures started in August and are proceeding smoothly. Drafting standards for P.I.& D. are under review. P.I.& D. development is set to start in January, 1993. Environmental Data collection of the James Creek Modelling Project was completed. The modelling should be completed in October. T. H. Huffman 10/26/92 Aberdeen Monthly Progress Report - September, 1992 Page 3 Environmental - Continued m The MDEQ requested that we submit a detailed work plan for investigation of the VGM contamination of shallow groundwater. The plan was sent to the State in midOctober. Reduction In Work Force Because of the shutdown of the rigid compound unit and the need to improve plant profitability, twenty-four jobs were elimi nated; others were combined; a temporary pool was created to reduce contractor costs; two Operators were assigned to develop operating procedures as part of the OSHA Process Safety compli ance effort; and through transfers two new positions were filled. These changes resulted in nine employees being laid off. These changes were effective October 1. D. C. Skokna Plant Superintendent rah A VAB.0001189107 DISTRIBUTION Houston * Austin Oklahoma Citv LCVCM Plant LCCF Plant LCLAB Plant Baltimore Hammond Premiere Aberdeen J. R. Ball COVER LETTER X R. T. Ferrell X T. H. Huffman X B. M. Myers C. J. Matson H. R. Flammer R. R. Smith B. J. Bean R. H. Gerlach R. D. Gamblin X C. R. Miller L. R. Kardos M. J. Schneider X R. L. Poe X H. G. Coleman H. D. Garrison P. E. Markey J. Friend X J. V. Hare X L. R. Bauer X J. Favao X P. L. Foote X J. A. Autrey J. E. Beall X J. M. Edwards X S. C. Hillman C. M. Markerson D. A. Miller J. E. Nickerson X J. D. Olson R. W. Seymour/ D. C. Skokna (File Copy) ENTIRE REPORT X X X -X X X X X X X X X X X X X VAB.0001189108 A SAFIlt1Y - J. V. Uptain First Aid OSHA Recordable Total Injuries Number of Restricted Workday Cases Number of Lost Workday Cases Fiscal Y.T.D. 1992 3 22 S Jt 3 26 02 00 Fiscal 5 0 Vinyl Operations Compound Operations Maintenance Laboratory Receiving/Warehouse Office Totals Injuries bv Type Cuts and Abrasions Eye Injuries Burns Bruises Strains/Sprains Stings Other Totals 1 1 1 0 0 0 3 1 2 0 0 0 0 0 3 Lost Workday Cases Days Lost Contractor Injuries 0 0 First Aid Cases Medical Treatment Cases Lost Workday Cases Safety Record 0 44 0 01 0 01 Last lost time injury - 7/5/79 Days since - 4,836 Employee hours since - 6,485,734 On September 30, 1992, the employees of the Aberdeen plant completed 4,836 days with no lost time injury. VAB.0001189109 SAF^tt - Continued Topics for the plant safety meetings during the month included: Safety, Plant Emergencies, and Handling of Chlorine and Caustic. Driving A lost time injury occurred on October 7, 1992, when a Maintenance Mechanic suffered multiple injuries, including bruised lungs while repairing a lift truck. Routine dosimetry results for the month were: Chemical >m Ntimha-r VCM Lead Total Particulates 78 98.7 -1 7 100.0 0 1 100.0 0 1.3 0 0 The single VCM overexposure was without benefit of respiratory protection. Monthly Injury Summary Iniurv Class Department Description FA Maintenance Cut of right index finger. FA Vinyl 610P plasticizer sprayed into both eyes. FA Compound Dust in right eye. i VAB.0001189110 QPAI.TTT mnAianiCTT rancma; . E. K. Smith Intex Plastics visited the Aberdeen Plant on September 21 for a plant tour and demonstrations of laboratory tests. Northwire visited the Aberdeen Plant on September 24. They made a presentation on the Aberdeen Plant's importance to Northwire. The Senior Process Engineers Team justified reducing condenser cleaning frequency using batch condenser U-value data. The Security Natural Team wrote an extensive procedures manual covering their many responsibilities (many of which are done infrequently). k VAB.0001189111 COST VARIANCES - D. C. Skokna Variable Costs Product _____Sept.. 1992 Variance. $M Effipieppy Price Total PVC Flexible Compound Rigid Compound Plasticizer Total $13.2 17.1 < 11.7> < 17.8> $ 0.8 <$313.2> < 4.2> < 13.5> < 37.7> <$368.6> <$300.0> 12.9 < 25.2> < 55.5> <$367.8> Efficiencies In the PVC, Flexible and Rigid Compound Units were near budget for the month. Plasticizer Raw material use was above budget during September. Maior Price Variances: Variance - SM VCM Debox Resin Credit Natural Gas AlcoholR Alcohols Plasticizer Micral 932 Electricity Other Price Variances Total <$273.0> < 43.4> < 39.5> < 39.2> < 33.7> 15.3 40.0 4.9 <$368.6> Fixed Cost Variances Payroll andBenefits MM&C Miscellaneous TI&D Clearances Payroll & Benefits Variance - SM Total <$ 2.6> 35.0 < 52.0> < 0.8> 7.1 <$13.3> Results were essentially at budget. MM&C Costs were controlled by minimizing contractor activity. VAB.0001189112 k COST VARIANCES - Continued Miscellaneous Assigned Vehicles: <$33.9M> - This corrects an August accrual error. Unclassified: $21.8M - Transfer of test run costs to capital. Moving, Home $13.3M pipeline repairs. $16.3M Credit from Tenneco for gas Warehouse Gain/Loss: <$41.7M> - Writeoff of Dry Blend Unit spare * VAB.0001189113 VxHYJL - J. D. Olson, D. E. Knittig Safety The Vinyl Department had no injuries in September. The monthly safety meetings were held on shift. General A power failure caused by a city transformer problem caused thirteen hours of reactor downtime. We continue to modify and Improve our DCS system to control the reaction with limited effect on quality during these upsets. 2. We re-organized our department to prepare for the reduction in personnel completed on October 1. September TTD - Production, MM Lbs. - Daily Rate, M Lbs./C.D. - Capacity Utilization Factor, % - Total Reactor Charges - Charges/C.D. - Reactor Stream Factor, % - Rotary Dryer Stream Factor (#4-#8), - Fluid Bed Dryer Stream Factor, % - Resin Quality, % Prime % 38.8 1293.3 97.6 920.0 30.7 93.9 96.2 96.7 96.0 447.2 1221.9 92.2 10661.0 29.1 87.3 91.7 91.5 97.1 Reactor Downtime Hours Operational downtime (recovery scheduling conflicts, charge/rinse water conflicts, Q.C. data delays, dump conflicts, and no blend tank space). 356.0 Maintenance downtime (D-741 condenser cleaning, D-742 steam leak, D-400 dump valve, D-300 charge valve, D-700 rinse nozzle, D-600 suspending agent ram valve, D-744 charge water valve, old module screener motor, PM D-742 agitator motor, D-400 catalyst ram valve, Old Module filter pack rinse valve, old module cooling water line, D-745 rinse nozzle, D-600 suspending agent valve, and D-300 high pressure service water line). 120.0 4* VImiL - Continued Dryer Time % of Total Operational downtime (centrifuge plugs, dryer cleaning, flameouts). n Maintenance downtime (activator problems, centrifuge repair). m Reactor limited production. Key Maintenance Tram* - j. B. Autrey/S. A. Truitt 48.8 16.3 35.0 The "B" vacuum pump in the Old Unit was taken out of service. The case had a tiny hole from a casting defect that was leaking water. The casing is being repaired and pressure tested to be used for a spare. Reactor 741 condenser was hydroblasted in an effort to control contamination. Reactor 700 critical instrumentation PMs were completed. One major valve in Vinyl was changed. The #4 cooling tower pump motor was pulled from service, sent out for repair and re-installed. The motor had bad windings. Cooling tower #4B was reinforced for structural integrity. Excessive vibration was causing the east fan motor to shut down, and the shrouds were unlevel causing the blades to strike the shrouds periodically. Repairs included a new fan deck and repairs to one of the distribution valves. The exhaust valves on #9 air compressor were replaced. The PM was completed on the propane vaporizers. The #1 boiler feedwater pump motor bearings were replaced. Critical instrumentation on the water plant was completed. A VAB.0001189115 COMPOUND - S. C. Hillman, J. B. Hegwood The Compound Department had no OSHA recordable Injuries in September. General Orders continue to be down slightly on Line I and Line III. Production for the month was down 650M pounds from last month. This decrease can be attributed to an increase in product change and maintenance downtime. We have been given approval to move two Line III products to Line V by the customer. This has reduced the requirements of Line III and leaves room for additional production on Line III. The Business Area is developing new customers to use this addi tional production. The Dry Blend Unit operated only twelve days during the month. The Unit was shut down on September 21, 1992. Compound Production Operating Davs Line I 30 Line III 29 Line V 20 Total % Prime Capacity Utilization Factor Downtime Line I Production M (Lbs.) Month Fiscal YTTfp, 1943 3754 772 6469 97.60 84.25 65 129 38 232 20356 41465 5672 67493 96.77 73.22 Hours - Product Changes - One Dicer Offline - Miscellaneous Maintenance - Quality 101 26 51 14 Line III - Product Changes - Miscellaneous Maintenance - Quality 60 63 10 Line V - Product Changes - Quality - Miscellaneous Maintenance 61 12 6 VAB.0001189116 COMPOPHD - Continued Operating Dav Rigid Compound 12 % Prime Capacity Utilization Factor Month 1411 98.66 27.99 118 22582 97.61 36.43 Downtime - Product Changes Miscellaneous Maintenance - Quality Operating Davs Hours 13 18 15 Production (M Lbs.1) Month Avg,/Dav Fiscal Y.T.D. Plasticizer 30 % Prime Capacity Utilization Factor 1655 81.81 77.97 55 gey Maintenance Items - J. B. Autrey/S. A. Truitt 18046 81.65 65.06 The agitator seal in P-1 reactor R-4 was changed. The seals in Line I Banbury were changed. The Schenk filter was disassembled and cleaned. Line I dicer hand/off/auto switch was revised to correct a safety hazard. Line III reduction gearbox was replaced and rebuilt for a spare, and the motor was sent out for PM. VAB.0001189117 ENGINEERING - J. E. Nickerson, T. R. Mackay, R. H. Sneed, I. L. Cartier PROJECTS IN DEVELOPMENT - GENERAL Water Plant Water plant construction Is nearly complete and contractors are working on punchlist Items. Equipment testing has begun. Chlorine training and certification is in progress. Water plant startup will begin in the second week in October. New Boiler An unallocated AFE for $450M was approved. A specification and bid package for an 80,000 lb./hr. boiler will be sent out to selected vendors in mid-October. Plans are to place an order for a boiler in early November, Work has begun on a Class "A" design for the boiler installation. Plastic*Expansion An estimate for the plasticizer stripper was completed by GED; the cost is $1.4MM. This estimate does not include tank and unloading facilities. A Class "A" design of the "No Additional Tanks" option of the plasticizer storage and transfer facilities was reviewed by Operations and Mechanical Engineering. A Class "A" design, including additional tankage, will be completed shortly. Capacity of all equipment and processes external to the plasticizer reactors were evaluated at expected production rates. The "No Additional Tanks" design is expected to increase capacity of the plasticizer unit to approximately 30MM lb./yr. Special water sampling was extended into October. The test which added extra loadings to the ponds was stopped, but sampling will be continued until October 9 to observe changes in waste water effluent. VCM Compressor Upgrade Construction for upgrading the compressors and installation of safety equipment is in progress. Operating procedures have been completed and training will begin as soon as possible. OSHA Process Safety The following policies have been approved thus far: Employee Participation, Process Safety Information Development Plan, Process Hazard Analysis, Operating Procedures, Training, Pre-Startup Safety Reviews, Mechanical Integrity and Management of Change Procedure. Since implementation in August, Management of Change is proceeding smoothly at Aberdeen. The plant is currently reviewing drafting standards for P&ID development. P&ID development should start January, 1993. VAB.0001189118 ENGINEERING - Continued Water Use Minimization A team has been formed to look for ways to redu< plant. The team includes engineering, vinyl and < and maintenance. The team has started surveying compound and plasticizer areas. As part of the External Steam Stripping Project, the plant has begun a dryer technology study. We received a budget estimate from Sulzer for a new 30,000 lb./hr. fluid bed dryer. We have received and re viewed technical information on UHDE's cyclone dryer. The techni cal information and cost estimates will be used to develop the scope for a Class "A" design. 5385/5395 Silo A Class "A" design was completed for transferring resin from 281/282 silos to silo 676. This project provides a silo for loading trucks or railcars for a new customer, North American Plastics. Potential sales are 8MM to 20MM pounds per year. Wastewater The plant review of the aeration design for Pond 3 was completed. The estimate should be complete in October. The AFE will be sub mitted immediately upon budget approval. Stream surveys of flow rates and oxygen levels were conducted on James Creek. Algae seems to be a major factor in the dissolved oxygen levels of the creek. Fat-head minnows have been placed in Pond 5 for a test to determine if the pond is habitable for algae eating fish. After an adjustment period of one week, the fish appear to be doing well. Cooling Tower Options for increasing cycles in the cooling towers are being looked into. This project has been focusing on quantifying blowdown. A plan for optimizing treatment will be determined after the new water plant comes on line. VAB.0001189119 ABERDEEN CHEMICAL PLANT MONTHLY PROGRESS REPORT CAPITAL EXPENDITURE STATUS M.L. CARTER SEPTEMBER REPORT 1992 F.Y. CAPITAL EXPENDITURES (MS) VARIANCE ACTUAL BUDGET MS % Month 231.0 192.0 + 39.0 +20.3% 4th Qtr. 482.5 479.0 + 3.5 + 0.7% YTD 3337.1 3034.0 + 303.1 + 9.9% Actua1 Expenditures - Expenditures in September were $39.OM more than the plant's budgeted expenditure forecast approved in the Fourth Quarter Budget submitted in June FY92. September FY92 capital expenditures were 20.3% more than the plant's budgeted expenditure forecast, while overall expenditures for the Fourth quarter were 0.7% more than the forecast. It should be noted that the capital expenditures associated with project H612 Pond 2 Resin Drying are not accounted for in the reported actual above due to the accounting procedures and contract agreement with Conoco. Total Expenditures for FY92 were 9.9% more than the plant's forecast submitted in June FY92. Quarter Budget - Current Quarter Expenditure Forecast as submitted and approved for the current quarter capital budget. YTP Budget - Total of current and previous quarter approved budgets. Forecasted Expenditures - The budget has been submitted for FY93 and 1st Quarter FY93, currently waiting for approval. VAB.0001189120 ENVIRONMENTAL - K. G. Akins Water All wastewater discharge parameters were met for the month of September. Data collection for James Creek flow modelling was completed in September. This included water sampling for dissolved oxygen, BOD, and a time of travel survey to determine average stream velocities. The modelling should be completed in late October. VCM Plume The MDEQ requested that Vista submit a detailed work plan on further investigation of the vinyl chloride contamination of the shallow groundwater at the Aberdeen Plant. This work plan will be submitted for MDEQ approval in early October. Waste Waste shipments during the month included: Fifteen drums of stabilizer spill to Fisher Industrial Service in Gadsden, AL. m A bulk shipment of floor sweepings to Chemical Waste Management in Emelle, AL. VAB.0001189121 ENERGY CONSERVATION J. A. Rodron I. Energy Conservation Data A. Unadjusted EUI B. Adjusted EUI C. BTU/lb. Product D* Total Energy Consumption MMM BTU II. Boiler Operation No. 1 No. 2 No. 3 September 1992 (6.9)% (6.7)% 2763 134.7 Fiscal YTD (13.0)% (12.1)% 2909 1611.1 Combustion Efficiency % September 92 Fiscal YTD 82.4% 83.4% 83.6% 83.3% 83.5% 83.3% ABERDEEN ENERGY EFFICIENCY 3600 BTU/LB TOTAL PRODUCTION 3400 3200 3000 m 2800 i-- CD 2600 2400 2200 2000 JAN B7 JAN 88 JAN 89 JAN 90 JAN 91 JAN 92 JUL 87 JUL 88 JUL 89 JUL 90 JUL 91 JUL 92 MONTH VAB.0001189122 * k ttttmam resource report flRP^BlfBBR. 1992 PBRSOMBL - J. B. Beall EMPLQYMBliT None. PROMOTIONS /TRANSFERS Roger Crain - Engineering Department - Chemical Engineer transferred to Lake Charles LAB Plant as a Process Engineer. Joseph Ganc - Engineering Department - Chemical Engineer transferred and promoted to Houston, Texas as a Process Engineer. Timothy Arbeiter - Laboratory - Manufacturing Chemist transferred to Lake Charles Chemical Plant as a Group Leader - Control Laboratory. Greg Norman - Engineering Department - Mechanical Engineer promoted to Project Engineer. George Prillhart - Vinyl Department - Vinyl "A" Operator promoted to Vinyl Lead Operator. Chris Gilreath - Vinyl Department - Vinyl "A" Operator promoted to Vinyl Lead Operator. Ricky Clay - Compound Department - Compound Utility progressed to Compound Operator. Deevie Rambus - Maintenance Department - General Mechanic "A" transferred to Instrument Technician "B" RETIREMENTS None. VAB.0001189123 Human Resource Report: X992 TERMINATIONS/RESIGNATIONS Virginia Belk - Plant Nurse - Termination due to reduction-inforce. Marvin L. Keaton - Compound Department - Deceased. TO/PROM r.mm ny ABSENCE R. Danny Flippo - Vinyl Department - Vinyl Lead Operator Union Leave of Absence. VAB.0001189124 ABERDEEN PLANT gHPl'TOTOT Salaried Hourly Temporary SUB TOTAL L.O.A. TOTAL 234 236 DEPARTMENTS #EMPLOYEES WAREHOUSE GENERAL PLANT MAINTENANCE | LABORATORY 1 COMPOUND I VINYL I PLASTICIZER 1 SUB TOTAL 1 SALARIED 15 10 36 22 35 32 5 155 77 MF 9 5 8 4 22 11 2 61 6 0 0 0 1 1 2 0 4 18 . 1992 NgW HIRES Salaried/Transfer Hourly Temporary TOTAL FYD %M s 60% 50% 22.2% 18.2% 62.9% 34.4% 40% 39.4% 7.8% %F 0 0 0 4.5% 2.9% 6 3% . 0 2.6% 23.4% n DEPARTMENT TURNOVER MO. FYD 0 0 02 03 01 13 02 00 - ANN.% 0 20% 8.3% 1 4.5% 8.6% 6.3% 01 APPLICATIONS U Month FYD | Minority 1 Female No. i 00 00 00 00 PLANT TURNOVER Hourly Month FYD Salaried Month FYD No i 1 6.5% 7 4.5% 4 5.2% 6 7.8% VAB.0001189125 mmivipmh VAB.0001189126 P rin te d 10/06/92 AII O) II C ii ?41 DEPARTMENTAL SUMMARY HOURS REPORT ........... MONTHLY ............. V i i P rin te d 10/06/92 DEPARTMENTAL SUMMARY HOURS REPORT ............... YEAR TO DATE .................. CM | 1 A ta0o1. s s01 Ui OLU o CO o ioonc UI CO UocI CO ooc o UI UI oUaeI CO o o oUcI S| l|IlllfilliIl a/> l ? TV 01 .5^ c01 "8 r u oQ. in CO 0. M VAB.0001189127 f r ADMINISTRATIVE SERVICES - D. A. Barclay Safety There were no reportable safety Instances this month. Quality All teams et during September to review progress on their projects. Futures YTD Natural Gas <$34,092.64> Statistics Processed Processed Invoices Working Fund Checks Written Cost Savings Through Bid Process Raw Material Purchase Orders Issued MRO/AFE Purchase Orders Issued Spare Parts Purchase Orders Issued Month 1,060 7 $471.47 80 61 197 FT9 2 Y.T.P. 12,783 181 $34,028.58 1158 2140 2310 Packaged Finished Goods Ending Inventory Sent.r 92 (Decrease) /Increase Change Compound "A" Grade PLENEX Compound Off-Grade (BC) Compound Off-Grade (H) Millscrap Dry Blend "A" Grade Dry Blend Offgrade Resin Type I Resin Type "BC" Vacuum Dust Total Packaged W/house 3,995,394 144,706 312,000 63,607 84,469 632,625 261,850 1,222,700 100 242.701 6,960,152 4,425,368 163,134 333,521 51,829 27,617 477,492 88,737 1,337,050 100 180.553 7,085,401 429,974 18,428 21,521 < 11,778> < 56,852> <155,133> <173,113> 114,350 0 < 62.148> 125,249 10.76 12.73 6.90 <18.52> <67.31> <24.52> <66.11> 9.35 0 <25.61> 1.80 Bulk Finished Goods Ending Inventory im-t'W Bent..*92 (Decrease) % /Increase Change Compound "A" Grade Compound Offgrade Rigid "A" Grade Rigid Offgrade Resin Type I Resin Offgrade Total 858,815 0 876,709 56,050 8,280,950 924.750 10,997,274 1,330,021 0 801,942 0 10,688,058 2.379.251 15,199,272 471,206 54.87 0 0.00 < 74,767> < 8.53> < 56,050> <100.00> 2,407,108 29.07 1.454.501 157.20 4,201,998 38.21 VAB.0001189128 ABERDEEN CHEMICAL PLANT SHIPPING ANALYSIS SEPTEMBER 1992 -SHIPMENTS BY PRttUCTS- PUBL1C RES1N-BULK RESIN-PACKAGED 12,404,400 684,394 FLEXIBLE COMPOUND-BULK 492,660 FLEXIBLE COMPOUND-PACKAGED 3,085,334 NEW BUSINESS 14,328 RIGID COMPOUND-BULK RIGID COMPOUND-PACKAGED RIGID COMPOUND-PELLETS 460,980 371,789 0 TOLLING - BULK TOLLING - PACKAGED 0 0 PLASTICIZER 85,680 TOTAL 17,599,565 -SHIPMENTS BY MODEBULK: SEPTEMBER* RESIN FLEXIBLE COMPOUND RIGID COMPOUND PLASTICIZER RAILCAR 157 13 7 1 TOTAL SEPTEMBER 178 MONTH IPT/ITC EXCH/TOLL 16,668,650 342,250 0 0 2,231,100 60,835 0 0 0 0 981,600 83,221 0 0 0 0 0 0 0 0 291,300 0 20,658,956 S3S CUSTOMER PICKUP COMMON CARRIER 10 21 0 12 27 07 12 47 07:50 AM 14-0ct-92 YTD PUBLIC IPT/ITC EXCH/TOLL 207,341,609 213,653,410 6,489,640 3,899,150 5,834,580 25,740,590 36,419,077 495,177 0 0 0 0 196,208 1,981 0 12,581,590 4,993,751 0 6,941,250 760,945 0 0 0 0 00 0 00 250,740 6,948,680 917,400 274,107,195 258,441,183 917,400 SZ=S=SSSBSSS3SCS&Stt3SSSSSSSSSSSSSSS3 TOTAL 188 25 16 8 m 237 *YTD* RESIN FLEXIBLE COMPOUND RIGID COMPOUND PLASTICIZER TOTAL YTD PACKAGED: SEPTEMBER* RESIN FLEXIBLE COMPOUND RIGID COMPOUND PLASTICIZER 1,998 147 83 40 155 402 0 144 20 133 0 28 2,268 175 707 E3I333S3838WSfe 33883888X3X3 S3S8883333S 88833333333 3SS3388S38S3338S83388833 CUSTOMER PICKUP COMMON CARRIER TOFC AIR/UPS AIR/UPS 2 36 0 0 18 77 0 0 4 11 0 0 0 100 0 0 0 0 2,555 291 236 68 3,150 TOTAL 38 95 15 1 TOTAL SEPTEMBER 24 125 0 0 0 149 YTD* RESIN FLEXIBLE COMPOUND RIGID COMPOUND PLASTICIZER 36 301 0 0 229 991 0 0 27 150 0 0 0 100 7 23 1 0 344 1,243 178 1 TOTAL YTD 292 1,443 0 0 31 1,766 SS8S3SS53SSSX3BCSS5555S8333S33SS833E3SSBSE83888S888S 8SS3333SI3ESS33S88SSSSSSSS8388833S33S:333S8SS333333383833338 CC: DAB,TLC,MAS,AEV,JRF II II II II II II II II It II II II II II I VAB.0001189129 A *, N U| S* Ui <-- ?i CO K W (A f 32 UJ T 5 8 |i I^ a i IA i II *1 v* Ol 3! NO (A (A (A o iii UJ (A VI (A CO UJ UJ % ddd iIi M UJ INI 8 t S5S 8 8 8** AJ PA 8 I 5 0 S fM N N N o oo c o R! Ot sp s* K m S r-fc N PA CO (A s5 (A CO CO CO g2 w - ? s s is uH o ia in UJ 40 CO & 90 UI Ui 8 i52 CO CO Of Of S $ 8 CM fM oo (A 88 PA 2 R 8 UJ u a 8J IA <M s a ft f\l S CM r*- ^ ^ 5S 5 rS S s <0 in 0 in 58 $ ss XXX 333 ill fvi O' $ * aaa ill T KP0PMI r VAB.0001189130 * 1 (Thousands o f lbs.) 10/91 12/91 02/92 04/92 06/92 08/92 PKG'D PRODUCTS INVENTORY wmmmmrn VAB.0001189B1 # laboratory - J. M. Edwards, J. R. Williams . Safety There were no safety incidents in the Laboratory during September. B. Customer Contacts Jeff Almendinger and Wayne Crandell from Northwire visited the Plant for a tour and technical discussions. C. Customer O.C.Problem Reports and CBR's 9/02 Armor Bond. Sardis, MS The customer complained of red and lavender colored resin in a railcar of 5385 resin. 9/07 Triangle Wire & Cable. Slkeston. MO The customer complained of poor dispersion of raw materials and pluggage in screen paks using the 35852 compound. Analysis of the samples showed the contaminants to be lead, calcium, clay and titanium. 9/09 Klockner Pentaolast. Gordonsville. VA The customer complained of high levels of contamination in a railcar of 5305 resin using a slurry test method. The contamination was within specification using the syntron test method. 9/16 Donnelly Corporation. Holland. MI 9/18 The customer complained that bulk shipments of 48451 compound were sent without a co*shipment sample. One shipment had two lot numbers and another shipment had no lot number. Silyerline Plastics. Ashyille. NC The customer complained of finding a chunk of die cast aluminum in a debox resin shipment. The piece of aluminum was from a truck accident. VAB.0001189132 LABORATORY - Continued C. Customer Q.C. Problem Reports and CNR's - continued 9/24 Bnsolite. Mishawaka. IN The customer complained of fisheyes and glassies in a railcar shipment of 5385 resin. 9/25 Essex Croup. Llthonia. GA The customer complained of experi encing a drop in pressure in their process and a grainy surface on wire made with 5415 in UTCX 46492. 9/28 Northwlre. Osceola. WT The customer complained that a box of 35852 Natural was shipped instead of the order for 38552 Natural. D. Product Waivers Issued Customer Available Plastics Product 80273G WHT 110 Reason Torque Rheometry No. 1 H/T Vista Performance Polymers - Mansfield 5395 Particle Size 1 R/C E. RVCM of In-Process Samples The following is a summary of residual VCM results on in- process samples, None of the reactor daily averages exceeded 400 ppm RVCM during the month of September, 1992. Reactor Slurries Drver 5265 5305 Number of Samples Average RVCM, ppm 924 47 29 0.165 72 0.133 k VAB.0001189133 LABORATORY - Continued F. RVCM of Shtcaent Samples The following is a summary of the residual VCM analysis of shipment samples for the month of September, 1992. Product Umber of Samples Average RVCM. ppm 5225 5265 5305 5325 5385 5395 5415 5416 5465 Debox Pond Dry Blend 12 53 122 16 36 24 74 0 0 0 0 0 0.692 0.083 0.079 0.069 0.087 0.030 0.039 G. Flexible Compound SmMimrv Adjustments M Lbs. Hardness Color Hard Particles Heat Stability Contamination Dicing Mischarge Metal 32.0 175.0 5.0 Totals 212.0 <0.05> <2.66> <0.08> <3.23> H. Rigid Compound Quality Rejections M Lbs a 81.1 31.7 34.2 3.4 3.0 6.0 6.0 9.0 174.4 <1.23> <0.48> <0.52> <0.05> <0.05> <0.09> <0.09> <0.14> <2.65> Torque Rheometry & Color Total Rejections M Lbs. <%> 3.8 3.8 <0.27> <0.27> t VAB.0001189134 VAB.0001189135 SAMPLE SHIPMENTS SEPTEMBER 1962 RESIN Ship Date 9/14/92 9/16/92 9/25/92 Product 5225 5305 5385 5415 5416 5395 5385 Amount 101be. 10 lbs. 10 lbs. 10 lbs. 10 lbs. 50 lbs. 20 lbs. COMPOUND Ship Date 9/02/92 Product 35852 NAT 9/09/92 38401 BLK 9/09/92 57121 WC 327 58831 CB 50 9/06/92 57462 BLK 58031 WC 328 58831 CB 50 9/10/92 PLENEX 1275 9/10/92 PLENEX 1200 PLENEX 1250 9/22/92 56961 BLK 9/24/92 PLENEX 1200 PLENEX 1250 Amount 50 lbs. 50 lbs. 50 lbs. 50 lbs. 100 lbs. 50 lbs. 50 lbs. 100 lbs. 100 lbs. 100 lbs. 1500 lbs. 50 fbs. 50 lbs. PLAST. Ship Date 9/29/92 Product 61 OP Amount 2 X 55 gal. Customer EVC AMERICAS INC. Intax AKZO Chemical Customer R&D - Austin CommScope Inc. SunSoft Corp. - Terhorst Mfg. BICC Cables Corp. Wallingford Wire & Cable Winders & Gelst ALLWIRE Customer Conex of Georgia Ship Mode Airborne UPS UPS Ship Mode UPS UPS UPS UPS CC CC CC Airborne Ship Mode CC VAB.0001189136 SAMPLE SHIPMENTS SEPTEMBER 1992 MfSC. Ship Date________ Product 9/09/92 Vent Dust Amount_______________ Customer_________ 2 lbs. Lakeland Chemical & Plastics Page 2 Ship Mode UPS VAB.0001189137 NUMBER OF INJURIES A ABERDEEN CHEMICAL PLANT INJURIES (Twelve Month Running Totals) MONTH TOTAL INJURIES --OSHA RECORDABLE VAB.0001189138