R. P. Stevens -- General Offices
June 6, 1967 Aroclor Expansion -- CEA 1430
*
Joe Cresca
J. O. Bright H. C. Carder li. C. Fuhmeister R. E. Howard J. Molloy - KGK R, S. Yates
Anniston
On May 23 we reviewed with you the preliminary scope of a project at Anniston for bulk storage and packaging of Aroclors together with some planning for WGK. The various stops being considered are summarized below together with order-of--magnitude costsj
Anniston
1. New tank farm to include 11 bulk storage tanks, 3 blend tanks, pumps, filters, separate product pipe lines, tank car and tank truck loading facilities. Included i3 a spur track, 1 block of 6th Street, a substation and various utility extensions.
Estimated cost for this is $1,000,000 including $140,000 for spur track, substation, road and utility extensions.
2. A new drumming station located in one end of a proposed warehouse at 6th and Parkwin Streets. Only that portion of the warehouse building re quired to house the drum storage and filling oper ations is included.
Estimated cost* $660,000.
3. Kew flaking 2nd packaging facilities for solid Aroclors and biphenyl in the same end of the pro posed warehouse as the drumming station.
Estimated costs $490,000.
4. Obviously the above presume a warehouse will be built. This will be lower in cost than the orig inal estimate ($450,000) since some of the facil ities (spur track, utility extensions) are included in the above proposals. We have not reestimated the warehouse cost.
DEFENDANT'S
.EXHIBIT ^
32$ "3/- OH
Because of the high costs, we are looking at alternate ar
rangements to weigh the potential cost reductions against
disadvantages. A review at Anniston of the present pro
posals will be held on Juno 12.
N
DSW 392357
WATER PCB-SD0000051377
Joe Cresce
-2-
June 6, 1967
Kruirjnrlch
5. Additional storage is needed at WGK also. We have not looked at this in detail yet but the plant has recently issued a proposal.
6. One .scheme for additional production capacity at WGK
(40 M lb3./year 1242 continuous chlorinator system)
has been scoped and estimated - $800,000. We are
looking at an alternate case that should be more
economical.
'
R. P. Stevens