Document a4pQ9eQpJj4EMv7NYMwM4rzKb

\J R. P. Stevens -- General Offices June 6, 1967 Aroclor Expansion -- CEA 1430 * Joe Cresca J. O. Bright H. C. Carder li. C. Fuhmeister R. E. Howard J. Molloy - KGK R, S. Yates Anniston On May 23 we reviewed with you the preliminary scope of a project at Anniston for bulk storage and packaging of Aroclors together with some planning for WGK. The various stops being considered are summarized below together with order-of--magnitude costsj Anniston 1. New tank farm to include 11 bulk storage tanks, 3 blend tanks, pumps, filters, separate product pipe lines, tank car and tank truck loading facilities. Included i3 a spur track, 1 block of 6th Street, a substation and various utility extensions. Estimated cost for this is $1,000,000 including $140,000 for spur track, substation, road and utility extensions. 2. A new drumming station located in one end of a proposed warehouse at 6th and Parkwin Streets. Only that portion of the warehouse building re quired to house the drum storage and filling oper ations is included. Estimated cost* $660,000. 3. Kew flaking 2nd packaging facilities for solid Aroclors and biphenyl in the same end of the pro posed warehouse as the drumming station. Estimated costs $490,000. 4. Obviously the above presume a warehouse will be built. This will be lower in cost than the orig inal estimate ($450,000) since some of the facil ities (spur track, utility extensions) are included in the above proposals. We have not reestimated the warehouse cost. DEFENDANT'S .EXHIBIT ^ 32$ "3/- OH Because of the high costs, we are looking at alternate ar rangements to weigh the potential cost reductions against disadvantages. A review at Anniston of the present pro posals will be held on Juno 12. N DSW 392357 WATER PCB-SD0000051377 Joe Cresce -2- June 6, 1967 Kruirjnrlch 5. Additional storage is needed at WGK also. We have not looked at this in detail yet but the plant has recently issued a proposal. 6. One .scheme for additional production capacity at WGK (40 M lb3./year 1242 continuous chlorinator system) has been scoped and estimated - $800,000. We are looking at an alternate case that should be more economical. ' R. P. Stevens vo 'i ; ~ v-~! v _ _ DSW 392358 WATER PCB-SD0000051378