April 8, 1974 AROCLOR 1254 STABILITY
cc= v. Brawley T. Carrico
REFERENCE
:
Meeting 4/3/74.
TO Those Present:
K. E. Boucher
G. L. Johnson
W*^'-F'Tfhginan%'-'"
J. R. Kuster
J. A. Gloeckner
A. E. Leisy
H. J. Horner
S. H. Vogel
D. W. Johnson
The above met on April 3, 19 74 ..to discuss the recent Aroclor 1254 stability problems. A brief review was given, of actions already taken at Dept. 246, which includes:
1. Changing the finished goods 1254 storage tank -
circulating filters.
2. Changing the, polishing prefilter to #1 absorber
(Porocel Column).
-
3. Checking the thermometers/hydrometers used for
batch chlorination^
4. Checking 1254 quality passing through the #3 still
system.
5. Checking moisture level at #7 storage (1154 feed
stock).
6. Checking moisture level in #2 and #3 batch chlorinators.
7. Running "isolated" 1016 column bottoms as 1154 feed
stock.
v
.
8. Running "double" catalyst charge 1154 batches.
' 9. Checking FeCl3 levels in "single" and "double" charged
batches.
10. "Bad" 1254 has been blended to give "good" Pyranol 70-30.
11. "Bad" 1254 has been released for shipment to transformer
customers.
12. AR&D has simulated olant S.T.O. distillation of crude
1154.
'
13. Changing out #1 absorber Porocel (in process).
Despite the above actions, the thermal chemical chlorides (TCC's) and Monsanto (Munch) stabilities remain out of specification.
Other possible sources of instability were discussed, and an action plan was drawn up. These actions and their areas of responsibility include:
%
. DSW 310128
STLCOPCB4070115
)
K. E. Boucher, et al AROCLOR 1254 STABILITY
Page 2 4/8/74 WGK
PRODUCTION
Operate only a single batch chlorinator for a 2-3 day period.
Check adequacy of Cl2 demister elements. Check the batch chlorinators CI2 spargers.
>* -
Check the batch chlorinators temperature instruments.
Check the #3 still system tenperature, level and pressure instruments. 6$l (JVC
Check the continuous chlorinators Cl2 spargers. (Item 6 on
hold.)
*-
.
LABORATORY
............
7. 8.
9.
10. 11.
Check FeCl3 levels on 1154 batches for 2-3 days.
Lab chlorinate pre-January 1974 biphenyl to 1154 and lab
distill.
.
Lab chlorinate post-March 1974 biphenyl to 1154 and lab
distill.f Lab distill "bad" finished goods 1254.
-
Evaluate WGK analysis of methyl-biphenyl content in biphenyl.
A subsequent meeting will be scheduled late April to discuss the results of these actions.
If you have any questions, please contact me.