Document Znq823Zoy7KNXXvZvw6bEMxzY
v-
LEAD POINT SOURCE CONTROL COSTS FOR MEETING LOWER AMBIENT ATRK rQnUiAArL.ITTrY/
STANDARDS
r v f) '
"
, D/w !/>#&*- 1
` ' OVi-- ,,
2.' /3fC 3>#
fK
5 *** ** ik^-M fdUjfio
work- j ** ft il^oSJtJL A/f*
)
w1
Prepared for:
JU*JL 4*4 Swy
Lead Industries Association
*
Prepared by:
^ f/ia.i/&. jadL -fo &*
Gale P. Hoffnagle, CCM
*r *f/>
^ Project 3952-P51 ^ June 1987
~ * '**'"* (M- & 4 w
TABLE OF CONTENTS
SECTION
EXECUTIVE SUMMARY............................................................................ .....
1.0 INTRODUCTION ...........................................................................................
2.0 2.1 2.2 2.2.1 2.2.2 2.2.3
LIA COST ESTIMATES............................................................................ Cost Estimate Methodology........................................... .... Cost Estimate Results................................................................... Present Costs ........................................................................... Meeting a 1.0 pg/m3Standard.............................................. Meeting a 0.5 pg/m3Standard ..............................................
3.0 3. l
BUREAU OF MINESCOST ESTIMATES.................................................. Bureau of Mines Results..............................................................
4.0 4.1 4.1.1 4.1.2 4.1.3 4.1.4 4.1.5 4.2
ADDITIONAL CONTROL REQUIREMENTS . ........................................... Review of Available Modeling Information ................... Glover............................................................................................... East Helena..................................................................................... Buick.................................................................................................... Herculaneum..................................................................................... El Paso......................................................... Consolidated Estimate ..................................................................
PAGE
iii
1
2 2 3 3 6 7
9 10
14 14 14 15 16 16 17 17
REFERENCES.....................................................................................
21
TABLE 1 2
3 4
5
LIST OF TABLES
Lead Industry Control Costs .................................................................................
Capital and Operating Cost Summary for Ambient Air Environmental Controls for Buick, Herculaneum, Glover, and East Helena . ............................................................................
Lead Emission Reductions .....................................................................................
Control Costs to Meet 0.6pg/m3 Primary Lead Smelting
Industry
......................... .....
s............. .
Consolidated Estimate ..........................................................................................
PAGE 5
11 12 19 20
-11-
EXECUTIVE SUMMARY
This report estimates the costs of air pollution controls wfuch would be
required by the lead industry (primary and secondary smelting, battery
manufacture and tetraethyl lead production) should EPA promulgate either a 1.0
pg/m1 or a O.Spg/m1 National Ambient Air Quality Standard for Lead.
The report concludes that $401 million in capital costs and $35 million m
annual operating costs would be required to meet a 0.5pg/m3 NAAQS. \ This
total cost has been arrived at by adopting the costs to the primary smelting
industry for complete enclosure of smelting operations derived
he Bureau
of Mines and adding to that the costs expected for ota<*contro 1 s at primary
smelters and the costs expected for the othec^iroustry sectors.
1.0 INTRODUCTION In preparation for hearings of the Clean Air Science Advisory Committee
(CASAC) of the Environmental Protection Agency (EPA) in March of 1986, both the Lead Industries Association (LIA) and the U.S. Bureau of Mines (BOM) prepared cost estimates of air pollution control requirements to meet a 1.0 or 0.5 pg/m3 NAAQS for lead. This report combines the work of both efforts into a unified estimate since neither earlier effort satisfactory covered al1 facets of control costs.
-1-
2.0 LIA COST ESTIMATES 2.1 Cost Estimate Methodology
A lower NAAQS for lead would require that stationary sources be re-evaluated for compliance with a new standard. In addition. State Implementation Plans would need to be revised and new controls placed upon existing stationary sources. While the full impact of that process can hardly be anticipated, a preliminary estimate of the costs was attempted by LIA through a questionnaire. The LIA questionnaire to all point source lead facilities1 asked for data on control costs to meet the existing standard of 1.5 pg/m3 and two alternatives, 1.0 and 0.5 pg/m3. It was assumed in all cases that the quarterly averaging time would be retained for the standard. This assumption makes for easier engineering judgements of how much control would be required to reduce emissions by 1/3 or 2/3. To the extent that EPA chooses a monthly average standard or an increased sampling frequency, these projected decreases in emissions are underestimated. A host of other variables such as modeling uncertainties, regulatory uncertainties and local and public pressure also cannot be quantified in these evaluations but may also cause these projected costs to be underestimated. That means that a 1/3 emission reduction will, in all likelihood, be insufficient to obtain an acceptable SIP to insure attaining a 1.0 pg/m3 standard at the plant fenceline. Similarly a 2/3 emission reduction would not insure attaining a 0.5 pg/m3 standard.
The costs of control presented here represent a single focus view of the cost, i.e. what the plant-level engineer expects the costs would be to achieve the stated emissions reductions. In many cases although not generally for battery plants, the plant-level engineer has a reasonable idea of the expected costs because of the recent completion or near completion of the SIP's for
-2OR5901147
\
i *
not gene ra 1 i y reflect ad l 3
CO rporation.. or the 1 ead
industry as a who Le ot these increased c< rol costs. The indust
especially the primary segment, was not in a pos .on to provide comprehens i ve
estimates since the feasibility of Q.5pg/m3 was doubted. IInn many ca ses
the plant-level engineer decided that reaching ai 00... 55 pg/m3 staandard wo uld
be "technologically infeasible". In a few more cases the plant-level engineer
s?offered that the plant would be closed before
to reduce emissions
most cases, however,
incurring the the viability
significant costs of the plant site
was not actively considered in developing a control cost. In no case was the
viability of the corporation considered, and the macroeconomic impact on the
lead industry has not been considered at all.
. VI/P^ 7^
2.2 Cost Estimate Results
Given that methodology, the results of the survey are presented in
Table 1. Costs are presented in thousands of dollars for three scenarios.
The first is the costs to achieve the present 1.5 pg/m3 ambient standard,
and the latter two columns present the incremental increase in control costs
to achieve the alternative standards. Costs are divided by industrial sector
as in the body of this study. In addition, they have been extrapolated to the
entire industry using the number of facilities existing in each sector (The
first line in each sector is reported costs with number of facilities in
parentheses while total industry values are on the second line).
The costs provided in Table 1 must be considered as substantial
underestimates of actual costs to be expected. Since the estimates were made
in 1985 it has become clear that EPA will force substantially greater control
-3-
costs to meet 1 . Syg/m1 , especially at the primary smelters. While these estimates were made on the premise of meeting the standard at the nearest monitoring site or nearest exposed children, EPA now requires meeting the standard at the fence line. Additionally, it has become clear that enclosure of the smelting operations (see Section 3) is 'unavoidable if a 0.5 yg/m5 standard is to be met. The doubt registered by plant level engineers, especially in the primary industry, was well founded. Therefore, *the costs presented in Table 1 must be viewed as a preliminary industry yanac based upon
'abut' what might be required and concern about what the industry could afford.
2.2.1 Present Costs
The column listed "present costs" reflects the air pollution control
equipment placed in service recent years or to be placed in service to meet
present SIP objectives. The primary objective is meeting the 1.5 yg/mJ
NAAQS for lead. Some facilities, most notably battery plants (12 out of 49
responding) do meet that standard at the nearest monitor without requiring
additional controls. In a few cases the expenses recorded will result in
overachieving the 1.5 yg/mJ standard. This occurs where public pressure
has forced substantially tighter controls, e.g. Dallas, Texas. In all
likelihood, the measured fenceline concentrations are now or will be less than
1.5 yg/m1 when the SIP controls are in place.
The timing of the costs cited under "present costs'* varies substantially
for the facilities. Since some of the capital costs were incurred as long ago
as 1980 and some of the capital costs are not to be incurred until 1988, the
cost basis varies. The operations and maintenance (0+M) costs more likely
reflect current 1985 dollars. SIP requirements have become substantially more
-4DR5901l49
TABLE 1
LEAD INDUSTRY CONTROL COSTS' (Thousands of 1985 Dollars)
Industrial Sector (# of Facilities)
Present Costs Capital O&M
Costs to Meet 1.0
Capital
O&M
--------
jm Costs to Meet 0.5 ^Capital O&M
Primary
Refinery Tetraethyl Secondary
Battery
Total Reporting Industry
(3) (5)
(1)
(1)
(ID (23)
(49) (98)
19,825 33,042
3,207 14.203 5,345 23,672
900 1,500
30,766 51,277
1,725 2,875
7,416
717 2,250
110 4750
140
7,000
3,000
it
it 3,000
500
24,889 52,691
5,414 8,611*** 11,320 18,084
696** 17,502***
2,034
36,755
1,499*** 3,079
26,659**** 4,903
53,318
9,806
359***** 1,600 718 3,200
14,335****** 3,402
28,670
6,804
85,789 153,467
17,241 25,423 30,188 44,724
3,579 6,844
70,353 124,452
7,266 13,398
* Believes the plant could meet this standard ** 3 facilities believe they could meet this standard *** 3 facilities believe they would be forced to close **** 12 meet without controls ***** 18 could meet, 6 would close ****** 3 could meet, 2 more would close
*It is demonstrable that these costs are substantial underestimates, especially for the primary industry. They were generated in 1985 and represent, on the whole, what industry could afford rather whan what would be actually needed to meet the various standards.
-5-
R5901150
rigorous since these estimates were made and it is clear the greater expenses will be required, especially in the primary industry, than anticipated by this 1985 estimate. The resulting total outlay for the industry to attempt to meet the 1.5 pg/m3 standard or othe r airborne lead requirements will be substantially, higher than the $150 mill ion in capital costs spread over eight years and $30 million per year in operations and maintenance costs reflected in Table 1.
2.2.2 Meeting a 1.0 pq/m3 Standard
Projected incremental costs to attempt to meet a 1.0 pg/m3 standard
are presented on Table 1 in the second column. These totals for the industry
are about $45 million in capital costs and $7 million per year in operation
and maintenance costs. It is assumed that these costs represent 1985
dollars. These costs are lower than otherwise might be expected because a
substantial number of facilities feel probably inappropriately that they can
meet the standard with present or proposed controls listed under "present
costs". A total of 22 reporting facilities
they can meet 1.0 pg/m3
without further controls. This XselThg comes from either measured fenceline
data after installation of controls reflected in "present costs'* or model
projections that after "present cost" controls the achieved. Six battery plants are apparently marginal
1.0 pg/m3 would be
JZ3L would
be forced to close if 1.0 pg/m3 were required.
In extrapolating to the totals for each industrial sector, costs were
scaled without including the percentage of facilities which feel these could
meet the standard. For example, out of 49 battery plants reporting, 24 would
49-24 not incur costs so the ratio--------- was applied to the 98 plants in the total
49 . industry, i . e., multiply costs by about two.
-6-
The costs of attempting to meet a 1.0 pg/m3 standard would apparently fall most heavily on the primary and secondary industries. But since the actual SIP process often results in overcontrol and since a monthly average standard may be adopted, these costs are grossly underestimated and the entire industry would bear much larger costs.
2.2.3 Meeting a 0.5 pg/rn3 Standard
Projected incremental costs to attempt to meet a 0.5 pg/m* quarterly
average standard are presented in the third column of Table 1. These totals
Q ..
.
for the industry are 125 million in capital costs and $14 million per year in
operation and maintenance costs. This column reflects costs of going from 1.5
to 0.5 pg/m3 rather than just from 1.0 to 0.5 ug/rn3. The plant-level
engineering approach reports that at least 3 secondary and 8 battery plants
would be forced to close with a 0.5 pg/m3 standard. As mentioned before,
this evaluation of closing does not truly reflect plant margins, corporate
decisions or lead market
^which might force closing^-ef--additional
plants. It also reflectsjV feeling~x>f|what the industry could
than what it will actually take. In addition it does not consider non-air
control costs which may force closure. Only 3 battery plants out of all the
facilities in the industry feel that they could meet a 0.5 standard without
additional controls.
These projected costs are seriously underestimated because of the
proximity of Q.5 pg/m3 to background or non-stationary source
concentrations. GCA* has estimated that, by the year 1995, concentrations
of lead due to automotive sources would average 0.02 but could go as high as
0.13 pg/*. In addition, reentrainment of soil dust lead accounts for
some reasonable fraction of measured lead concentrations.
Practical
experience with comparisons of modeled versus measured concentrations suggests
-7-
0R.59R1 t s?
that reentrainment accounts for 10-20% of maximum measured concentrations at
stationary source locations. These other sources of lead suggest strongly that
the emissions from stationary sources will have to be reduced substantially
more than dividing by 3 to demonstrate attainment of a 0.5 (ig/m3
standard. If the averaging time is monthly rather than quarterly, it may be
infeasible to meet the standard short of shutting down the facility.^
r facility closure does not terminate all contributions to ambient air.
For
example, ambient concentrations at Bunker Hill exceed monthly averages of 0.5
8- -
3.0 BUREAU OF MIKES COST ESTIMATES
The U.S. Bureau of Minesz chose a different methodology to estimate
costs of controlling lead emissions. 3GM 1 imited their study to the four
operating primary smelters; Buick, Glover, Herculaneum and East Helena. El
Paso was not considered because it is temporarily closed. As of this date
Buick is also temporarily closed.
BOM took an engineering approach to the problem of reducing lead emissions
from these four primary smelters. They reviewed the present controls either
in place or
required by the SIP's which seek to meet the 1.5 pg/m1
standard. They concluded that they would focus their efforts on process
fugitive lead emissions rather than point sources or open fugitives. Point
sources were not considered because stack emissions are controlled to meet
Best Available Control Technology (BACT). Open fugitives were not considered
because wind-blown dust from stockpiles, soils and roadways have been a
subject of major control in most SIP's and engineering of further controls is
not only difficult but of unknown efficiency. In short, BOM focused on the
following engineering control alternatives to develop costs:
" Closing existing openings on process-related buildings presently emanating lead-bearing fugitive dust.
Enclosing open concentrate, sinter, and storage areas that are sources of dusts containing lead.
Installing new baghouses and adding fans for positive ventilation.
Adding selective local controls."
The need for the latter two items is because building enclosure has been shown to increase employee exposures to airborne lead, usually well in excess of OSHA standards therefore necessitating localized controls.
9- -
3.1 Bureau of Mines Results The results, in terms of cost, were presented by BOM2 in Table 6 which
is reproduced here as Table 2 for completeness. They chose to provide an alternative cost for a new technology, continuous drossing, which would require more capital but, BOM claimed, lower operating posts. Although there was a qualitative conclusion that the alternative might result in less emissions, no quantitative estimate was made.
The costs are further refined in the Appendix of the BOM report to delineate the costs for each of the four smelters evaluated. They are separated as follows for the conventional technology:
Buick Glover Herculaneum East Helena
Costs ($1.000)
Capital
O+M
55,174 97,029 60,190 37,627 250,020
3,517 7,796 4,517 2,677 18,507
BOM did not attempt to provide ambient air quality modeling of the emissions after controls. It is difficult, therefore, to discern whether the proposed controls would provide reductions in ambient air quality concentrations to the 1.0 or 0.5 yg/ms proposed NAAQS. BOM did provide a "theoretical emission reduction" in pounds per day (lb/d) which might be achieved at maximum efficiency of control operation (most baghouse efficiencies would have to increase to 99+% control>. BOM did not cost the reductions from point sources or open fugitives that are inherent in the "theoretical emission reduction". The results of the reductions are shown in Table 3. Table 3 shows that the "theoretical emissions reduction" from the enclosure of process fugitives ranges from a 6% reduction at Herculaneum to 39% reduction at Buick (see Process Control Effect line).
-10-
DR5901155
TABLE 2
TABLE 6*. - Capital and operating cost summary for ambient air environmental controls for Buick, Herculaneum, Glover, and East Helena
Category
Cost Summary
Conventional Drossing Process Technology
Capital Costs
Existing building closure Baghouse New building Local control
TOTAL CAPITAL COST
Operating Costs
$ 5,217,500 161,933,600 31,243,200 51,619,800
$250,014,100
Baghouse New building Local control
TOTAL OPERATING COST
13,960,700 638,400
3,908,700
$ 18,507,800
Continuous Drossing Process Technology
Capital Costs
Existing building closure Baghouse New building Local control
TOTAL CAPITAL COST
Operating costs
Baghouse New building Local control
TOTAL OPERATING COST
$ 5,217,500 161,933,600 31,243,100 59,950,500
$258,344,800
13,960,700 638,400
1,505,600
$ 16,104,700
* Reproduced directly from BOM report2.
1iiiiiiiuiiiiiiiiiiiniiiMiiiii
R5a0i 56
TABLE 3 LEAD EMISSION REDUCTIONS*1
Current Lead Emissions**{Ib/d)
Theoretical Reductions from Point and Open Fugitives (lb/d)
Theoretical Reduction from: Process Fugitives (lb/d) Percent Control Attained (X)
Total Theoretical Reduction (lb/d)
After Controls (Ib/d)
Process Control Effect (X of Current Emissions)
Total Control Effect
(X of Current Emissions)
Glover
882
393
160 92.0
553 329
81.9
37.3
Buick
Herculaneum
1.181
1.780
286
1.243
465 60.3
527
654
101 52.3
1.344
436
60.6
94.3
55.4
24.5
* Data from BOM study1 ** Assumed to be equivalent to sufficient to meet 1.5 pg/raJ NAAQS
-12-
OR53011
Because East Helena has used a chemical mass balance method of quantifying emissions, the results of controlling process emissions are presented in terms of ambient air quality. Out of a total of 5.29 pg/m3, process emissions account for 3.33 pg/m3 or 62.9%. It is difficult to judge how much reduction might be attained from control of these process fugitives. At the other smelters BOM projected control efficiencies from 53.2 to 92% (Table 3, Percent Control Attained) for the proposed building enclosures and evacuations. This might imply a similar range of reductions at East Helena, i. e., 1.77 to 3.06 pg/m1 reductions, if the same control range could be attained and the effect on air quality were proportional.
-13-
4.0 ADDITIONAL CONTROL REQUIREXENTS 4.l Review of Available Modeling Information
Given that the Bureau of Mines did not deal with either point or area source of lead emissions, it is necessary to check whether these sources would also require controls to meet a 0.Syg/m' standard. Significant modeling
i efforts have been undertaken in revising the State Implementation Plans for Lead. In each of these efforts, controls were imposed until the modeled concentrations plus background concentrations from other sources were equal to or less than 1.5 yg/mJ. A review of these studies has been conducted to discover the percentage of remaining ambient concentrations due to the various source groups.
4.1.1 Glover In analyzing the situation at Glover, an April 1984 modeling study by Region VII EPA has been used. This study reviewed the contribution of major source categories to the maximum predicted concentrations prior to controls to meet the 1.5 pg/m3 standard. It indicates that the following source categories can contribute up to the stated percentage of the maximum concentrations:
Sinter Building Fugitives Blast Furnace Fugitives Dross Building Fugitives Defining Building Fugitives Point Sources Area Sources
<22.5% <31.6% <35.3%
<8.3% <8.5% <55.9%
These maximum percentages occur at different receptors and times (the total is not 100%). Although there has been considerable debate about which receptors in the modeling represent "ambient air quality", one was selected for the following breakdown:
R5901159
Sinter Building Fugitives Blast Furnace Fugitives Dross Building Fugitives Defining Building Fugitives Point Sources Area Sources
20.65* 31.52* 35.28*
7.61* 3.43* 1.25*
It is immediately apparent that at this maximum concentration receptor the process fugitives dominated the pre-SIP modeling result. The point sources do not affect this receptor much because of its close proximity (stack emissions have their maximum impact much further downwind). Area sources do not effect those receptors much but are very important at other receptors.
The final SIP to meet 1.5 pg/m3 has yet to be approved and the post SIP mode ling is not yet finished. The basic plan is for substantial controls on process fugitives, i. e., partial building enclosure and ventilation with construction of new baghouse capacity to process the ventilation. Additionally there are area source controls primarily to reduce impact at a different receptor.
Recognizing that the area and point sources could individually exceed a 0.5 pg/m3 standard, it is probable that electrostatic precipitation (at $1 million) on the main stacks and more area source controls (at $250,000) would be necessary. If we estimate those costs at $1,250,000 capital and $225,000/year O+M, the result for Glover would be $98,283,000 capital and $8,021,000/year O+M when added to the BOM estimate of $97 million to control process emissions.
4.1.2 East Helena Mo air quality dispersion modeling has been performed for the current status of the East Helena smelter since reliance has been placed on the chemical mass balance (CMB) technique. The CMB results presented in the BOM report2 indicate 1.80 pg/m3 from non-ASARCO sources, which makes
-15-
DR5901160
attainment of a 0.5 pg/m! standard problematical. CMB also assigns 0.16 ug/ra1 to open fugitives and nothing to point sources.
It appears, therefore, that the maximum possible effort would be required from the smelter on process fugitives. The BOM report2 concluded process emission controls would cost $37.6 million. It is expected that more area source controls would be necessary and should add $500,000 in capital costs and $50,000/year in O+M costs. The total for East Helena would therefore come to $38,100,000 capital and $2,727,000/year O+M.
4.1.3 Buick
Because Buick and Herculaneum have chosen a SIP which relies on monitoring
as opposed to modeling, little modeling has been performed. For Buick, only
the monitoring plan4 contains some hints about relative impact of process
versus other sources. It projects that, at the maximum location, 95% of the
concentration is due to "all fugitive sources" and 5% is due to the stacks.
Again, the predominance of the process fugitives seems evident. While there
is substantial disagreement about the absolute value of the modeled ambient
air quality, it is probable that the point sources or area sources could also
exceed a 0.5 pg/mJ standard by themselves.
It is therefore again
appropriate to add point and area source control costs of $5,255,000 to the
BOM costs for process fugitives. This results in a total for Buick of
$60,429,000 in capital costs and $4,043,000/year in O+M costs (assumes 10% of
capital cost per year to operate the point and area sources controls.)
4.1.4 Herculaneum The only modeling available for Herculaneum* is for the point sources only. This indicates that control of point sources would be necessary to attain a 0.5 pg/m1 standard even if process sources and area sources were
0R5991ici
control led to the maximum possible. If we use the 3ame costs as Buick for point and area source control, this would result m a total of $65,445,000 capital and $5,043,000/year 0+M costs.
4.1.5 El Paso BOM did not investigate the situation at El Paso because the lead plant is presently not operating. Despite this idling of the plant, ASARCO has pursued a final SIP and it is reasonable to assume that the plant may reopen if market conditions allow. The final modeling for post-SIP compliance yields a maximum quarterly concentration of 0.87 pg/m5. At those two maximum concentration locations, the contributions by source category are as follows:
Points Process Fugitives Area Sources
RECEPTOR 5 hsl/jb3
35.6 63.2
1.1
.31 .55 .01
RECEPTOR 24
X pq/rn
53.0 40.8
6.2
.46 .36 .05
can be seen, the process fugitives are still the largest category but in order to meet a 0.5 pg/m1 standard with room to spare for other sources, some control of point and area sources would be needed. A somewhat confusing factor at El Paso is that the copper smelting plant contributes 0.12 pg/m5 of the above total. It seems that for El Paso to attempt to meet a 0.5 pg/m* standard it too would have to enclose the lead process a la BOM and provide some point source controls. It is therefore reasonable that the average cost at the other facilities might be needed; i.e. , $65,570,000 of capital costs arid $4,959,000 for annual O+M.
4.2 Consolidated Estimate It is possible with the above information to estimate the total cost to
the primary industry of controls to attempt to meet an ambient air quality -17-
DR5901 1 b'2
standard of 0.5 pg/m1, Table 4 provides this estimate. The 8CM estimates for control of process emissions are probably higher than possible, given the industries problems, but contain necessary costs that would assure compliance. The presence of background concentrations, the possibility of a monthly average rather than quarterly average standard and the potential for continuous rather than every six-day sampling mean that the combined costs presented in Table 4 are in all 1ike1yhood, and underestimate.
Table 5 presents a consolidated estimate of the control costs expected across the entire industry for all the potential standards. It is already known that costs for controlling to meet the present standard {first column) are going to be considerably higher than these estimates based on 1985 data. This is because of considerable tightening of the definition of ambient air quality being used now by EPA. These additional costs would not necessarily allow for easier compliance with a lower standard since EPA would retain the same definition.
The costs to meet a 1.0pg/m3 standard as presented in Table 5 are expected to be a severe underestimate especially when compared to the requirements to meet a 0.5pg/m3. A more logical conclusion would be that half the costs needed to meet 0.5pg/m3 would be needed to meet l.Opg/m*.
-18-
TABLE 4
CONTROL COSTS TO MEET 0.5 ug/ni! PRIMARY LEAD SMELTING INDUSTRY
($1,000)
SmeIter
Buick Glover Herculaneum East Helena El Paso
Total Process Total Points
and Areas Total All
Process Fugitives (BOM)
Capital
O+M
55,174 97,029 60,190 37,627 62,505
3,517 7,796 4,517 2,677 4,627
312,525
23,134
327,850
24,793
Points and Areas
Capital
Q+M
5,255 1,250 5,255
500 3,065
526 225 526
50 332
15,325
1,659
-19-
o
X>
3C 3o
03
e X0I
r--4 0u
H
X(0J cn
a its o
O
a
cOo' r-
ur0o0>
ooin
Or-'' oN
o 00
*
rH ton
CM CO M0 00
CM CO
tO0o0*
mO r-*
o oo
.
mm
oniD
%
in OCM
V
r-' CCMO
CO
MCOD
CCMD
rH
o
C o n so lid a te d E stim ate
(Thousands o f 1985 D o lla rs )
It
in
u 5
a0)i Oi'
X -h
xoi
o
Xl
tn xc>o
CM 3
O
u
oo
O rH
in rH
rH
<* CO O
V
CM
CM o
r- m vD CM
sv
CO CM <M
CD O
\
GO rH
O0
CM
CQ xi ^5 <? O u
rH Xl O c Xi CD H CM /T UO &
u Q
XI U cn
m
oO
*
* rH o CM o GO
CO P*** o CO GO GO
**
rH
tn
CO rH <y*
*
rH o
CO
CM vD o rH 00 X
<* rH o O' rH r-
O *
%
o .
v> CO v
CO r* r* <M CO
.
CO m uo <M
m
rH
O'
c
H
XI
rH
<21
rH
CD
O' -C
c XI
w H
c -H
Ih
**H *44 X
u 9
04 os H
O' c H
x> rH
CD
U
s u
c
o xi
o XI
CD
$
rH <0 X O H
>i
U
x 3 *0 C VH
aM
-W "0 >1 <u c
CD u 4) <8
^e
*H o
3 O c
H
4oJ
*IB* *
O
u
u
o o
2
m 2
^-1 o
~
c <o0
E
u
Qj <O8
--t c cHn
CO
Ua, JS
4o->
c
ua
c *o e `5
g>
U
5 e
* i
& ^ pN
2
u
g0
XI *0
H 4J
Os
c
5
r3H
tt s xi 0 N ^
XI 4
O' 3.
L*
in
s>
>i
O t3 CD
*H
H XI
rH*
S3
O' rH
XI
3JC
o8
^
W
O
9 e
C
XI
9 9
C H XI
'X Id ^
H
9 rH
X 0 ^ fc
>< m
<H O .H d
o 2 J5
x Ql H
3 ki
m H
3
a
9 s
U
3v
a) C o o I
|c
Id o
g,
H rH
99
g rH
o xi u S4 \ .-(
3 3 O H * O'
rH 9 3
o 9 0* 0* in o c U X C fsj IH Oi U u % o m-
-f
x 4-
REFERENCES
1. Hoff nag 1 e, G.F. and Klinger, W.A.: "Exposure To Airborne Lead From Stationary Sources: An Evaluation of Proposed Matronal Ambient Air Quality Standards from Lead", IRC Report 3220-J5I prepared for the Lead Industries Association and submitted to CASAC in May 1986.
2. Smith, R.D., et a 1. : "Lead Reduction in Ambient Air: Technical Feasibility and Cost Analysis at Domestic Primary Lead Smelters and Refineries", Bureau of Mines Minerals Data Analysis Report, May 1986.
3. Daye, R.L.: "Air Dispersion MCdeling Results ASARCO Lead Smelter, Glover, MO" memo to Dewayne Durst, June 4, 1984 Region VII EPA, Kansas City, Missouri.
4. AMAX Lead Company of Missouri, "Long Term Monitoring Plan for Lead", submitted to the State of Missouri DNR.
5. C.T. Main, Inc.: "Assessment of Relative Impacts On Ambient Lead Levels of Herculaneum Lead Smelter Emissions Scenarios" Report for St. Joe Minerals Report 3544-4-1, March 1983.
-21-
DR5901lbb
V/,
i X v3 iti
I '5 U
!7 +, <* V <\
1 (O,
i (X (3::
: (*i f ' (5 ^ Up-: i7.; 1 17
' 19 1 lo;
' 5.1,
1 XL 1
o.4-:' X5"
aV
< 27 ? US -^x\
a
lu
s--
o<
D LU
DC
Q LU b"
o<
Q LU QC
Ou^V
IBBVcVv-m
_ ____ 5 no
330 d
A,D_.... 13
H
sn _A.l
0,5 --
\ 6)0 13o
-'
1X0 \~ID T&0
ml>o VC^D
-2I
70 Ii; 3,-5ry6v-3, io *'"7 <7
Do JXHo
13 _U ,2__......
7L\0 7^0
'1 NOAO 13 ^ "2x^o
60
lit? Bid Bid
17 63 BA 14 \1
WVc ~no (0S0 7Bo 0 ' O-o Ho
1lT> no . 3o 03o0 ' ' 7\o -
u 73 . o_
6>6o
______ 7:0. _...... To
33 ........... \&10
7,1
iGlo
0.1 ......... Ar 7 0
1
i
______ 37).... _...... \~10D
ik ' ]
!_>
C7
III
1
\.o
\3t0
. 3,7 ........... ^ loo
^*s4b
3 r > , =.-- co
-----------
1
1
I
' I I iin n lin n Ml Klt IMII HIM M ill I I |I | I
ORE,5 0 0 3 2 8
' " s2'"".... 3715 1111&' 3jr0
...... ..... ......
(Bo
_
735 017 Stcc7
\7_0 -.fcve^S"
sO~ ~ y z r' vl. I
X -3.
-*5,: 6 -7
"+l' 10 -11
-a -13 114 15 14 ~417 11 17 ----- 3---x 2.1 ---- 25 ^ 2*1
7S *11 , n
Wac
\7o --* 5o
Ho ^3/
O LU b~
0
( W 3.32.
_
c:.l-H^O.73 c
.
.
._ 33 -34
< vJSl 35
Q
LU
DC
LSo . - ^~ ' ^0
-St
4.57
\3o ;;.31
WO 37
430 . :4c
D \4o ~4 j LU 7A 0
bO <
Q
UO -43
V5o -w ~lz> -46
LU U> :4.t
DC u 0 -:4fl
7 74d . - 4S
----- '
O LU
\01o -So 1570 - 51
OS< O
4>\00 1V00
bo
; 52
*53
-*o4
LU - 55
DC %>0 - *5t
7)36,0 -:. 57.
~Z<o& o -- *s%
Q
LU
h O <c Q
LU
DC
Q
JJ
O<
Q
LU
DC
Q
U
<o
Q LU
DC
. ftoi Q ^ _ :\-30o \f
H-frp /
. S3n / ZH2&4
' 3^0 7 135`?z? ^ "Iso v vw / __ __5 D _7___ \<b0 , ^
.."SS-SL^^770 ; ^
~~UoQ Wo /
, \5o L_j
3_to...... ,U%......
VOo , So ^
7d
v<7
4d /
Cxrui-
/-u: yw
J-7q JJI: J-IZ. J~ 73, -74|i /^ -71 5!i;|ii ^'74;! - 77 ^71, l 7q Ao,
y. : 4 w; 7 - ?5 J %(ei
Q
LU
H
o
< o
LU
rr
Q
LU
o < Q
LU DC
\4$0
...
uyo \Mo <\1S0 yu>o
...................................... __
7io ^10 0 Y\7b
W7o ->3 S 0 yio
3>Gi o
\(Q0 St)
3>S0
DRb50k)a:jW
V- f-b -K
Mr?^x-Cvs3^{)
04.
b(.
yA.
O
43.. LLJ
y44s: ./ 4,
o1-- <
Q.r.7,
LU
CC
'9-
/./o
y 10
v/.!3.
Q
JJ
44
<44
O
Q /&.
'/IT.
cr7.7
LU
01..
(.SLo.
Q LU301,
I-
(12.
o
<
Q LU'Ak
A1 DC
'M
M
3esJc
-> 007.
74 (
t "i, /.2)- i <? o <i /W76.SO
7.34
34-40 as\j. v/30.
,75_T.(1 SB +
S3TM 49 143;_43L
.1 S.-J7_._ 11*......
3.P - 46>, (4o.\.7.3o.
44.- 4-
01-41... 44;_/33...
5.<*-j9 & 35-
74" 01 44^35,
2.4" ?. HS-,434..3LSjtJ1.*2M~/3Z
5S:_.(3%04-34.. 33;....39..
04.-43 OT- 44 o,
Q LU
h
o
<
Q UJ
DC
..|J:M..^.:....
L3.-J1 4.C?_*..._. I/.-..(5. 35;..+ .
IO..--03 ...5JL*.._+. ;lo`-Z6> OS _____ ..4.-30 35 * +_
4 -34. 43. :___
04 - 3 4 ! 5 * y 41
. 4 - 30 40-.
^3 r 40_ SX:..744. 42 -31. 37-b ^43. 00,-01 37-4-^44.
1.r43J.i;._.... 1 -31 37 +
1-33 gy___
10-45 3IitTif3.
11-33 34;...044, (7 - 35 -3"... y /4.7. 17-fl 30.- HI.
_7L-.45. _3
4-17 4Q * 4 5 ~Qg SO-
17-11 llr.A'L 40-+oSo.
5. - 11 35 -t-' to-37 (3
fl-34 03*
L
1 OQ____
ik.~3:L (5T"4-yS^
11-30, 33
F-S
A
IS- 3 t 19- X (4.52, ...Cl4,13^ 15-34 7Q-4- sA- 7.475 (TfcOl)
9.707
10.14 ^3.77 7.4<
.YS^47 37-4- tr^--5S.og- (S4.7S) 15 -14 31- SI - 7>g-C (739 )
90.71 fc.
/ 4 4>9
15-0.1 So- vo - So
(5St)
5a
r> r-t .-
/ S.
yL
X.7,
y 9,
//O. Af.A. y fl
213, y f 4.
/J4 t/ f
/IX.. /ri_
/IX. ^Xo /XL MX.
/X3,
(XL
15.
+^f ax XX...
X- FS-EF Gx
t C. ( M Jt o-X-C-i. `'JL.c^, Vh- ( V'l'j ^0 ^
11T.
767.
H ,/2>~ 1 ttfSH ~ 1 #.SX
1.56
34-40 2$~s$'o.... S3-49 43.x/3j,
f-- l yj
15-H 55 * 41SrJJ^Mi____
3.o - 4.6. I42*.._../3X11-4f 44- v/33.
|--
O
| fL-11 43 * "4" 13-23 10*
26.- J4 * 3Si_/34_. 46- ^35.
<C
O
(3-H 17 -
13
--
46*4-
Li 16-IS. 43* X3t-
[5..3Si... .
dJ &sin*aj'C/3z 25-jf ^ 55* 73S.
w'"'
(0-23 51* 4 40-26 27 *
14-34 33* /39. 14 "43 IS* /4o.
Q
4 -31- 35* 4*7 - 3 6 23 *
a
LLl
Ho
<
Q LU
DC
14 - 3 6 I 5 * 3 41
33 -W 12,-3/ 37-+-'43.
. 12-2S 37-4-144.
.
tC
3/
<L /-%
- .4 -30 31:. ..... 2 -43 1^*
3 "37 37* + 2-33 23*
Xo-45 37*4-145. . i1.TM33... 34i_.X44,
1Mfe1 ssIl OH
7-13 37*4Z_-as -3.il>'..
(7-35 13* -'47.
6-17 40* +
n-{% 32* y41.
5 -10 32-
17 -17 46-4-/49.
S- (2 35 4*
(7 -17 40-Wso.
lo-37 i1!
(6-24 17* /5(.
2 20
16-43 (5<X4-y52,
5 - 37
16-31. 33*
7
71* l-
' ' PS
A
1.5-3! |9* X - L6.SZ /JLISI. . 29.31
15-34 70-+- s<i - 7.495 (7-GOfc)
_ '. 9.717
(2.16
*3.7774
15-47 37- 4- 1^= S5.05- (56.73) 92.7!#.
`
15 -14 31* 15 -11 3o-
H - 316 (739)
w - 50
(sx)
/ 4 #9 50 '
uminiiH ORbSfciiyyyg