Document ZBmGe4QV1DqZMEapJDVavJBR0
UVJN 1 Gr
5/26/67
INQUIRY OF ''NEAR MISS" ACCIDENT - HENRY PLANT
Attending:
C. B. Cooper; C. R. Flynn; J. W. Rowe; R. L, Ehnle; G. P. Smith; D. E. Noder, Maintenance Foremen; A. J. Skutt, PVC Production Foreman; J. L. Kingen, Dryer Operator; T. W. Lou and Larry Botolettot Maintenance men.
May 23, 1967, at 0900, two maintenance men were working on a gear reducer that was leaking at compartment #2 on Spray Dryer #2. They attempted to pull the gear box but were not successful. One removed bolts from rotary valve face plate and one had gone for cardboard to place over opening, when the timer opened the damper to compartment #2 and covered one maintenance man with Resin blown out the rotary valve opening. The Dustex rotary valve was locked out in control room. The Maintenance Coordinator had informed the Production Foreman of work that would be done, however, it was not known that the rotary valve would have to be removed.
Conclusions:
1. Job could not be completed as assigned. This was the first time a Duster rotary valve had been removed since PVC operations were started.
2. If Production Foreman or Dryer Operator had known that rotary valve was to be removed, they probably would have thrown switches to timing box which would have let air by pass this equipment.
3. In the future, when MWO's require that work be performed on manufacturing equipment, the area Shift Foreman will sign the MWO, and the operator of the equipment initial the MWO.
4. The Maintenance Men involved had worked on gear reduction units before and realized the entire unit needed to be removed when the plate holding the gear reduce to the rotary valve could not be broken loose.
This is the first inquiry of a "Near Miss'1 accident and the start of a program which will be continued at the Henry Plant.
cc:
Those in attendance J. L. Nelson Dennie Douell/ A. Vittone W, L. Cato
NGC 01489
REDACTED
i_ B. F. Goodrich Chemical Company
Inter-Organization Correspondence
To
Denny Dowell--J.L, Neleon--A. Vittone-
R. Scott--George Pow--Walt Cato Location cieveland--Akron
Date From
May 12, 1967 Henry Plant
WAY 1 5
Subject ^ear m^ss accident,
At 0110 hours, Friday, May 5, 1st class operator
received a puncturr
wound to the inner bicep of the right arm when hit by the Lenape manhead of poly #34,
a lo-supe polymerizer. The wound was of a nature to require 27 sutures, but since
the striking force was somewhat dull the wound did not bleed. After the Doctor had
closed the wound,
was returned to work in order that a close observation
could be kept should complications arise.
The accident was a direct cause of failure to follow manufacturing specifications
procedure, which stated to close the recovery valve and break the vacuum with air.
Operator
was completing the recovery of the poly. He had pulled the
vacuum down to 25 inches. Procedure then called for the inspection, port (figure #2)
to be opened and the bottom valve (figure #3) in this line to be opened to bring the
poly to atmospheric pressure. After reaching atmospheric pressure the Lenape locking
closure could be released and the manhead opened. For some time some operators had
apparently been short-cutting this procedure by breaking the vacuum by means of
pressuring the poly with nitrogen by first releasing the locking mechanism, but
leaving it rest loosely in the curved channel(figure #1), or releasing the locking
closure completely. Thus, when the vacuum was broken the Lenape cover would rise
approximately \ of an inch if loose, or float gently at the first indication of
pressure, and the pressure gauge would also indicate 0 pressure.
SGC 01490
2-- --
redacted
By reconstructing the events in this case, apparently the locking device was released during the vacuum condition of the poly, then with the nitrogen pressure causing the lid to raise slightly, it apparently reseated sufficiently by means of the 0-Ring to cause a build up of nitrogen pressure. As indicated by figure 6 in the attached photo the locking mechanism was in this approximate position. It is evident that
did not observe the pressure gauge at this time, because the pressure recording chart later showed a build up of 24 lbs. of pressure on the poly. With thi locking mechanism resting on the very edge of the locking lug, he reached with his right arm directly over the manhead to release the locking mechanism. This could noi have been done had the locking mechanism been in the curved portion of the lug. (Number 1) (We have demonstrated that the Lenape closure cannot be opened with pressure on the poly, but it would have been possible for the handle to be almost open during the vacuum period and resting on the end of the locking lugs #4.) As he released the manhead, a loud noise first: reported as an explosion was heard through out the poly building. The first assumption was that an explosion had occur but this proved a fallacy, as there was no smoke, HCL fumes, or no visible evidence
charring in the poly. Also the nitrogen release through the poly manhead would have precluded the possibility of ignition at that time. The handle (number 5) struck the operator on the inner bicep of his right arm, and t lower locking lug (number 4) struck the right edge of his hard hat just above the ri ear. The suspension of his hard hat was popped loose and the hat was thrown into tl pipes above. The operator was thrown onto his side about 8 feet from the poly.
was taken to the Doctor's office for treatment. Strangely, the wound bl< not at all, probably because of the sudden force and the dull rounded edge of the handle (number 5) which drove into the bicep, and closed off capillaries.
NGC 01491
--3 - -
REDACTED
was on his last midnight shift prior to a long week end. However, the
Doctor stated he saw no reason that he could not work on the succeeding day unless
bleeding should begin or pain be too intense.
reported the occasion of
neither of these on Saturday, and did return to work at his scheduled time on
Wednesday, May 10.
This injury most easily could have been prevented by properly following the
manufacturing specifications for the operation. In another manner, by merely
looking at the pressure gauge on the poly, a 24 lb. pressure could easily have been
ascertained.
A meeting was held with all shifts immediately upon their report to completely explaii
the accident and further cover the possibility of dire consequences of short cutting
any portion of the manufacturing specification.
Everyone in the plant is quite cognizant of the fact that we were quite probably only
inches away from a possible fatality.
Don Laible Ray Ehnle
DGL:mm Encs. Denny Dowell--2 Encs. J.L. Nelson--A. Vittone--R.Scott--Gcorge pow--Walt Cato--l
NGC 01492
0
NGC 01493
.j.......
Li--^ .lid
(
REDACTED
SUPERVISOR'S REPORT OF ACCIDENT INVESTIGATION
1.NAMEOF INJURED -9
2. JOB CLASSIFICATION
| PLANT
Pl'c.-
1 DEFT.
ANOP"
PJI. NO. Co ^7
AGE J7
APPROXIMATE EXPERIENCE IN THIS CLASSIFICATION
3. EXACT LOCATION OF ACCIDENT
ICE SPECIFIC!
__zJlI____zi/Lr -?j >-*c/L<-=$ --C---/Q ^^
4. DATfc^OF ACCIDENT
jJ
HOURJF gj
..-r- ^ ^ ?
5. DESCRIBE THE INJURY DAMAGE OR LOSS
.ci a.c.^ Z-c**r-ci<$C iCi Jl cc. fXS _C
6. OESCfllQE THE ACCIDENT
(BE SPECIFIC. GIVSCOMPUTTE DETAILS)
gy/<^ n
WWEEAATTHHEERR CONDITION
____C^c_
LOST TIME
XS&. JZL m.
/
YEARS
rtkkCi -2<< - J, ,-^w^y*.
l-.)T ./ lC.-'AL
^
.^A-. /-. . ZZ. i-
/?'l1 , .'jC -yiT' ?1-2>Cr-+L-ln
L. L
*/ .1;
-j^J.r-1 .
..s& Cfi^ isjfjt J--*'- ,
/,'L '-/ hl.~.L.-,-P ,
~t~L^ ^.Y 'V~ *'
l^'l'''-t-
A-'.-
Aj kt c'-' a l/: .. y?.- .. -.>./,.<
-Cy //;.'[ ,i,kT-F.7.,iuc.^ -`v.^ -
n't* i-- %J
Si.r Ci ,<X .'. ^.,
^,-__ -iA-^C ^CC
-
jAliv ^t^rsY^-.-itLu- *A
is.. *-CvtA Tu .-. -/-Ln.t/7 :yrJLi , z4>-n.-
.-.AtZj.
/i--et-C J:c_...,
sVx-rt W__ ^ - f l 1 ^ ' 1 l*~ ^ ~ J IHiETlCtT* j j--*T--
|.,;y.' -'f< , i ^ ^ . r.. <?__ J-''.J^1H lw_ . f
__ tT -w ., fT/--' ISirT.tll
/ji,i..i,i_
7. EMPLOYEE'S ACKNOWLEDGEMENT. *
At
<
/ / /1 V 7 V;
2^'2f J' .
^!
V~ - y , *
^L
('U'l.'-cc.'t.'Vy, T-l'y..k^iJ- As-,
7i >-A-w-L .u 1/Aw^-dyV .
.1^**--'UT^jf'LA-. .
..^Ol^XaJSlA ,-^T,
CU-/iLjftJ- 1M1-V,
p.^j. tte/AywuX.-*. 2^T-t
/V/A. c&iti' A-tc-n^U<
-^/y- ^7^aRECIFICAU.Y. WHAT WAS UNiAF"e "aUOuTThe YCHICLE. MACHINE. TOOL. EQUIPMENT OR PREMISES) IIF ANSWERED. SEE BELOV/I
UNSAFE CONDITION
Z/L__r^.L__________________ 1'L.Cl-j YC- ,
-ALctT-cV .____ r_-----------------------------------------------------
WHY, IN YOUR OPINION. DID UNSAFE CONOfTION EXIST? 1CHECK ITEM OR USE LINE -cT"
^ NOT RECOGNIZED AS UNSAFE CONDITION
n. HIDDEN DEFECTS
C. .
UNSAFE ACT
ZJCC/r
.-'^-.'1
/
F, F. CA. k_ jts-1 /pjjC-
st/ /y,f,^f/ Ji-msgC
REASON FOR UNSAFE ACT
WHAT SPECIFICAU.Y. IN YOUR OPINION WAS REASON FOR UN5AFC ACTT ICHECK ITEM OR USE LINE "I"
DISREGARD OF INSTRUCTIONS
E. NOT CONVINCED ABOVE ACT UNSAFE
FAILURE TO UNDERSTAND INSTRUCTIONS
INATTENTION
=.gl DID NOT KNOW THE NEEOCD METHOD
INDIFFERENCE (LACK OF INTEREST)
, UNSKILLED
MENTAL OR PHYSICAL CONDITION (EXPLAINl
V.i
-br REDACTED
B.F. Goodrich Chemical Company
Inter-Organization Correspondence
------------------------------ *"------------------------------------ 7---------------------------------
To Da,c 5^5- . C. 7
Location
From
Subject p}Q[)PP P\)ZA `Py
/\ fo{\'f
P 't&e, UC^utU^zuj:'+jfcr ^Z.-C^'Z.- J-C-^tu-a^P P
<'-<^rtX'.s<-<rtqj^
i24,*-cZtb
j- ^n.
jfg-^
r
^:z
_ ./r%'~r>'L.
/
&Lo --`^
7. ^'-7
C/L^,
<'
7Zz/a,
/
X-*-ct ^s
'tZcs
t '*
s--*t^ . *\/s ^P-L^ul is-ZZZ-P-
c^.
6FG-10I44
^^ <>T^^<iZbu*ZUu
X.y cZZjZ
Lsksl.
/k 7tZj>~-
rP. /w<3_
7~ aSf ok a O CTr\ ~?dst
NGC 01-195
V
HNRY 013 R CLER CLER 05 05 VCK1146 010
DEtfara^OWELd
JOHN NELSON -
VITTONE
- HAD A' SERIOUS NEAR MISS ACCIDENT THIS MORNING ON THE- 12-8 SHIFT. WAS COMPLETING THE RECOVERY OF POLY 34, A LOW SO PE PJ
SAYS HE HAD PULLED THE VACUUM DOWN TO 20-25 INCHES. WITH THE VACUUMS FOLY, HE TURNED THE HANDLE ON THE LENAPE CLOSURE UPWARD. THIS RELE^Sl
FRESSURE ON THE CLOSURE. HE THEN OPENED THE NITROGEN VALVE TO BREAK STHE-' THE OPERATORS WATCH THE PRESSURE GAUGE ON THE POLY AND WHEN IT GETStB^dKj ATMOSPHERIC, THEY TEN PUSH THE HANDLE OFF THE END OF THE LENAPE LUGSjSpI
ft-SO NOTICE THAT AS THE VACUUM IS RELEASED, THE MANHEAD EASES UPWARDS JP# 1/4 OF AN INCH. THIS MORNING THE OPERATOR SAYS HE DID NOT LOOK AT THETp^1
GAUGE BUT NOTICED tHE MANHEAD EASE UP THEN WITH HIS RIGHT ARM DIRECTLYWV THE MANHEAD, HE PROCEEDED TO MOVE THE HANDLE OFF THE END OF THE LUGS.^.-fiS^
DID THIS, THERE WAS A LOUD NOISE AND, THE MANHEAD FLEW OPEN WITH CONSIDER ABU* FORCE. THE UNDERSIDE OF THE 0 PERATOR ' S ARM WAS RAKED BY THE EDGE OF SHE-^
MANHEAD AND CUT RATHER BADLY. HE WAS THROWN BACK TO THE FLOOR ABOUT, AWAY. THE SIDE OF HIS HARD HAT WAS STRUCK AND THE HAT WAS FOUND I NT HE IP ABOVE.
THE POLY BUILDING FOREMAN, TED MCGHIEY, FIRST CALLED THE DOCTOR AND S
OPERATOR TO HIS OFFICE. THE DOCTOR PUT ABOUT 25 STITCHES IN HIS RIGHt
HE RETURNED TO WORK THE DOCTOR STATED THIS MORNING THAT HE WOULD*
WORK IF THE INJURY DID NOT PAIN HIM TOO GREATLY. THE MAN IS GOING'*
<jJNG WEEKEND AND DOES NOT HAVE TO REPORT UNTIL WEDNESDAY AFTERNOON.
,
BASIS, WE ARE CALLING THIS A NEAR MISS BUT IT COULD STILL BE POSSIBL'E#|ft
TIME ACCIDENT.
. ' -y&h.
I THE TIME, BECAUSE OF THE LOUD NOISE, IT WAS FELT THAT AN EXPLOSION." ` OCCURRED AND THE FOREMAN INDICATED THIS ON HIS REPORT. UPON INVESTIGAT^O; HOWEVER, THERE WAS LITTLE EVIDENCE TO BEAR THIS OUT. NO SMOKE OR HCL'Vl" WERE EVIDENT AND NO CHARRING IS VISIBLE IN THE POLY. WE FEEL THAT THE' WAS PRESSURED WITH NITROGEN AND THAT THE HANDLE WAS RIGHT ON THE OUTERS EDGE OF THE LENAPE LUGS AND THE OPERATOR WAS ABLE TO PUSH IT OFF WIT,H.$ IN THE vPOL Y. WE HAVE DEMONSTRATED THAT THE LENAPE CLOSURE CANNOT BE;;QI>L___ WITH PRESSURE ON THE POLY BUT IT WOULD HAVE BEEN POSSIBLE FOR THE HANDCgM ALMOST OPENED DIKING THE VACUUM PERIOD AND THEN FOR THE ABOVE ACCIDENT] OCCURRED.
VE NOW SEE THAT THIS PROCEDURE IS DANGEROUS AND WE ARE IMMEDIATELY CHA^Qf; SD THAT THE OPERATOR WILL REMOVE THE INSPECTION PLATE AND OPEN THE POLYj&O ATMOSPHERIC PRESSURE ONLY. ALTHOUGH WE WILL BLEED AIR INTO THE POLY NITROGEN, THIS IS THE TRIED AND TRUE METHOD OF BLEEDING VACUUM OFF THE 'tE BELIEVE IT IS PROBABLY BETTER THAN WHAT WE WERE DOING
ray ehnle
NGC 01496
jUL l U9W
L
c
B. f/g oodrich
chemical
company
/ Inter-Organization Correspondence
To: C. R. Flynn
Date: July 20, 1967
Henry Plant
From: C. E. Kemp
Subject: Near Miss Accident from Improper Electrical Lock-out
In the recent investigation of electrical connection failures in the poly building a very hazardous error was discovered: A Maintenance electrician was working on the No. 1 poly agitator dis connect switch without having the starter locked out in the control
room!
The maintenance man had locked out by mistake the wrong piece of equipment.
The production foreman had signed in the maintenance work order without accompanying the maintenance man to the control room starter or to the start button at the poly.
Confusion and doubt about the intended meaning of the Electrical Lock-Out procedure was discovered among the supervisors involved.
Maintenance personnel are being instructed to lock out equipment only when accompanied by the foreman responsible for the equipment.
The sole purpose of this note is to emphaoize the need and con firm our intention to tighten our safety program.
CEKtsfm
cc:
C*,B..Cooper C. R, Flynn - A J. P. Piers M, W. Ross . G. P. Smith"' Safety Dept.
W. W. Walk
J. W. Rowe All Maint. Foreman C. V. Male J. G. Davidson
C. E. Kemp
'GC 01497
B.F. GOODRICH CHEMICAL COMPANY Inter-Organization Correspondence
To: All Concerned Subject: Inhalation of Vinyl Chloride Fumes.
Date; July 28, 1967 From: P.A, DeWitt
On July 27, 1967, a chemical operator helper was washing the walls of poly 28 after dropping the recovered charge to the blend tank. These walls are washed as soon aa possible after dropping a charge to the blend tank since polymer is most easily removed at this time. The helper smelled Vinyl Chloride as he started to work, did not notice anything unusual and lost consciousness.
The chemical operator noticed the helper acting drowsy and caught the helper as he fell toward the poly. The two men fell to the floor, the foreman was called, an pneolator brought to the area, and before oxygen was applied, the helper regained consciousness. After taking oxygen for a brief period, the helper noticed no ill effects from the inhalation.
While this accident did not result in a serious injury, it does point out the well known but often ignored fact that Vinyl Chloride fumes have definite intoxicating effects which can lead to errors in judgment when under the fumes' influence. Since each person has different tolerances to VCl fumes, all people working where Vinyl Chloride fumes are present must take precautions to eliminate the fumes before continuing the work. Failure to do this can result in . utfconsclousness or suffocation.
Anytime Vinyl Chloride fumes are smelled while in a vessel or working on a vessel, the worker must leave the area immediately and re-evacuate the vessel or area. Use of this common sense warning will present serious inhalation or unconsciousness.
PAD/saj
cc:
A.E. Basile C.B. Cooper M.W. Ross (2) C.R. Flynn J.P. Piers C.E. Kemp (2) Dennie Dowell
P.A. DeWitt
MJG 2
NGC 01498
J {/ .
S ~7
ALL PLANTS SHOULD CHECK BONDING STRAPS ON LENAPE MANHEADS AS SOON AS POSSIBLE.
Dennie L. Dowell 11-1-67
J. L. belsoa Cleveland Office
October 27, 1967 C. K. ripaii
Static Ipctk on Unft Wariiiri * Kesry Pint
Ban is tbs lafoiMtioa X btvt comandm tbs tutie ipok okacm4 os tbs Uaapt nsmhead opening. following Is s 41mt ^aBUCien Cm tbt fomn who was oa shift mt tbs tbs la tbs Poly blUiatt
**Ihm Lo*Kp operator bed jast finished mavtrlai tbs poly. X beppeasd to bs tbro t tbs tiaa bo mi ready to span tbs lid. Jwat ss tbs lid was about 1/1 way open, there was a anal! are sr spark that Junpad be tween tbs lower blags as nsiditsil At tba sms tlas of tha apark tbara was a pop or nap tbat could ba baaed,
we triad opening asd closing tbs lid too or three times
after that, bat could not produce tbs spark again.**
tba lneldaat bsppaaed on tho 12*8 ddft and tba for--n coatactad Jia rraeic, oar FfC coordinator, about 074$. Jin got an eleetrleUa to look at this fc--fiataly. Tba alactrlelaa alas triad spaaing and closing tha manhaad and to bo dbaolutaly safe, tbay raplacod tba ground strap, thsy cheeked tbs systan osar electrically and could find nothing wrong. Tba ground strap, uhlab on* rsaoved, shooed seas greenish discoloration but It was checked later la tba ahsp for continuity and appeared to ba O.K.
Since the foramen vae present when tba apark was observed, X have to believe that it actually occurred, lie snepeet that perhaps the strap was not bolted tightly but os bam no proof of this. Do bam bad maintenance inspect tba ground straps on all Lossy* manhoods in tba Poly building to make certain tbay oars all tightened properly.
1 am one losing too pictures of tbs siwhasd la question. Tbs pictures oars tafcee after tbs ate ground strap oas installed.
Us don't hem s greet deal of infemotion to offer other than tba fact that this occurred. We intend to fellow up end taka soaa measurenests to sea whether or net oa can --sure any static buildup across tbs meahead. If you bam stay further suggestions or if X caa supply you with say additional information, please feel free to ask.
C8F: vek
cc: C. I. Cooper
J. P. Piers J. J. valksole 8. P. Smith
11
REDACTED
B.F. Goodrich Chemical Company
Inter-Organization Correspondence
IG^VZD
To ermts-Rerttl Location _ .
Cleveland
Date From
JUL 2 2 1GG0
July 16, 1968
DEP'-
Donald G. Laible, Henry Plant
Subject _ . , _ , Incident of experience value. Near miss to
-7/14/68 08i
Operator-Helper with 5 months experience, received a slight contusion to the inner bicep of his right arm when the hose of the high pressure lance__burst suddenly with a slight tearing of the hose about two inches above the quick coupling.
____
was beginning to lance Poly #28, and had the hose and quick coupling connectic
under his right arm. He had received no water when first closing the trigger, and
had already released it, when he felt the water stream strike his inner right bicep.
The only discoloration was a slight reddening of the area on the inner bicep.
A Plant Manager's Board of Inquiry was held at 0900 hours on 7/16/68 with the
following in attendance:
C.B. Cooper J.J. Palkovic
J.D. Francis T.A. McGhiey
J.W. Greasier
D.C. Redlin
D.G. Laible
It was determined that the coupling on the hose had general rusting on the Hansen fitting which caused the pressure build-up on the hose close to the coupling. This
possibly from repetitious lance extension changing while holding the lance improperly.
The following recommendations were presented for 6tudy and compliance:
1. Emphasize that Helpers use proper.procedure when changing extensions
. in order that k-ink-tny of the hose near the coupling shal 1 nnr nrvuir.
2 Investigate possibility of Stainless Steel Fittings on the Hansen hose
couplings since rusting has been persistent in these areas at Henry. 3 . Install an additional hook near each high pressure hose rack to prevent
kinking near the coupling. Consideration given to installing a section of hose (1 1/8 inch Radiator Type) approximately three feet long at the section near the coupling over the high pressure hose to better protect the lance operator near the coupling. Check with other plants to see if all are using the Hansen series 4 HK quick coupling and if any consideration has been given to a screw type fitting instead of the quick coupling.
Donald G. Laible
CC: J.L. Nelson R.D. Scott E.H. Harrington
S. Pow .E. Brodine W.L. Cato
t J ftUJuJtL fatJU
. /!
*
yj sfi
AA
/
/
Csjukjl yg<ygi^
NGC 01500
redacted
SUPERVISOR'S REPORT OF ACCIDENT 1NVESTIGAT10?J
PLANT
\. NAMr OF.iiOUMED ?. JOU CUA&ilKlCAliON
hrt'T.
PI' no.
s>y.311___I mi
z/
APPROX I,MAI I- 1-XI-trllt.t ICU IN 1 MIS C.l AS SI I" 1CA I'lON
yki/l/iy _____--
3. tXAC r IjPC.Al IOi'J O;- ACt.IDf.NI
...-1:1l/l________
A. OATH OHACCIHLi/t
7 -A.Z________________
S. OL CCRinr 1HL INJURY - DAMAGE OR l
(OE S."l;OI IC>
I'M AM.
WtATHUR CONDITION
____I__________L_Lp.h.i__
LOST TIMti
.S^^Jr .fill- it" i' *!-d!sO- > ..-IjA,.'
DL'scmiif im: Ar.tiDiiMT
(nr: specific, give complete details,)
.J
;____________ ; z,.
;>/
-j1 sll^XlZU^^^jLlLlrlc-/Y^
P.KSt iJ .`if_______-2--e. -
-__________-fll'll
,:-uu________-z_o
l'.
-? <
_C > l.
- y./ls.Zl-r.L-.. - .- -srlA' h
7'
xY -, A
7. rw'LOVEE'i. ac.:;nowlj ijdi:me_nt
SPECIFICALLY. WHAT WAS UNSAFE AVjOUT TIC VLHIC'-E. t/AClHNE. TOOL- ECUITOENT oh I'Nl.MICES? (Ip AKSWKKECl. SEL bl
-- -z-____ /l 7
<*_{.~<);.________ ?..<s<:*sC___0*:. <<r 'J- c i____ ?
^ <--0 ...
UNSAFE CONDITION
-H.il-...
_____/-!-!, ^ -
/' shi'/Zi''-*'
K.V....'H..Y......I.N...Y..O...U...H..O...P..I.N..I.O.N. EDTIOuTUuMfS' AI :. CONDI HON EXIST ? ICHFCK IT L M OH USE LlML "C")
os/,-.
n N OT RbCOGNII'.UD AS UNSAI'E CONDITtOrj
HIDDEN nEFLCTt
.... " ,,Y s, f
,n
SPECIFICALLY. WHAT DIO AAJYOSL DO. OR FAIL TO DO. THAI LLL> TO THIS ACCIDENT ? l,f AUSIVERBl'. BEL ITEM NO. TO LUTLOVV)
UNSAFE ACT
WHA r SF FC-IFICALLY. IN YOUR OPINION. WAS REASON FOR UNCAI IT ACT? (CHECK mu C'liUSf. IINL T"
ClA. DISRIEEGARD OF INSTRUCTION;
E. n NOT CONVINCED ABOVE ACT UNSAFE
REASON FOR UNSAFE ACT
n. FAILURE TO UNDEKSTANLT IN.'S I RUCYION` C. m DID NOT KNOW THE NEEDED METHOD
D. UNSKILLED
F. U INATTENTION
G. F "l INLXI-FEKl- l.'CF (LACK OF INTI-REST)
1 -JH. ML IITAl OH PIIVT.ICAI. CONDH ION (FXPLAIN)
.. _________________________________ ________________________________________
WHAT CPLCIT 1C ACTION 11 AY'. Hill TAKEN TO CONTROL ThI AflOVI. UNSAFE AFT, UNSAF-i: CT CJ ND I i TO N . AND REASON?
coRRr.cnvr AC.rfON
L'l.// `ill ._a. mil .1/1
:i<'
/
v
DAT! r.N FHJS l.rroHT
I7-
l_S_JO!? HrT_HjJD Ar'LOUAIF
s'c/
HEVIrAVrO ANU APPROVED KV
'Jci,- j)ll/-^-i-t, 'hfl -( 1
-tj
_YT:S NICiH')
k.
/-
f) /
j__ j fjQ__ _ ir "NO'J A;TUvC!l T'XFM/Fj AT E>_RYi_r.' pVl cZ
..if'/ // ' V .
^>y ''>!'/ / y/'/ /'
^ 'J
. /y / r O'-' ll'.ul'.ifAT'l: SVrf.ilVISOK-/
1) 1
NG t 01501
B.F. Goodrich Chemical Company
Inter-Organization Correspondence
JUL 1 6 1968
To Dennie L* Dowell
Date July 15, 1968
==mprwr
Location Cleveland
From Donald G. I^ible Henry Plant
REDACTED
Subject Report of Near Miss Accident, 7/11/68 1915 hours to
Operator-Helper FVC with eight months experience, was
with
vinyl chloride vapory near the
wanh^Ad of Poly j? 16, while washing down the p&ly
witn DM Water through the manhead* He was carried to the fire escape landing and
revived almost imnediately by fresh air* ' The pneolator was brought from the laboratory
and oxygen was administered for a short time* He rested for awhile and was referred
to the plant nurse for further examination*
He was examined by the plant doctor on 7/12/68 and returned to work on his
normally assigned shift at 1600 hours on July 12*
A. Plant Manager^ Board of Inquiry was held at 1530 hours on July 12 with the
following in attendance*
C. B. Cooper
C. R. Flynn
J* J. Palkovic
K. L. Mussel man
G. P. .Smith
D. G. Laible
Shift foreman Musselman explained the details of the incident* He was in foreman's
office when operator
i reported that _ had passed out* When Musselman
arrived at the third floor landing fire escape,
had been revived* A pneolator
was brought from the laboratory for administering oxygen*
pplY
bean recovered satisfactorily and shortly after the manhead was
opened,
was washing down the poly with a DM water hose* He passed out and was
helped to the third floor imwUnp; by operator '
This was the first occasion with regard to the pearl poiys of any operator helper coming in contact with excessive VCL vapors*
General Foreman Palkovic reported that tests were run on 7/12/68, and that after
the proper recovery of a poly there is enough residual VCL in the poly to cause acme vapor escape as the poly Is being washed dowrf*
Recommendations *
1* A memorandum was issued this date calling for^jacuErtion^oj^th^goljriMj^^
uBeof^jiejaouatioi^ioseoriwMjowashiiij^lown*^
2* ^adSioSrevaSSa^BnToseso^arsE'o^^KngtEr^operly identified for
this purpose only will be provided1*
ADDENDUM:
It was later discovered this day that
; is unable to readily distinguish the
nf tHtivI
He can detect vinyl acetate which is used only in copolymer
manufacture. A flask sample of VCL could not be Adentifled bv odor by
A Further
research brought up a previous incident concerning
when he was struck on the
cheek unidentifiably while washing down a paste poly on 3/10/68* It is now felt that
he may have been struck on the cheek by the valve handle of the DM Water hose, while
dazed from VCL fumeef* It has been brought to the attention of
the need for
complete procedural following in any association with VCL in the future.
cct J, L* Nelson E* H. Harrington G* Pow V. L. Cato
/
R* D* Scott V, E. Brodine C* B. Cooper C* R. Flynn
J. J* Palkovic
NC.C 01502
^ flcCom/n
^ P6-
c/r P*C pfArtTS
't/W/W
MEMORANDUM FROM THE TECHNICAL DEPARTMENT No. PCI-4-6
To: Date:
J. J. Palkovic 7-12-63
Subject:
Poly Evacuation
1. Immediately following opening the manhead and prior to washing down, each Poly will be evacuated for a period of 5 minutes^using the
evacuation hose.
2. The above procedure will be followed for the purpose of removing excessive fumes from the manhead area.
3. This procedure will apply for all polys - pearl, paste or Lo Sope.
4. The above evacuation will not apply to later evacuation for entry.
Active Tech Memos:
PCl-4-2 item 4, PCl-4-5..
NLK/mr cc/ Normal Distribution
N. L. Ruchenmeister
Vcc!5j
o REDACTED
SUPERVISOR'S REPORT OF ACCIDENT INVESTIGATION
PLANT
1. NAME OF INJURED Z. JOB CLASSIFICATION
-
DEPf.
AND
P.H. NO. * , "* ' **
AGE
/ /
f-1 /
APPROXIMATE EXPERIENCE IN THIS CLASSIFICATION
* 3. EXACT (.OCATION OF ACCIDENT
// .
'
V ' s (BE SPCCIFICI / . .
1
A. DATE OF ACCIDENT
/' //
/ ;
.
5. DESCRIBE THE INJURY DAMAGE OR LOSS
6. DESCRIBE THE /ACCIDENT
. (BE SPECITIC. GIVE COMPLETE DETAILS)
HOUR
D A.M.
1 1 P.M
WEATHI.R CONDITION
. -'
*i
, V*. /
LOST TIMG
i<
[ 1 VIES
... I '
V
/;
.
-/
..
_
..
...
* * '
. f T
> i. . i
. '
'V
... 7. EMPLOYEE S ACIKOWLI DC 1.LIE,'ll
-/
V/.-
; -...
YEARS
R NO
.( ` /
< fj ^ .
-
* * .
t . . -O ;r;.
; , :.T
-; . _____
SPECIFICALLY. WHAT WAS UNSAFE ABOUT THE X'EHICLn. MACHINE. TOOL EQUIPMENT OR PREMISES? (IF ANSWERED. SEE BCLO
UNSAFE CONDITION
WHY. IN YOUR OPINION. DIO UNSAFE CONDITION EXIST? (CHECK ITEM Oft USE LINE "C")
NOT RECOGNIZED AS UNSAFE CONDITION
, HIDDEN DEFECTS
SPECIFICALLY. WHAT DID ANYONE DO. OR FAIL TO DO, THAT LKO TO THIS ACCIDENT? (IF ANSWERED, SEE ITEM NO. 10 BELOW!
UNSAFE ACT
REASON FOR UNSAFE ACT
WHAT SPEC I FI CALLY. IN YOUR OFINION. WAS REASON FOR UNSAFE ACT? (CHECK ITEM OR USE LIKE "I"
a.d DISREGARD OF INSTRUCTIONS
E. NOT CONVINCED ABOVE ACT UNSAFE
B. I I
FAILURE TO UNDERSTAND INSTRUCTION!
p. INATTENTION
C. 1____I DID NOT KNOW THE NEEDED METHOD
G. [Z] IN Dll-FERENC E (LACK OF INTEREST)
D. UNSKILLED
____
___________________________________________________
h. n MFNTAL OR PHYSICAL CONDITION (EXPLAIN)
WHAT SPECIFIC ACTION HAVE YOU TAKEN TO CONTROL THE ABOVE UNSAFE ACT. UNSAFE CONDITION; AND REASON?
CORRECTIVE ACTION
V'
____________________ DAI E or T I 'IS REPORT
______________IS JOE METHOD A LIE O U AT C
REVIEWED AND A< I 'HOVE D BY
EL____________
YES______
IF "NO" ATTACH f-XFL AN ATOF-.Y MEMO IMMEDIATE SUAl IIVIFOII
NGC 0150-1
B.F. Goodrich Chemical Company
Inter-Organization Correspondence
To Location
G.P. Smith Henry Plant
Date
From
9/23/68
Safety Department
Subject
Near Miss--Vinyl Chloride Escape
A vinyl escape occurred from a 2'1 drain line on the #2, 100 series recycle storage tank east of Building 731 at 1515 hours on Thursday, September 19, 1968. The 2" drain line separated from an extension of the bottom drain valve and flew 30 feet The gas alarm was sounded, the bottom chain valve was closed, and the area was clear of vinyl in approximately 30 seconds. No injury resulted. _ J.J. Palkovic, General Foreman PVC, and J.W. Gressler, Safety Inspector, were inspecting a recent modification of the drain line. A 24" pipe extension with an elbow had been added to the drain line on this date to divert water directly to the sewer. While Inspecting the new Installation the drain valve on the #2 recycle storage tank was opened by Palkovic and then closed. Palkovic and Gressler then proceeded to the #1 recycle storage tank. Palkovic then opened the drain valve and all water drained. They then returned to the #2 recycle tank to finish draining the water. Upon opening the drain valve a sudden thrust of back pressure caused the pipe extension and valve to unthread Itself rapidly.
When the pipe and valve were thrown, a large amount of vinyl vapors were releasee to the atmosphere before the chain operated bottom valve could be closed from the north side of the tank. This was complicated due to the fact that the chain was, not .swinging freely and was wrapped around a pipe support.
While Palkovic was closing the chain valve Gressler turned in the building gas aLarm. The gas alarm sounded for approximately 30 seconds and then was silenced
upon Palkovic's instructions. Five minutes later the all clear was sounded.
NGC 01505
The unsafe conditions that existed were as follows: 1. The elbow should not have been installed on the extended pipe. The proper procedure of draining the tank was followed. The proper safety rules and plant policies were being followed.
2. The chain should not have been wrapped around a pipe support. 3. The recycle tank did not have an excess flow check valve in the drain line.
4. Existing drain line was corroded.
5. All fittings were threaded. The following recommendations have been made:
(jT) Install an excess flow check valve.
Elbows on both #1 and #2 recycle tanks have been removed. All chain valve chains will be inspected to assure that they are not obstructed. Replace drain line with stainless steel.
Back weld pipe fittings.
John W. Gressler Safety Inspector
JWG:tnm CC: J.R. Nelson--R.D.
E.W, Harrington D.L. Dowell G. Pow W.E. Brodine W. Cato C.B. Cooper C.R. Flynn J.J. Palkovic Safety (3) File (2)
Scott
A
WajjUtjJL
iNGC 01506
PICTURES TAKEN AFTER REPAIRED
1. This is the piece of drain pipe that was added. The circle is where the elbow was located.
3. This is the chain that was wrapped a the pipe support. This is also the valve that was used to close the bot drain. Arrow 6hows path and final location of pipe.
NGC 01507
REDACTED
January 4, 1969
NARRATIVE REPORT OF ACCIDENT AT HENRY PLANT. DECEMBER 27, 1968
On Friday, December 27, at 10:22 AM, while they were attempting to put IPP Catalyst into a polymerizer from a two gallon, stainless steel,
portable, charging bottle, the bottle ruptured injuring three people. A foreman, Ted McGhiey, had a bad cut on the inside of his left thigh and his
left arm badly cut and shattered just below the shoulder. McGhiey was
taken to St. Margaret's Hospital at Spring Valley, where he died about
2:30 P.M. while undergoing emergency surgery.
a charging
operator, had his left hand seriously injured. The index and second finger
on this hand were removed by a surgeon at St. Francis Hospital in Peoria.
a charging operator, had a facial cut on his left jaw and
a scratch on the left side of his face near his nose.
A portable, stainless steel, charging bottle, about 5% inches in diameter and 22 inches long, was being used because the regular charging bottle was being moved to a more convenient location. Portable charging bottles have been used regularly to add short stops to polymerizers, and also to add catalyst to Low Sope charges. They have occasionally been used to add IPP Catalyst to Pearl polymerizers. These charging bottles are mounted on two-wheel carts along with a standard Nitrogen cylinder which is used to blow the contents of the charging bottle to the polymerizer. The charging bottles are not equipped with pressure relieving devices. Catalyst or short stop is sucked into the charging bottle, the charging bottle connected with a rubber hose to the polymerizer, and its contents forced into the polymerizer with Nitrogen being supplied through a standard pressure regulator. The catalyst in this case was a 20% solution of IPP in Hexane.
were working together to put the catalyst
into No. 1 polymerizer. This catalyst bottle had been thoroughly cleaned
the previous day and, after being cleaned, had been used to put catalyst
into several polymerizers. On the morning of the 27th, the proper amount of
catalyst (slightly more than 1 gallon) was weighed out and pulled into the
bomb through the hose connected to the bottom. The charging bottle was
connected to the polymerizer and the Nitrogen regulator valve opened to
pressure it. The valve to the polymerizer was then opened. Up to this point,
everything appeared to be normal.
who was operating the Nitrogen
regulator valve, believes that there was about 500 lbs. pressure on the
cylinder before use. He noticed that the cylinder pressure was dropping
very rapidly and that gas was escaping from the weep holes to the Nitrogen
regulator body. The delive.ry pressure to the catalyst bottle was about 180
lbs. Since the delivery pressure was dropping much faster than normal,
Ted McGhiey, the foreman, was called over t;o assist. When the delivery
pressure was about 110 lbs., the valve to the polymerizer was shut off,
this cylinder disconnected, and Nitrogen cylinder No. 2 connected. At
this time, the pressure in the polymerizer was about 105 lbs. Cylinder
No. 2 had about 700 lbs. pressure in it. The valve to the polymerizer
was opened and
mentioned to the foreman that they had better hurry
and get the catalyst into the polymerizer before it blew up.
both remember that the charging bottle and hose to the polymerizer
were warm at that time. They estimated the. temperature at about 110 V.
NGC 015f8
REDACTED 2- -
was opening the Nitrogen regulator on cylinder No. 2 and calling off
the pressure on the delivery gauge. He remembers that the pressure was
about 200 lbs, when the catalyst bottle ruptured. The catalyst bottle
fragmented. At this time, the people and equipment were in the approximate
positions shown on the attached diagram. McGhiey,
were knocked to the floor.
was pushed about 10 feet but does not
remember falling. There were no injuries to other people in the area,
except a slight scratch on the left leg of
The time spent in First Aid training at this plant was proven
effective by the very efficient handling of the emergency by several
employees. The large artery in McGhiey's left arm was completely severed
and the doctor believes that only the quick application of pressure kept
him from bleeding to death. The first ambulance arrived quickly and
McGhiey was sent to St. Margaret's Hospital with two employees holding
the pressure points on his arm and leg.
had the back of his left
hand seriously injured and several puncture wounds on the inside of both
arms. He was escorted to the plant dispensary where the plant nurse
attended him till the plant doctor arrived. He was given a shot to relieve
the pain and taken in an ambulance to St. Francis Hospital in Peoria.
The plant nurse went in the ambulance with him.
was taken by
ambulance to St. Margaret's Hospital in Spring Valley.
A Safety Inspector then took several pictures of the scene of the accident. In the meantime, witnesses were asked to dictate their information and comments so that we would have an accurate record while it was still fresh in everyone's mind. At this time, we thought that the catalyst tank had ruptured due to a failure, of the Nitrogen regulator causing over-pressuring.
We then began collecting information and trying to determine exactly what had happened. The evidence now indicates that rapid decom position of the catalyst occurred. We believe that Vinyl Chloride got back into the charge bottle through the connecting hose and polymerized, providing heat and the violent decomposition of the catalyst. There is no evidence of corrosion inside the charging bottle. The inner surfaces are bright and clean. Also, there is no evidence of short stop contamination in the bottle. The Nitrogen regulator being used was a Matheson, Model 9-580. The glass on the low pressure gauge was broken and the needle bent. This regulator has been examined by representatives of the Matheson Co. and found to be in good working order. The regulator on cylinder No. 1 was found to have a ruptured diaphragm. Mr. Okladek, Matheson representative, stated that under no operating conditions should either regulator be able to supply more than 250 lbs. pressure. The catalyst tank being used was rated at 400 lbs. psi pressure. A sample of Nitrogen from both cylinders has been tested and has been found to be approximately 99% Nitrogen. A sticky material which was found on many parts in this area after the explosion has been analyzed.
It appears to be very low molecular weight Poly Vinyl Chloride, containing about 367o Chloride. Metallurgical tests will be run on the metal from the
ruptured catalyst tank.
NGC 01509
The investigation is continuing and a complete report, with pictures and exhibits, will be issued soon. The facts which we have at present indicate that the Vinyl Chloride leaked back Into the catalyst bottle, causing a rapid and violent decomposition of IPP, shattering the charge bottle. The total time which the catalyst was in the bottle has been estimated at approximately 5 minutes. At the present time, we have discontinued using these portable charging bottles and will not resume using them for any purpose until revisions have been completed to make them safe.
C. B. COOPER, Plant Manager Henry, Illinois, Plant
CBC
cc:
D. L. Dowell J. L. Nelson - R. D. Scott E. W. Harrington W, E. Brodine W. L. Cato George Pow C. R. Flynn G. P. Smith File
NGC 01510
CONCLUSIONS:
1. The direct cause of the vessel rupture was overpressure, likely in the range of 700 to 1000 psig. This was caused by vinyl chloride vapor entering the vessel, condensing with heat liberation. This in turn elevated the temperature of the catalyst solution to local ized decomposition of the IPP solution. At this point rapid, selfdecomposition of the solution occurred. At a temperature of approxi mately 158F. instantaneous decomposition of the IPP occurred. This latter temperature is theorized frgm physical data. Witnesses reported temperatures at about 110 F. (skin temperature) shortly before the rupture.
2. The procedure of using this portable vessel for charging catalyst was a temporary method while maintenance was being scheduled on the normal vessel. This technique has been used in the past without difficulty. Operators involved in this operation knew the proper procedure and were using approved methods in this case.
3. The failure of the nitrogen regulator on the first cylinder initiated the sequence of events culminating in the eventual rupture of the vessel.
4. Although this technique had been utilized in the past, the inherent possibilities of such a sequence of events had not been foreseen prior to this event.
5. The use of such portable vessels, either for shortstopping or catalyst charging, has been temporarily discontinued.
6. Engineering is currently working on a new design for two portable vessels to be used only for shortstop charging. This vessel will also have pressure relief.
7. Considerable investigation has been done regarding the characteristics of IPP solutions. The Catalyst make-up and handling system has come under scrutiny. In addition to some procedural changes, we are recommending these equipment changes:
a) Bulk handling of hexane. A D.J. is underway. b) A new upright catalyst freezer for solution storage in the Poly
Building. A D.J. is underway.
An M. A. has also been approved for study of a more dilute solution of IPP (157D) .
8. The Henry plant bad a record of no lost time injuries for all of 1968 until December 27. This emphasizes the point that despite continual safety programs, a good safety record and ratings not the least decrease in accentuation of our safety attitudes and programs can ever be tolerated.
9. The events immediately following the accident illustrate very strongly that the time spent in First Aid training was proven effective. Since this accident we have relooked at our First Aid training and are in the process of updating the program.
NGC 01511
IV. Review of IPP-Hexane Solutions
Al Berens has done considerable investigation in this area which has been reported in recent letters with date line of January 13, 1969, and February 14, 1969.
He confirms that 20% solutions do not undergo strong exothermic decomposition at sample temperatures below 25 C. (77F.). We
have observed this, also, noting practically no decomposition below 90F. At this temperature for a prolonged period, some
bubbling will occur. Berens notes that: from about 130 F. to 149 F., decomposition becomes quite rapid with appreciable generation of heat. Sudden decomgosition (nil half-life) occurs at a temperature about 158 F.
At normal ambient temperatures, we have found that the solution poured over a large surface area will decompose and evaporate without any evidence of ignition or explosive violence. This is not a plant procedure, however. In cold weather the IP? will crystallize before decomposition or evaporation and is then hazardous on warm-up of the crystals.
Al Berens has also conducted these same experiments with IPP-Hexane solutions saturated with VCl. With about 10 - 157o VCl solutions, he noted polymerization adds very little to the exothermic effect (less than 0.25 BTU/minute per pound of solution).
Al Berens has also demonstrated that the primary triggering cause was neither the heat of polymerization nor the heat of the IPP decomposition. My own figures verify his calculations. For instance, the bomb has been calculated as 500 cu. inches or 2.16 gallons. The recipe in use involved 9.1 lbs. of solution which is 1.49 gallons. This leaves 0.67 gallons free space. When the VCl vapors entered the bomb they would be condensed, and in so doing the heat of vaporization would raise the temperature of the bomb by the equivalent sensible heat. Recalling the testimony, if we say the vessel temperature was 115F. just before rupture, this
calculates out to about 2.0 lbs. of VCl condensed. would allow about 4.8 lbs. before hydrostatic.
The free space
When the system reached this temperature, we then get into the rapid, self-accelerating decomposition. These calculations also demonstrate the rupture was not due to a hydrostatic situation after condensation.
01512
Calculations were made to estimate the theoretical pressure in the vessel at the time of rupture. Assumptions used were:
a) IPP decomposes yielding gaseous products at the ratio of 3.8 mols per mol of IPP,
b) None of the catalyst entered the poly during the first attempt.
c) 2.0 lbs. of vinyl chloride condensed. d) When condensing Vinyl chloride raised the liquid temperature
to 115, assume localized heating sites and then rapid rise to about 158 causing instantaneous decomposition. e) Assume heat of polymerization of 0.25 BTU/minute - lb. of solution. Using these factors and recipe quantities, it has been calculated that a pressure in the range of 800 to 1000 psi would be attained.
J. P. Piers
JPP/mr
NOC 01513
B.F. Goodrich Chemical Company
A DIVISION OF THE 8.M00DRICH COMPANY
GENERAL CHEMICALS PLANT
HENRY, ILLINOIS
On May 4, 1965 at 10:30 a.m., a tank truck load of 2700 gallons of sulfuric acid was being unloaded at the truck unloading station of our tank farm. The acid is unloaded by pressuring regulated factory air at approximately 35 to 40 lbs. psi, into the tank truck, and the sulfuric acid flows through a 2 inch rubber hose approximately 12 feet in length, into lines leading to our tank farm storage. This rubber hose is supplied and carried on the tank truck. The regulator valve for the factory air was positioned close to the inlet of the tank farm lines.
The acid hose broke about ten minutes after air pressure was applied, in such a time that full pressure had not been reached. Estimated pressure at this time was 25 psi. A two inch slit opened in the hose about four feet from the truck valve. This sprayed acid approximately 7 to 8 feet into the air in such a manner that it was impractical to reach the air pressure regulator valve.
Our tank farm operator had just left a position near the hose to answer the telephone which rang in the tank farm pump house. The acid truck driver was positioned on the other side of the hose, and some spraying acid did strike him on both arms between the wrists and elbows and some also in his hair. However, our operator would have been in the direct path of the acid had the break occurred as little as a minute sooner.
Our tank farm operator was able to reach the air valve by circling around the pipe rack support, and wearing a face shield and rubber gloves was able to shut off the air supply. Approximately 400 gallons of sul furic acid was lost on the concrete pad of our tank farm, before the air pressure was shut off.
This was the National Cartage Company's first experience of a hose breaking in this manner after pressure had been applied and the pumping actually starting.
Corrective action was instituted immediately should any similar occurrence ever arise. Our air line valve was relocated to a position 25 feet away from the truck unloading hose. In our new procedure both our tank farm operator and the driver are instructed to be at this location when actual air pressure is applied. Along with this action we have modified our installation and we now use instrument air 6upply instead of factory air. It is somewhat lower in pressure and a regulator is not required since its pressure is maximum at around 36 psi. The use of instrument air should greatly aid us in preventing water condensation which had previously caused freezing conditions in our air line in winter at some times when the air was not in use.
On May 25, 1965 our first tank truck load of sulfuric acid was unloaded, and the new procedure met with the approval of all personnel involved. It required approximately 10 minutes more of unloading time than the previous method.
Don Laible Safety Inspector
NGC 01514
B.F. Goodrich Chemical Company
Inter-Organization Correspondence
To Location
K. L. Lindhurst Cleveland
Date From
9/13/66 Donald G. Laible
redacted
Subject
Disabling Injury--
--8/20/66
5 d? =
Pf'
On August 20, 1966, at 03:30 A. M., '
0C
Second Class Chemical
Operator, sustained an injury to his eyes which caused hospitalization and an
absence of four days.
While preparing to add the content of a plastic container of 2.11 lbs. of dry
hydrated lime to the open manhead of a 3300 gallon Polymerizer, the operator lost
his grip on the plastic container. As the container slipped to the floor, he bent
suddenly to catch it in mid-air. The container hit the floor and the lime puffed
behind his safety glasses and into his eyes. He went to the eye bath and flushed
his eyes with water. He was taken into the dispensary and later sent to the
hospital for further treatment since he suffered a superficial corneal burn to
his right eye. He was confined to the hospital for one day and returned to
work after an absence of four days.
In this pearl charging operation containers of lime and phosphoric acid are added
to buffer the w'ater through the open manhead into 250 gallons of water and with tl
agitator off. The present containers used are rectangular plastic containers,
6 inches width on the side, 8 inches deep and with a circular mouth 4% inches in
diameter. The operator wears gloves, and a face shield is available in the
pigment room for use.
This accident could have been prevented by the operator having worn a face shield
or had he turned his head aside instead of reaching in an attempt to catch the
container.
a. NGC 01515
It is hoped that in the near future this method of buffering wilL be eliminated. In the interim, containers with handles for easier handling are to be secured, and a face shield has been affixed to the cart which carries the buffering agents
*
CC:
C. B. W. W. File
Cooper Scull
Donald G. Laible Safety Inspector
\GC 015H>
B,F. GOODRICH CHEMICAL COMPANY Inter-Organization Correspondence
To: C* B* Cooper Henry Plant
Subject: Near Miss Accident Report
Date: October 19, 1967 From: E. V. Wilson
A Plant Manager's Safety Meeting was held at 2:00 P.M* on October 18, 1967, to review the near miss accident to a construction electrician during the morning. Those in attendance at this meeting were C. R. Flynn, G. P. Smith, R. L. Ehnle, J, W. Rowe, M. D. Tawney, E, J. Green, and E. W. Wilson.
As part of the Paste Expansion construction electricians were setting up to pull a new electrical feeder through existing underground duct from the manhole below sub-stations #4 and #5 to the pad west of sub-station #6. They were attempting to do this by inserting fish tapes from both ends of the duct. There was some confusion about the duct openings at the west window in the manhole because the drawing showed a reverse section detail of the duct bundle out in the run between the sub-stations whereaa the window included another row of ducts above this bundle which stubbed up into the high voltage dis connect switch section for sub-station #5,
They were attempting to locate the proper duct by having a person at sub-etatlon #6 yell into the pipe so that the person in the manhole could pick out the proper opening. With cable extending out of these ducts it was impossible for the construction electrician to get his ear close enough to the bank of the duct to ascertain the proper one. The electrician in the man hole selected one of the upper ducts as being the correct one leading to the pad from where his partner was yelling. When he inserted his fish tape into this duct it was fed up into the 4160 volt section ot the sub-station where it finally connected between phases and dropped the sub-station #5 circuit breaker and the main plant circuit breaker.
This happened at 11:06 A.M. The plant electricians shut off all other high voltage feeder breakers except #1 and #2 which are in a different structure. They then checked to find out what the actual cause of the trouble was. Following this they re-set the main breaker plus breakers #3, #6, and #7. Total time elapsed to accomplish this was approximately 13 minutes.
The trip flags were showing on feeder breaker #5 but plant personnel was certain that the unit in trouble was sub-station #4. So an attempt was made to re-set circuit breaker #5. When this failed to energize the unaffected sub-station both #4 and #5 breakers were held open until the trouble was cleared. After the trouble was cleared both circuit breakers were closed and at this time it was determined that the sub-station that was in trouble was actually sub-station #5. This placed all the electrical system back on the line at 11:36 A.M. These last two sub-stations supplied the power for our poly building. During this down-time, production had to partially vent 10 polys on the pearl side.
NGC 01517
0CT 2 3 09
2- -
In review it appears that the construction people failed to use a blower they had for identifying the proper conduit. As a side issue it was later determined that they had failed to obtain a vessel entry permit to enter the manhole but this was not directly related to the accident. The construction foreman admits he was confused from,the Goodrich Field Engineer. The Goodrich job procedures were normal for this type of work except for the failure to obtain the vessel entry permit. The relations between the construction foreman and Goodrich Field Engineer are excellent.
Additional observations are as follows:
1. The 5 KV cables in the manhole look similar to the 600 volt feeders so that there was no warning to the electrician that he was putting the fish tape into a high voltage conduit bank.
2. Original construction failed to properly blank off the open ends of the conduit where they stub up into the high voltage disconnect switch enclosure. This was clearly called for on the original drawings and is considered good practice by all electrical contractors.
3. The failure to get back on the line in a reasonable period of timehas . to be blamed on lack of identification at the sub-stations.
4. A small mark on the west end of sub-station #5 included a #4 which apparently was written there at the time of manufacture or shipping. This mislead our maintenance people as to the true number of the sub station. This marking must be obliterated.
5. Another problem noted was that the high voltage circuit breakers were temporarily tagged by marking on a piece of masking tape instead of permanent name tags.
6. Another factor that created confusion with getting back on the line involved volt meters and ammeters at the sub-station being in the off position, with the switches for these meters located some 18" below the devices they were controlling.
7. A major complaint on getting the sub-station back on the line concerned poor communication between the high voltage switch station and the low voltage sub-station. Not only the distance involved but, also, that the line of 6ite was obscured by large clouds of steam issuing from the cooling tower pump turbine. Not only did this hinder communications but made walking between the two points very unsafe.
8. Another major complaint made by the electrical maintenance people in volved the inordinate number of sidewalk superintendents they had to contend with. This hindered their efforts to get back on the line to a considerable extent.
EWWjsfm cc: A. Vittone
L* N&lann_/.-lL, Dowell
K. E. Burch C. E. Kemp Those Attending
E. W. Wilson
NCC 01518
-f-
v --''
Vf .'!< .'I
:`-r!
HNRY 005 N CLER 10 19 VCKJ140 010
nrnntF rrm r
REPORT OF NEAR MISS ACCIDENT ^' HENRV PLANT
. /.*?
AT - A'P PR 6 XI MAT ELY 11:06
OCTOBER 19. A CONSTRUCTION ELECT]
^ WOR KING' FOR LEITER ELECTR IC>,.``SHORTED 0UT .THE ^POWER ' IN THE ENTjRfr
IE WAS PUSHING A STEEL TAPE THR0U3H A FEEDER CONDUIT FROM A: MANHOLE] -JHE-NORTHEAST CORNER. OF THE' DHY.ER BUILDING, BUILDING .752, THE.'-Tj^'
SUPPOSED TO GO TO' A NEW SUB ST AT 10 N FOR THE CONCENTRATOR EXPANSION
JCW SUBSTATION WAS LOCATED WEST.OF WHERE THE MAH WAS WORKING AWD/f
OF. BLDG i 752. THE ELECTRICIAN PUSHED THE TAPE' INTO THE WRONG <C0:
AND IT WENT INTO ONE OF TWO 4 ISO VOLT ^UBSt AT 10 N 'DISCO NNECT SWlt'
THE POLY' BUILD ING . THIS SUBSTATION WAS ONLY'A FEW FEET . SO UTH'O F*
THE-MAN-WAS?WORKING-. THE T ApE-WENT'INT0, THE SWITCH BOX/LOOPED^*!
'ffiVERALMTMES AND FINALLY. TOUCHED. A HOT -WIRE AND/ SRORTED. THE-Y
- JJ TRAVEL-BACK ALONG THE-. TAPE* B UT SHORTED TO THE'BO*. BEFORE^BtlftN
OFF THE TAPE AND THROWING THE MAIN BREAKER, ^SUBSEQUENT DJSC.USS.fO:
OUT THE F$CT that.
; ; - -y ... v'-'--'Vv.V : '
SPI
A) K;DRAWiRGS WERE PRpPE*j/BUT MIGHT HAVE-'BEEN _ ?RE\XLfARi'^S
B) T HE ELE CTR ICIA N "b IT)1 NOT USE THE.`ST ANDARD. PRO CEDURERFOf CERTAIN HE HAD THE RIGHT CONDUIT, THAT ,l`S BY BLOWING'fy THE TUBE* , THEYrHAD A COMPRESSOR AVAILABLE WHICH THEY' PREVIOUSLY JO DRY OUT THE TUBES. ^
C) the drawings Showed the unused conduit were supposed to.>
CAPS.ON THEM. ' THESE WERE NOT INSTALLED ON THE ORIGINAL^
STRUCT ION JOB. -
-
; , ;f;
AFTER DETERMINING WHAT HAD HAPPENED AND THAT NO 0 NE WAS INJUREk^p
ELECTRICAL . CREW -PUT THE:POWER BACK ON THE RUBBER CHEMICALS PARISH
-a.ANT 'AFTER 13 MINUTES. AFTER THE TfAPE HAD -BEEN PULLED OUT..AI1DJ
y-'CDNNECT SWITCH CHECKED .OVER /'POWER WAS PUT BACK 0 N THEl;JVC : A^E^
MINUTES' - CORRECTION:'- SHOULD READ 30 MINUTES.
,
THE PVC PRODUCTION CREW BEGAN VENTING SOME. POLYS IN ORDER TO COOti
- MAINTAIN PRESSURE AFTER ABOUT 20. MINUTES*. AFTER POWER WAS BACXGO;
./G.ITATORS ABLE TO BE RESTARTED. TWO QHARGES, WHICH HAD only BJEEW
C HOUR OR TWO HOURS, WERE RECOVERED. NINE OTHER PEARL CHARGES '
WERE KEPT GOING, AS WERE SIX LOW SOPE CHARGES. IT APPEARS THIS MOUNTS
NO OFF-GRADE POLYMER WILL RESULT.
j'.Vl&s
C. R. FLYNN
T' ;fy > L'L'v'. Y >/YV:.v />*?
^ ' ./ . ; ^ ( ^* ' / 'V-\; ** ////
NGC 01519
B. F. Goodrich Chemical Company
Inter-Organization Correspondence
To R, D# Scott--J, L* Nelson--
Date May 17, 1968
LocitirfT), L. Dowell, Yf, L, Cato, G, Pow
From Donald G, Laible Henry Plant
Submission to Subject Doubtful Cases Report for Eye Injury to Charles Dietsch, Production Foreman
-
On April 25, 1968, at XEQQfi hours, Production Foreman PVC, 5525-0057, reported to the plant nurse at the dispensary, that his right eye was bothering Mnfr He stated that around 4*30 a',of he had been cleaning a rupture disc assembly, while wearing his glasses, but that apparently a piece of polymer had struck his right eyelid. The eye was closely examled but no .foreign bodywas found in the eye, but the right eye was slightly inflamed. He was given Metaphen & Butyn Sulfate oitment to place in the eye prior to going to bed* It was checked with the plant doctor's office at that time, that the doctor was not in his office, and would not be back in town before hooxf, Dietsch was advised to call the doctor later in the afternoon if the eye appeared painful?.
He worked his normal shift on Friday, moaning April 26, but did experience discomfort, and reported to the plant doctor, Or, Tochalauski on Friday morning and was treated for a corneal abrasion, and again no foreign body could be found in the eye'. The employee was scheduled off work, on his long weekend from Friday at 8 a,nfi' until 4 p,m, Wednesday, May 1st, Or, tochalauski continued the treatment of butyn Sulfate, with the recommendation that a patch be worn over the eye for 24 hourrf*
Dietsch appeared at the plant on Monday morning, for the purpose of picking up his pay check, and at this time did see the nurse in the dispensary*,' He was wearing dark glasses, and reported that the eye felt much better, but that since he had. scheduled to be out of town on Tuesday, If it did not appear completely better that he would see Or, Tochalauski on Wednesday,
He experienced dome discomfort on Tuesday evening, so Dietsch did return to see Dr, Tochalauski on Wednesday morning. At that time an appointment was made for consultation with Dr, Henry Boldt, an opthamologlst in Peoria for Wednesday afternoon. The doctor in Peoria at that time could find no foreign body in the eye, but at that time instituted new medication, in the form of aureomycin dropd? He was to return to see Dr, Boldt at 11 a,m, on IhursdajV Dietsch worked a part of his shift on Wednesday evening, but left at 8 p,m0 due to the discomfort. The diagnosis reported from Dr, Boldt, on Thursday was a corneal abrasion with seme erosion, that the medication in the form of drops would be bothersome, and that he must not work on Thursday evening, as both eyes should be rested, He again saw the doctor on Friday morning, and was cleared to return to work on Friday May 3*
Past history of the injured Charles Dietsch, discloses the following information: In May of 1966 Dietsch sustained an injury to his right eye, when hit in the eye
with a Bharp stick, while mushroom hunting in the voodB, and apparently a piece of wood stuck in the corned
\
NGC 01520
B.F. Goodrich Chemical Company
Inter-Organization Correspondence
To
Location
i
Date
From D. G. Laible Henry
-
Subject
2*--Sutmission to
_ _ _ _ _ Doubtful Cases report for Bye Injury to Charles Dletach, Production Foreman*
At thia tins in 1966, Dietsch was treated by Dr* Tochalauaki, who was also his family doctozt^ Scar tissue frcan that injury is Btill visible on the corneafr
It la the opinion of Df* Tochalauaki, that the severe conjunctivitis which Dletsch has experienced following only an apparent blow to the eyelid, might not have occurred had it not been for the old injury and resultant scar* Dr* Boldt was also advised of the prior injury, and concurs that the lengthy period of discomfort and treatment may be as a result of the prior injury and residual scar*
These facts are submitted in their entirety for consideration by the doubtful cases committee* The time in question for the purposes of consideration are only the hours between Wednesday May 1, and the shift of Thursday May 2nd, since the Injured, would hare been able to work had he been scheduled on April 27, 28, 29 and 30th.
Donald G. Laible Henry Plant
\ NGC 01521
SUPERVISOR'S REPORT OF ACCIDENT INVESTIGATION
| PLANT
,,
C*\ch1, NAME OF INJURED
/
D,tT<ci,
2. JOB CLASSIFICATION
Production /v>/-tf/4
L
3. EXACT LOCATION OF ACCIDENT
<BH SPECIFIC)
11 DfePI,
ANO
SSXS
PA NO.
cos 7
/yg/i/rv
AM
3/
pVC office
. DATE OF ACCIOENT
HUR
53 A.M.
8. DESCRIBE THE INJURY OAMAOB OR LOSS
Coty TviSfO J1- QK- Te^a
ft_* AT
?f*i> p-M-
,.
<?ye /(d
e. DESCRIBE Tv IHTBE'ACCIILO/CtXnT|
!(UBCE 0SrPbEVClTIIF%ICN. >OBIIVVEB WC<WJ"**PrWLfEcTI E-- 1D> ETAILS!
WEATNEE CONOrTiON
/ A ^ -- C-7?d
LOST TIME
n
n
TEg-
ns.
UNSAFE CONDITION
SPECIFICALLY. WHAT WAS UNSAFE ABOUT THE VEHICLE. MACHINE. TOOL EQUIPMENT OR PREMISES! (IF ANSWERED. SEE BELOWl
AAAj -_
TTxJ. L^-j-rd i^r.dds-f/ rtseL<$ /~t>d,
jAtfsCSs f&~y,
------- ti-trr/ud erw.
^t.. A--tisu*f/
WHY
did Unsafe condition exist! (check rrtri oR use line cn
A_ ^ NOT RECOGNIZED AS UNSAFE CONDITION
e. HIDDEN DEFECTS
C. ___________________________________________________
UNSAFE ACT
SPECIFICALLY. WHAT DID ANYONE DO. OR FAIL TO DO. THAT LED TO THIS ACCIDENT! IIP ANSWERED. SEE ITEM NO. IO BELOW]
-MA-r&tef, Tfa /hvlk.
^
/ i-
ThsK. dtriAlA
t. XTU---------------------------------------------------------------------
REASON FOR UNSAFE ACT
WHAT SPECIFICALLY. IN YOUR OPINION. WAS REASON FOR UNSAFE ACT! ICHECK ITEM OR USE LINE -|
aD DISREGARD OF INSTRUCTIONS
ISE. NOT CONVINCED ABOVE ACT UNSAFE
=. FAILURE TO UNDERSTAND INSTRUCTIONS
F. INATTENTION
c.D DID NOT KNOW THE NEEDED METHOD
G. INDIFFERENCE tLACK OF INTEREST)
d.d UNSKILLED
H. MENTAL OR PHYSICAL CONDITION (EXPLAIN)
CORRECT1VE
*ct,on
WHAT SPECIFIC ACTION HAVE YOU TAKEN TO CONTROL THE ABOVE UNSAFE ACT. -___(_F-E C---O----N---OmoN. AND REASON7f
tL^
ZW| 4
d~v>.L ty T/\J.
~7TT
ft
f2
OPPATE
THIS REPORT
,r- /
IS JOB METHOD AOEOUATEI
REVIEWS D AND APP^tOVI
9-7-a
1 SIGNED
n no
C'J^Cc^rx^
IF "NO" ATTACH EXPLANATORY MEMO
0. (f&dtoci&^K
NGC ()1?22