PAGE 1 REQUEST FOR TECHNICAL SERVICE
PROBLEM TiiLt: Ceiling Material Ivalua .on
WRQ 002359
REPORT: GROUP:
59609 ICC
DATE:
3 August 1980
CHARGE NO.
9-113-20-009
REQUESTOR: H. A. Eschcr.bach
-MARKETING UK .ihiiurmu i uK i iiu NAME: . A. Eschenbach
APPROVED:
.... .
,o-
c3S?
PLAINTIFF'S /R T EXHIBIT"
Asbestos Content
WRG-7/41 '
SIGNIFICANCE:
Ceiling material that contains asbestos must be removed to concrol any employee exposures, and to comply with OSKA regulations.
sfe:
Determine whether or not the ceiling material supplied from the Organic Chemical Plant, Nashua, N.H., contains any asbestos.
SUGGESTED APPROACH: X-ray
DEADLINE (Last day Information will be of value): 2 weeks
DETAILS OF PROBL
Sample supplied to lab "CCD-NTA Plant.'
bottle identified as
^EO'JE jr IJL TECHNIC. _ SERVICE
rMbt tL
NUKLk
69609
GROUP:rm__________________________
ACTUAL COST:___________ $70.00
REPORTING QATE:
k*
SUMMARY:
The ceiling material from the Organic Chemical plant in Nashua, New Hampshire, was examined by x-ray diffraction method and light micro scopic method, and found to have both chrysotile asbestos and mineral fibers.
EXPERIMENTAL
1. XRD Analysis
The crystalline fibers were identified by x-rays as chrysotile.
2. Petrographic Microscopic Examination A portion or the sample was heated in an oven @ 450C, overnight,
to burn all the organic fibers if present. Then the remaining material was wet ground lightly with acetone in an agate mortar, and immersed in oils with R.I. 1.545, 1.520 for microscopic examination at 100X and 430X.
Two kinds of fibers were identified, one was chrysotile and the other mineral wool fibers.
Reference:
XRD Mi sc. - 350.
JCY :ml r
ClfeTRuCTlON PRODUCTS DIVISION
' fV i ;J
, PAGE 1 REQUEST FOR TECHNICAL SERVICE
REPORT:
69609
GROUP:
ICC
DATE:
8 August 1980
CHARGE NO.: 9-113-30-009 REQUESTOR: H. A. Eschenbach MARKETING OR manufacturing approv;
NAME: H. A. Eschenbach
APPROVED:
r ~(s
PROBLEM TITLE: Ceiling Material Evaluation -- Asbestos Content
SIGNIFICANCE:
Ceiling material that contains asbestos must be removed to control any employee exposures, and to comply with OSHA regulations.
SPECIFIC OBJECTIVE:
Determine whether or not the ceiling material supplied from the Organic Chemical Plant, Nashua, N.H., contains any asbestos.
SUGGESTED APPROACH: X-ray
DEADLINE (Last day information will be of value): 2 weeks
DETAILS OF PROBLEM:
Sample supplied to lab in bottle identified as "OCD-NTA Plant."
i
ACCEPTED BY RESEARCH DEPT. :
c
DATE:
ASSIGNED TO: T..I9. OJ/,T'c.
/\
ADDITIONAL COPIES: Original to Library* H.C.Ouecker, H.A.Eschenbach
4 RECJE-*- - -FCr TECHNIC- _ SERVICE
f r.o
NUMUER:
OV'O'J J
GROUP: ACTUAL COST: REPORTING DATE:
$70.00 Aijmi^ f 1 ^ , I'l-'l
SUMMARY:
The ceiling material from the Organic Chemical plant in Nashua, New Hampshire, was examined by x-ray diffraction method and light micro scopic method, and found to have both chrysotile asbestos and mineral fibers.
EXPERIMENTAL
1. XRD Analysis *
The crystalline fibers were identified by x-rays as chrysotile.
2. Petrographic Microscopic Examination
A portion of the sample was heated in an oven @ 450C, overnight, to burn all the organic fibers if present. Then the remaining material was wet ground lightly with acetone in an agate mortar, and immersed in oils with R.I. 1.545, 1.520 for microscopic examination at 100X and 430X
Two kinds of fibers were identified, one was chrysotile and the other mineral wool fibers.