Pre-Startup Safety Review on #2 Steam Turbine Generator Lube Oil System
Gentlemen:
*
You have been selected to form the Pre-Startup Safety Review Team for the new #2 steam turbine generator oil reservoir installation.
The project review will be held Thursday, September 11, 1975, at 1:00 P.M. in the training room and is estimated to require about two hours. J. D. Hopkins will serve as chairman for the review team. A summary of the team's findings will be published by September 24, 1975.
Since this project is felt to be fairly straight-forward and there will be no major changes in system flows, an engineering package is not in cluded in this announcement. However, the package will be included in the review session.
JDH:mfw Attachment
Very truly yours.
Qa,,dj
Ms*C. A. Keil
BRE 0275
PKE -STARTUP SAFETY REVIEW AGENDA OPERATING CONSIDERATIONS 1. Access 2. Lighting 3. Tripping hazards and head knockers 4. Slick surfaces 5. Alarms 6. Indicators (monitoring operation) 7. Pollution considerations 8. Valve operation. 9. OSHA (heat, platform, etc.) 10. Abnormal operation (loss of main oil pump) MAINTENANCE CONSIDERATIONS 1. Access 2. Equipment maintenance 3. Slipblind locations 4. Drain connections
JDH:mfw 8/20/75