Document Yr5XwvJxqXMQyBgnqqgZ6aJxO
OPERATING MANUAL AMS EMERGENCY KILL SYSTEM
ABERDEEN PVC PLANT UPDATED FEBRUARY 13, 1986
VAB.0001135292
TABLE OF CONTENTS
OPERATING MANUAL
AMS EMERGENCY KILL SYSTEM
ABERDEEN PVC PLANT
Page No. I. INTRODUCTION............................................................................1
A. PURPOSE........................................................................... 1
B. OPERATOR RESPONSIBILITIES .....................................1
C. PROCESS INFORMATION.................................................1
II. GENERAL PROCESS DESCRIPTION ......................................... 2
III. SAFETY...................................................... .................................. 5
IV. OPERATING PROCEDURES .......................................................... 7
A. WHEN TO USE.................................................................. 7
B. HOW TO USE ........................................ .......................... 8
C. NORMAL OPERATION............................................................... 11
D. TESTING PROCEDURE ..................................................... 13
V. APPENDIX.......................................................................................... 16
VI. P & I DIAGRAMS..............................................................
18 *
f
h
VAB.0001135293
I. INTRODUCTION A. Purpose The purpose of the AMS Emergency Kill System is to inIncrease the reliability and effectiveness of equipment and procedures used to safely and quickly stop the poly merization reaction in the reactors. Stopping the reaction prevents excessive pressure buildup which can cause emergency releases through the reactor relief valves. This system allows any or all reactors to be shut down in an orderly and safe manner. This manual describes the system and the operator's responsibilities for operating and maintaining the system. B. Operator Responsibilities The operator is responsible for producing quality pro ducts in a safe and efficient manner. He fulfills his responsibilities by knowing the following: 1. Understanding how his equipment functions. 2. Understanding what role each piece of equipment plays in the process. 3. Keeping a close and regular check on equipment. 4. Knowing how to spot malfunctions and correct them. 5. Keeping his area of responsibility safe and tlean. 6. Keeping complete and accurate records. C. Process Information The polymerization reaction of VCM to form PVC gives off heat and accelerates as temperature increases. It is therefore necessary to remove the heat of reaction with cooling water in the reactor jacket and condenser.
I
-1-
r v
*
VAB.0001135294
I. INTRODUCTION - Continued
C. Process Information - continued Reactor agitation is also required to maintain uniform reactor mixing and efficient heat removal.
If reactor cooling and/or agitation is lost, the poly merization reaction must be stopped. Failure to do so will result in a runaway reaction with increasing temp erature and pressure. The reactor pressure would in crease until the rupture disc/safety valve assemblies would vent the reactor contents to the atmosphere.
The AMS Emergency Rill System provides the capability of injecting up to 25 gallons of AMS into each of the large reactors and up to 60 gallons into the expansion reactors. This can be done either remotely from the control room or manually at the reactor top manway plat form. AMS can be injected into a reactor as soon as agitation is lost to take advantage of mixing caused by residual swirling motion. Maintaining cooling water flow after loss of agitation will also help mixing by refluxing in addition to removing heat of reaction.
II. GENERAL PROCESS DESCRIPTION Refer to the attached P & I diagrams for the complete
i
system layout for each reactor area. Emergency kill injection pots are provided at grade level for each reactor. All injection pots are to be maintained at 250 to 275 psig pressure using high pressure nitrogen cylinders. A separate nitrogen
II. GENERAL PROCESS DESCRIPTION - Continued
cylinder and spare are provided for each injection pot. A local AMS level gauge and a pressure gauge are provided on each pot in addition to a board-mounted low pressure alarm and a low level alarm.
The A operator is to check the appropriate injection pot level and pressure before starting each reactor charge sequence
Killing agent can be Injected into the reactor either
remotely by the lead operator or locally by the A
operator. Normally, the emergency kill system is
activated from the board to minimize time and maxl-
ize mixing. One switch
matic double block valves at the reactor top manway
level. Placing the switch in automatic mode opens the
valves and allows a low level switch in the Injection
pot to close the valves. Placing the switch in the
momentary-contact manual mode also opens the valves
but the valves close when the switch is released. Each
Injection pot low level switch also activates a local
light at the manual injection point at the reactor top
manway
The automatic
jectlon valves and the local low level Indicator light
are provided to prevent nitrogen from being Injected
*
into the reactor, blanketing the condenser and reducing
cooling efficiency.
-3-
b
VAB.0001135296
II. GENERAL PROCESS DESCRIPTION - Continued An emergency injection header is provided at the reactor
r
top head level in each reactor module. The header allows any Injection pot to be used to kill any reactor in the module or to inject additional killing agent if needed. The procedure requires two hoses, one to connect the injection pot to the header, and one to connect the header to the reactor. Killing agent can then injected locally by the A operator or remotely by the lead operator. It should be noted that when the emergency Injection header is used, the injection pot low level switch will neither automatically close the remote injection valves nor light the appropriate local indicator light. Caution should be taken to prevent charging nitrogen into the reactor when using the header.
The remote injection automatic valves are operated by nitrogen supplied by a high pressure nitrogen cylinder and spare. A board-mounted low pressure alarm is provided for each area to alert the board operator when the cylinder in use has dropped below 600 pslg.
f A cylinder with less than 600 pslg pressure does not contain enough nitrogen to operate the control valves and is to Immediately changed out with a full cylinder.
HUMP
VMM
VAB.0001135297
III. SAFETY The operation of the emergency kill system does not pre sent any extremely hazardous situations* In fact, its main purpose is to reduce the potential for having hazardous situations in the reactor area* However, some potential hazards are present and precautions should be taken to prevent serious incidents* A. The killing agent AMS has been in use for some time in the plant and the operators are already familiar with the corresponding safety hazards and proper handling procedures. The attached vendor literature describes chemical properties and safe handling procedures* It should be emphasized that AMS is highly reactive in the presence of the peroxide initiators used in the plant. AMS AND INITIATOR SHOULD NEVER BE MIXED UNDER ANY CIR CUMSTANCES . B. The AMS injection pots are to be maintained at 250 to 275 psig by high pressure nitrogen cylinders. Due caution should be exercised in the handling of nitrogen cylinders. Operators should avoid damaging the outlet valves on these cylinders. The A|(S in jection pots will contain AMS at 250 to 275 psig pressure, so proper safety precautions should be taken while working with or near these vessels.
*
An injection pot must be depressurized before the block valve on the AMS fill line is opened*
VAB.0001135298
III. SAFETY - Continued
The nitrogen supply to the pot must be turned off at the pot prior to venting the pot. The pots are only to be vented through the bleed valve on the pressure gauge/pressure switch piping on the top of the pots.
The rupture
tion pot is set to relieve at 400 pslg, the vessel
design pressure. Since the nitrogen bottle
regulator may occasionally leak through, a potential
exists for overpressuring an injection pot and
rupture
Even if the
killing agent didn't spray out when the relief
devices opened, it is probable the relief valve
would not completely reseat and the nitrogen
bottle would slowly depressure through the pot and
relief valve to atmosphere. The outside operator is
to routinely check injection pot pressures to insure
it is neither too low nor too high.
The AMS killing agent is a volatile hydrocarbon, and
thus fire and explosions are theoretically possible.
Precautions are to be taken to prevent spills and t
excessive accumulation of flammable vapors.
E Since the injection pots are connected to the
reactors, a potential exists for backing VCM into
the pots. This poses no serious Immediate problem
since the AMS would kill any reaction that was
occurring. However, it could present an exposure
problem later when the injection pot is opened.
VAB.0001135299
III. SAFETY - Continued The injection pots are to be maintained at 250 to 275 psig pressure except when refilling.
F. Finally, operators are to keep in mind that this system will be used when the plant is in an upset condition, l.e., power failure, loss of cooling water, reactor runaway, etc. It is critical that this system operate properly in such an emergency. System maintenance and operator familiarity with this system are equally important factors for ensuring the dependability of this system.
IV. OPERATING PROCEDURES A. When To Use The emergency kill system is to be used under the following circumstances: 1. If there is a power failure. 2. Extended loss of cooling water to a reactor in polymerization mode. 3. Extended loss of agitation to a reactor in polymerization mode. When agitation id^lost, it is Important to kill the reaction as soon as possible. The reactor contents will con tinue to swirl for about four minutes after agitator shutdown, and AMS injection during this period is much more effective.
*
VAB.0001135300
IV. OPERATING PROCEDURES - Continued
4. A runaway reaction with increasing temperature
and pressure which is not responding to small
AMS injections (short stop) from the initiator
charge pot.
5. Any other circumstance considered by the
operator to represent a significant chance of
over pressuring the reactor or affecting safe
operation of the plant.
6. If for any reason the reactor temperature or
pressure reaches the following:
j
a. 5305 & 5265
155 psig
160F
b. All other resin types 145 psig
142F
B. How To Use
1. The Lead Operator is to depress the manual AMS
emergency kill button and keep it depressed for
two seconds after to open light comes on. This
opens both remote operated valves and AMS is
Injected into the reactor. Both valves close
when the button is released stopping the
addition of AMS into the reactor.
2. The Shift Supervisor or Chief Lead wlllfthen
check the local level gauge on the AMS in
jection port to confirm AMS was added to the
reactor and he will also determine the number
of inches of AMS added from the ruler on the
injection pot.
*
\
VAB.0001135301
IV. OPERATING PROCEDURES - Continued
B. How To Use - continued
- 3. In case of a power failure, the Lead Operator is to kill reactors in the following order and
all must be killed within two minutes.
a. 5265 or 5305 batches
b. Reactors which are near pressure drop
c. Reactor just reaching end of heat up
d. Remaining reactors
A. After AMS injection, the Lead Operator will
W 4
closely monitor the reactor temperature and
pressure and will add additional AMS per step
1 if the initial injection does not kill the
reaction.
5. If the remote operated injection system falls to work, the A Operator is to manually inject
AMS into the reactor by opening the two manual
valves on the manual AMS injection line at the
reactor head level.
6. If all the AMS in the injection pot is added to the reactor and more AMS is required to stop
the reaction, the emergency injection header is
to be used. This header allows AMS which is
contained in any of the other reactor injection
pots to be added to the reactor which is being
killed. To use this header, the A Operator
connects one hose from a full and pressurized
injection pot to the header and a second hose
from the header to the reactor being killed.
-9-
VAB.0001135302
IV. OPERATING PROCEDURES - Continued
Additional AMS injection can then proceed either locally or remotely from the control room. Caution is to be taken when using the header system since the injection pot low level switch shut off feature will not work in this situation and nitrogen may enter the reactor. 7. If excess nitrogen does enter the reactor, the condenser is to be vented to the recovery system. 8. As soon as possible after AMS injection, the A Operator is to refill the AMS injection pot by the following procedure:
a. Close the block valve on the nitrogen supply line at the pot.
b. Depressure the pot through the pressure gauge vent valve.
c. Refill the pot with AMS from the 55 gallon drum using the air-operated drum pump.
d. Close and plug the pressure gauge vent valve.
e. Pressure the injection pot to 250 to 275 pslg with the nitrogen supply system..
f. Radio communication between personnel in
*
the field and the Lead Operator is to be maintained at all times. The A Operator is to Inform the Lead Operator how the system is operating and what Is being done
-10-
K
VAB.0001135303
IV. OPERATING PROCEDURES - Continued
in the field. The Lead Operator is to keep the A
Operator informed of reactor pressure and of any
apparent need for additional AMS injection.
Normal Operation
1. A reactor is not to be charged unless its AMS
injection system is in proper operating
i
condition. It is the responsibility of the A
Operator to check this in the field and notify
the lead operator who will record the informa-
tlon on the batch sheet prior to each reactor
charge. The following items are to be checked
immediately before each charge:
a. The AMS level in the Injection pot is to
be at or above a seven-inch outage. The
actual outage is to be recorded by the
lead operator.
b. The pressure in the injection pot is to be
250 to 275 psig. This is to be checked on
the injection pot pressure gauge.
c. The pressure of the nitrogen cylinders
being used for AMS injection is to te at
least 1200 psig. Cylinders with lower
pressures must be changed out and replaced
with full cylinders. EMPTY BOTTLES ARE NOT
TO BE LEFT IN THE BOTTLE RACKS.
VAB.0001135304
IV. OPERATING PROCEDURES - Continued
C* Normal Operation - continued d. The pressure of the nitrogen cylinder being used to actuate the automatic AMS injection valves must be at least 600 psig. A cylinder with a lower pressure must be changed out and replaced full cylinder. The pressure on the outlet of the regulator for this cylinder is to be 100 pslg. e. The block valve in the AMS kill line (outlet valve at bottom of pot) is to be fully open. f. The block valve in the AMS instrument nitrogen line at the reactor manway level is to be fully open.
*
g. Both block valves on the manual AMS injection line at the reactor manway level are to be fully closed.
If any of the above conditions are not met, they are to be corrected before the reactor is charged 2. To Insure proper operation of the systdm, the following items should be checked by the A
s
Operator at the beginning of each shift: a. The pressure gauges between the double
block valves on both the automatic and the manual injection lines should routinely be bled to 0 psig.
-12-
VAB.0001135305
IV. OPERATING PROCEDURES - Continued
C. Normal Operation - continued
If pressure subsequently builds up on these
gauges, it indicates that one or both of the
double block valves are leaking. Note: These
gauges will have pressure on them after AMS
injection.
b. All spare nitrogen cylinders in the racks are to
be full. The above items are vital to the proper operation of the
emergency kill system. If any of these conditions are
not met, they are to be immediately corrected.
D. Testing Procedures 1. The AMS Emergency Kill System for each reactor
will be tested per the frequency indicated /
below. Each system will be checked to assure
proper valve position, proper operation of the
remote operated valves, and that the AMS Inlet
lines to the reactor are not plugged. The Shift
Supervisor, the Chief Operator, the A Operator
and the Lead Operator will conduct the testing.
The testing procedure for each reactor A as
follows:
To Be Conducted Weekly
a. The A Operator is to perform a complete
visual check of the system both at grade
level and the reactor manway level. All
on--off valves are to be in their proper
i
position and any problems detected with
the system are to be noted and corrected.
"13"
VAB.0001135306
m
IV. OPERATING PROCEDURES - Continued
D. Testing Procedures - continued To Be Conducted Weekly - continued b. The Shift Supervisor is to check for any pluggage in the manual injection system nozzle (also the remote Injection system nozzle for D-300, D-700 and 745) using a rod through the rod-out port. Any blockage found is to be removed. This check is to be made during dump or rinse of the reactor. The shift supervisor is to note in his log book which reactors are checked for pluggage of the injection nozzles. c. The following procedure will be used to check the remote operated system and to assure the injection nozzle is not plugged. The checkout will consist of injection of a small amount of AMS into the reactor by cycling the remote operated AMS valves. The check is to be made after dump is complete and before the rinse to the sewer. The Lead Operator, who is in communication wAh the field operator, will cycle the remote operated valves using the manual addition button and will also check the lights on the panel for open and close indication. The field Operator will check the operation of the remote valves in the field. The A
-14-
VAB.0001135307
IV. OPERATING PROCEDURES - Continued
D. " * * edures - continued
~~ " *
.............
continued
Operator will check the AMS injection pot to
assure AMS addition to the reactor by
measuring the level in the AMS injection pot
before and after the AMS addition. The
reactor is to be rinsed after the AMS is
injected and the A Operator is to refill
the AMS injection pot before the next batch
is charged in that reactor. The Shift
Supervisor is to note in his log book the
reactors which are checked.
2. The normal pre-charge checks are to be
conducted on the AMS kill system before the
reactor is charged.
3. Whenever the ambient temperature drops below
20F, the AMS kill system for each reactor
is to be checked once per shift. The check
is to assure the injection nozzle is open
and that there is no pluggage due to
freezing in the kill system. The ctfeck out
will consist of injection of a small amount of
AMS into the reactor by cycling the remote
operated valves and is to be made after dump
*
is complete and before the rinse to the
sewer
-15-
VAB.0001135308
IV, OPERATING PROCEDURES - Continued
D, Testing Procedures - continued The Lead Operator, who is in communication with the field operators, will cycle the remote operated valves using the manual addition button and will also check the lights on the panel for open and close instruction. The field Operator will check the operation of the remote valves in the field. The A Operator will check the AMS Injection pot to assure AMS addition to the reactor by measuring the level in the AMS injection pot before and after AMS addition. The reactor is to be rinsed after the AMS Is injected and the A Operator is to refill the AMS injection pot before the next batch is charged in that reactor. The A Operator is to record the checking of the AMS kill systems on his Winter Protection Check List.
*
VAB.0001135309
V. APPENDIX
VAB.0001135310
STORAGE AND HANDLING OF
ALPHA-METHLY STYRENE
Alpha-Methyl styrene is usually stored and handled in steel equipment. It is also compatible with stainless steel, aluminum, and galvanized iron. Copper and copper alloys are not recommended for this service.
This product has a fairly low freezing point (about -10F) and low
viscosity. Underground storage tanks and lines should be
considered, as their use will prevent freezing in winter and keep
the product cool in summer. Storage temperature should not exceed
100F. Storage under a nitrogen blanket is preferred; exclusion
of air (oxygen) will reduce the chances of polymerization,
peroxide formation, and fire.
*
Piping can be of the materials listed above. A centrifugal pump is suggested for transfer service. "Teflon" is suitable for gaskets and packing.
An inhibitor, para-tertiary butyl catechol (10-20 ppm), is used in alpha-methyl styrene to inhibit polymerization. If storage time is prolonged, the inhibitor concentration should be check^l occasionally and more inhibitor added, if needed. Alpha--Methyl styrene is a toxic chemical; contact with liquid or vapors should be avoided.
j
VAB.0001135311
r
U.S. DEPARTMENT of labor Occupational Safety and Health Administration
MATERIAL SAFETY DATA SHEET
Aporowtd OM No. 44*R13I7
Required under USOL Safety and Health Regulations for Ship Repairing, Shipbuilding, and Shipbreaking (29 CFR 1915, 1916, 1917)
SECTION I
MANUFACTURER'S NAME
USS Chemicals Division, U. S. Steel Corporation
EMERGENCY TELEPHONE NO.
(614) 532-3420
address (Number. Street, City, State, and ZIP Code)
15230
CHEMICAL NAME AND SYNONYMS
Alpha Methvlstvrene. Phenvl Propylene
TRAOE NAME AND SYNONYMS
AMS (Aloha Methyl
C HE MICA L FAaAiLy
FORMULA C H
9 10
rene
SECTION II HAZARDOUS INGREDIENTS
paintsTHh^ervatives. a solvents
TLV % lUnittl
ALLOYS ANO METALLIC COATINGS . | %
TLV 1
(Units) 1
PIGMENTS
BASE METAL
CATALYST VEHICLE SOLVENTS ADDITIVES
ALLOYS
METALLIC COATINGS FILLER METAL PLUS COATING OR CORE FLUX______________________ sOTHCRS
|
|
OTHERS
1
1
HAZARDOUS MIXTURES OF OTHER LIQUIDS. SOLIDS. OTB4ES
1 TLV I <Units)
BOILING POINT (F.| VAPOR PRESSURE (mm Ho.) VAPOR DENSITY (AIR*1) SOLUBILITY IN WATER APPEARANCE AND OOOR
SECTION III - PHYSICAL DATA
329.2 Low 4.1 Nea Colorleaa liquid
SPECIFIC GRAVITY (H30 1J
k
PERCENT, VOLATILE BY VOLUME (%)
EVAPORATION RATE
f UPap
*1)
Less Than
0.907 Low 1
SECTION IV FIRE AND EXPLOSION HAZARD DATA
FLASH POINT (Method used)
0
Tag Closed Cup - 114 F.
FLAMMABLE LIMITS
extinguishing media
Water, foam, dry chemica1 and carbon dioxide
special fire fighting procedures
Water spray can be used to control unconfined fires, but a straight hose stream
should not be used.__ Fireman should have self-contained breathing apparatus.
UNUSUAL Ft re AND EXPLOSION HAZARDS
None
PAGE (1)
(Continued on reverse side)
Form OSHA-20
Rev. May 71
VAB.0001135312
SECTION V - HEALTH HAZARD DATA
THRESMIOOJlD*I_IMIT VALUE
%
100 ppm or 480 mg. /tr m per Ptdtrtl Higiiff
/'""^EFFECTS
Headache. diaainees. light-headadnass
EMERGENCY ANO FIRST AIO PROCEDURES
Hov to frh lr. K--P oul.t nd wrn.__ If not breathing. opply
respiration
STABILITY
UNSTABLE STABLE
SECTION VI - REACTIVITY DATA
CONDITIONS TO AVOIO
X oxi
Add
hazardous decomposition products
HAZARDOUS POLYMERIZATION
MAY OCCUR WILL NOT OCCUR
CONDITIONS TO AVOIO
oxldia initiators
SECTION VII SPILL OR LEAK PROCEDURES
TEPS TO BE TAKEN IN CASE MAATTEERRIIAALL IS RELEASED OR SPILLED
Large amounts - flush with
drains and sewers
Small amounts - mix with sand and burn
WASTE DISPOSAL METHOD
amounts - atomize into an approved combustion chamber
SECTION VIII - SPECIAL PROTECTION INFORMATION
RESPIRATORY PROTECTION (SfH'dfy tvnc)
Self-contained breathing apparatus
VENTILATION
LOCAL EXHAUST
Preferred
MECHANICAL f(ttHenil)
for
severe
exposure
SPECIAL
OTHER
None
f
materials
EYE PROTECTION
ONTHoEtR aPRsOeTErCioTIuVsE EiQnUdIPuMEsNtTria.l h.aza.rd - norma,,l care
goggles
SECTION IX SPECIAL PRECAUTIONS
PRECAUTIONS TO BE TAKEN IN HANDLING ANO STORING
Keep awav from heat, sparks and open flame.
t
i
PAGE (2)
of0 30*940
Form OSHA*20
IU. May 73
VAB.0001135313
..................... ..
r
wi ............. n..............n.i.iiui|iwwm*nnii'
*
HtWmumnc
.!
i -1. ............ 11 I............I i 1111111111 i 111+14-111 11111 mrq
4k )
VAB.0001135314
...................... ........................... --..................... .......................................................... ........ .
/
..................................................................... ...
, .h-
I M II ............................... .
' I 'fUtWPt
NHJMfcG
S9I9S
XT
tn
it 5.
vSo r0 T< rr
> i" $
<* n>0i)
0 wr JE) r l*1
O C*
r1
o
O'
o *i*
'7
iT
n i m n ii m i im it*
/ I*
................MM..........
1
Tl H p 1 > >I 4 >I
QJ O5*>O -O SSSo
ip
x*
ip
jr** y-l
5 3^r2r
\
r c'
rjj fr O
a>
X
v
X
s
O
*
rO
2m m
S
*j\
*p
/
r
Nr
KX]--
--fr
- -ui
IX > 54
ixj
O
**> V?
*y
1X1
A #s|
r XM- lt>fct- M- *-| B
f-UM-UtC
-I 0^
r*ht IOO*M*Wi1-2
^p
T1 iv
*-- XU
in
M-l
r<)
i =t^ Zl
n
fn
m fn
VAB.0001135315
OUIi!!l!!l!l!
Il!!'!1l1:!,!l!1!1' !:Vr!
rn :! J rj 111|11 M I \ j I: I M Ml; i !t|HI f+lHl I . i 11 H I
--mu..... ........
H Ml
T.T J
ENGINEERING FILES
16*0.0
OPERATING MANUALS
16*1*0
16.1.1 16.1.2 16.1.3 16.1.4
VINYL
General Vinyl Reactors Dryers Pilot Plants
16.2.0
16*2.1 16.2.2 16.2.3 16.2.4
COMPOUND
General Line 1 Line 3 Line 5
Compound
16*3*0
DRY BLEND
16*4.0
16.5.0
16.5.1 16.5.2 16.5.3
PLASTICIZER
GENERAL PLANT
Utilities Wastewater System Auxiliary Facilities
i
I i
i
i i i i i i I
4
3
\ j
a
S
i-I I-
I k| | r" I
....... "IM'I 'll.................. I............ I................I- "I........................ ...11-11IIMilIM|h|nIIINItl
t
+
f j I
t
I
i i
ii
i
l i
I
1
i
i i i i i i
t t ji i
i I
i
i
I t
VAB.0001135316
h ir'iTfTFfiM- III |i|HPMUimpiHH^nM>w|t>H'|W>iitWimWW^yWWWtiriHMM<|*M<win^ManiTni|*n
16.3.0
DRY BLEND
(1) Dry Blend Operation (2) Guap Sereener Addition (3) Profile Dry Blend Boxina Silo
iwwwwwiiiiiuwwiiipmiiiriirnirii: nniinmiiiii imniiTirn " iiiiimim mi r
in n 'iniii'iii'iin t " iiniiiiiiiiiiiiii'iiiiiiiiiinMitimTT^nTTTTTTTTmnTTMTron^--nTmimm "iinTr--iinn----- ....... ............ ................................. Ill I I I I ' IS I I I I him
.......... .
1-t-iHiM-M iM'-mi'IIIHHl
I
|
J
i i tx
i i!
i
3]
i
4
.i
i
ji i |i .i i ;i 'i ii
ii ii I i
I
i
i 'i
n i I
\
H A
,1
.1
4i
I I
i( <i
ft'J-
t i
f
t
3i
i
*
!I.
t fs \ t l
f
li r
?
j i
y
i
i
|
i
'i I
J
1 i j d I
I
I
I -I
i(
!<
IJ I4 *
L
I
VAB.0001135317