Document YDrp8Z0oVbEJ77D65Gr4ajwJn
istribution:
cc: H. S. Bergen J. L. Ledbetter R. E. Howard R. J. Stratmeyer/W A. Kuhn W. B. Papageorge - Anniston
December 26, 1969
MONSANTO COMPANY ORGANIC CHEMICALS DIVISION
To: The Director of Manufacturing Organic Chemicals Division
Estimate No. 3353 Department No. 826.08 Anniston Plant, Anniston, Alabama
PURCHASE AND INSTALL MOTOR CONTROL CENTER EQUIPMENT FOR THE AROCLOR DEPARTMENT
FINANCIAL SUMMARY:
Capital Additions
$18 ,483
Dismantling Expense
5 ,258
Total Appropriation
23 ,741
Savings
None
Installed Cost
32 ,718
Value Not Retired
21 ,918
Value To Be Retired
10 ,800
Accrued Depreciation
5 ,265
Retirement Loss
5 ,535
Net Charge to Obsolescence 10 ,793
APPROVALS:
Urib
--
Plant Manarger
Original Signed by W. A. KUHN Technical Production Manager
Original Signed By R. J. Sikhimulk
Date
l ? 1C7T
Date
Date
DSW 199793
STLCOPCB4057857
Estimate No. 3353
Page 2
BACKGROUND INFORMATION:
The Aroclor motor control center contains starters and relays for all electric motors throughout the Aroclor Departments, along with some other associated departmental electrical apparatus --trans
formers, bus work, lighting panels, associated piping and panels, etc. An electrical fire in this motor control center on 9-27-69 damaged beyond repair one third of the electrical gear in the center. Due to this fire we were shut down completely in our Aroclor Department. It was imperative that this electrical gear be replaced on an emergency basis in order that we might maintain our capability for producing Aroclors and associated products at the Anniston Plant.
PROJECT DESCRIPTION AND OBJECTIVE:
This project provides for the purchase and installation of the necessary electrical equipment to replace the failed electrical equipment due to the fire in the Aroclor motor control center.
ECONOMIC JUSTIFICATION:
When the fire occurred we were in a loss of sales position o,n Solid Aroclors and Muriatic Acid but not on Liquid Aroclors. The downtime value for this equipment amounted to $7,344 per day. From an economic standpoint, it was economically justifiable to take the necessary steps to get production of these products back on stream.
OTHER JUSTIFICATION:
None claimed.
ALTERNATE COURSE:
Jury rig the remaining part of the motor control center with temporary jumpers after the burned portion had been cleared away. Mount
temporary starters and feeders to one third of all the starters in this motor control center. This was not an acceptable alternative due to the temporary nature of such an arrangement and the ever present safety aspect that would be involved in such an undertaking. Good judgment, common sense and safety justification made it necessary to replace the damaged equipment rather than jury rig it.
STATUS OF PROJECT:
,
Delivery of replacement hardware was accomplished in 4 days and in stallation of all the electrical equipment and associated wiring was completed within one week after receipt of the equipment.
Prepared by ___
DSW 199794
Requested by _
/dp
STLCOPCB4057858
Md&s&sro
A'^i'Sc 5
PLANT
KLJ'ser Atfmosmr for EXPif^rm^
AKS/OR RETeSISENT
(r.iis foea to be used fch authorities KE0uif:3 sereral kaeroee akb Loma levtu of apfsctaiv
2UDCSST !?( NO.
BEST. NO.
DATE
ENG. joa NO.
pass s OP.
AUTKORTTV NO.
Anniston
826.08
12/26/69
3353
DESCRSsTKXS, REASON AND JUSTIFICATION FOS WSI^:
Purchase and install motor control room electrical equipment for the Aroclor Dept.
Reason: An electrical fire on 9/27/69 damaged the motor control room equipment and the damage is of such severity that replacement of the damaged equipment is required. This motor control center provides electrical apparatus for all the Aroclor Dept., along with several other associated departments. It is necessary that this work be done in order to maintain our capability for producing Aroclors and Muriatic Acid. Work complete.
USS TOFtftS A-S2~f TO DETAIL. RETIREMENTS
DSW 199795 STLCOPCB4057859