Document YDk7Vw4DbGp35Bb95OgMLno4O

EPA REGION 10 Enforcement and Compliance Assurance Division INSPECTION REPORT Inspection Entry Date/Time Inspection Exit Date/Time Weather Media Statute/Programs Type of Inspection 06/07/2023 09:40 AM (PT) Announced: No 06/07/2023 03:40 PM (PT) Access: Granted 46F, Overcast, Drizzly Water Clean Water Act, NPDES, Industrial Compliance Evaluation Inspection Permittee Name Facility or Site Name Facility/Site Physical Address City, State, Zip Code Borough Facility GPS Coordinates Mailing Address City, State, Zip Code Silver Bay Seafoods, LLC Silver Bay Seafoods - Kodiak Plant 517 Shelikof Street Kodiak, Alaska 99615 Kodiak 57.786393, -152.415894 4039 21st Avenue W, Suite 201 Seattle, Washington 98199 FRS ID Permit Numbers SIC 110010780976 AKG528353 - APDES General Permit for Seafood Processors Operating Onshore Facilities in Kodiak, Alaska AKR06AF77 - Multi-Sector General Permit for Stormwater Discharges Associated with Industrial Activity (MSGP) 2092 (Fresh & frozen seafood processing (pt) Lead Inspector: RAYMOND ANDREWS Date: 2023.07.20 11:38:40 -07'00' Digitally signed by RAYMOND ANDREWS Raymond Andrews EPA REGION 10 andrews.raymond@epa.gov (206) 553-4252 Supervisor Review: PETER CONTRERAS Date: 2023.07.20 12:59:23 -07'00' Digitally signed by PETER CONTRERAS Peter Contreras EPA Region 10 contreras.peter@epa.gov (206) 553-6708 Silver Bay Seafoods - Kodiak Plant AKG528353 AKR06AF77 SECTION I - Opening Conference I arrived at the Silver Bay Seafoods - Kodiak Plant (the "Site" or "Facility"), located at 517 Shelikof Street, Kodiak, Alaska, at 09:40 AM (PT) on 06/07/2023 for an unannounced inspection. I presented my credentials to Kyffon Brinegar, the Plant Manager; Ken Holt, Chief Engineer; and Jinko Domingo, QA Manager; and informed them I was there to conduct an inspection to determine compliance with the Clean Water Act (CWA) and the Alaska Pollutant Discharge Elimination System (APDES) general permit for Seafood Processors Operating Onshore Facilities in Kodiak, Alaska ("Permit"), permit # AKG528353 and the Multi-Sector General Permit for Stormwater Discharges Associated with Industrial Activity (MSGP), permit #AKR06AF77. This report is based on information supplied by Silver Bay Seafoods representatives, direct observations made by me, and records and reports maintained by the permittee. In addition, information gathered prior to or after the inspection from a review of EPA, State, and/or public records may be included in this report. NOTE: There are two items of note. 1. The facility was not processing at the time of the inspection. 2. As stated above, the facility was inspected under two different permits, but the findings of the inspections are combined into this single report. Attendees Organization EPA Region 10 Attendee Name Raymond Andrews Title Lead Inspector Present in Opening Conf. Yes Present in Closing Conf. Yes Silver Bay Seafoods Kyffon Brinegar Plant Manager Yes Yes Silver bay Seafoods Jinko Domingo QA Manager Yes Yes Silver Bay Seafoods Ken Holt Chief Engineer Yes Yes Silver Bay Seafoods Tiffany Lake Director of Compliance Yes Yes Facility/Site Information Responsible Official Tiffany Hanson, Director of Compliance, tiffany.lake@silverbayseafoods.com Type of Operation The facility is a fish processing plant, which process salmon, herring, white fish, etc., into fresh and frozen filets and other products. Size of Facility The site's total footprint is approximately 1.83 acres. Processing activities are conducted in a building with a combined 81,000 square feet of space over two levels. Number of Employees and Hours of When processing, the facility employs approximately 250 people working two 12-hour Operation shifts 24-hours a day, seven hours a day. How many outfalls does the facility have? The facility discharges through a single underwater outfall into St Paul Harbor. NOTE: Facility personnel said the facility discharges through a single outfall but there are two outfalls shown on the SWPPP map and the name of one outfall is cut off. How often do you visually inspect the outfall? The outfall's discharge point is underwater. The facility is not required to inspect the outfall this year. Per Table 9 of permit AKG528353, the facility is required to conduct a dive survey every (or in?) 4 years. Do you maintain any other environmental permits? The facility has two active permits. AKG528353 - seafood processing operations AKR06AF77 - industrial stormwater. Industrial Sector/Sub- For permit AKR06AF77, the facility is in Industrial Sector U (Food and Kindred Products); sector Subsector U2 (Fats and Oils Products). 2 of 8 Silver Bay Seafoods - Kodiak Plant AKG528353 AKR06AF77 How is process wastewater treated? (AKG825353) How is industrial stormwater treated? (AKR06AF77) What waste does the facility generate? What do you do with it? Wastewater from all processing areas is collected in the "Wastewater Main Sump". The contents of the sump are pumped to a 1mm x 20mm rotary screen for screening of seafood solids. The screens are used to dewater solids from the processing wastewater prior to discharge through the outfall. The screened wastewater is gravity fed to the outfall for discharge. The solids are conveyed to the Bio-dry hopper, which are then transport to the Kodiak Fish Meal Plant. All industrial stormwater is collected in a tank under the dock and pumped to the roto screen to be comingled with seafood wastewater before screening and sampling. When no production occurs, the stormwater tank continues to pump to the main sump and out the outfall. Per facility representatives, industrial stormwater samples are collected after it co-mingles with process wastewater. The waste byproduct is fish parts which go to "bio-dry" first and then are sent to a fish meal plant for processing. In-house analysis - temperature of effluent, flow; pH is analyzed by a contract lab down lab down the road, lab - Kodiak Seafood Laboratory Do you use in-house or contract out for laboratory analyses? Or both? At the time of the inspection, the facility analyzed flow and temperature in-house. All other parameters; pH, total residual chlorine (TRC), biochemical oxygen demand (BOD), total suspended solids (TSS), total dissolved solids, settleable solids, oil and grease (O&G), and total ammonia were analyzed by a local contract lab. The contract lab used by the facility is: Kodiak Seafood Laboratory, Inc. 301 Research Court Kodiak, Alaska 99615 Phone: (907) 481-1700 Per Jinko Domino, the facility does not conduct its own water sample analysis for pH or total residual chlorine (TRC). Water samples are sent "down the road" to the contract lab for analysis. According to 40 CFR Part 136, Table II, both TRC and pH have a 15-minute hold time. It does not seem possible TRC, and pH are analyzed within the required 15minutes if the samples are sent down the road for analysis. SECTION II - Observations No Areas of Concern were observed during the site tour. SECTION III - Records Review Records may not be in sequential order. Record: Other - Spill Prevention Control & Countermeasure (SPCC) Plan - AKR06AF77 AOC: No Ref #: RA1-RR-012 Reviewed By: Raymond Andrews Reviewed Date: 06/07/2023 At the time of inspection, I reviewed the facility's SPCC, revision dated February 1, 2023. I did not find and issues. Record: Other - Annual Reports - AKG528353 AOC: No Ref #: RA1-RR-011 Reviewed By: Raymond Andrews Reviewed Date: 06/07/2023 At the time of the inspection, I reviewed the facility's annual reports for 2021 and 2022. 3 of 8 Silver Bay Seafoods - Kodiak Plant AKG528353 AKR06AF77 Record: Other - Collective Ambient Receiving Water Quality Monitoring Study - AKG528353 AOC: No Ref #: RA1-RR-010 Reviewed By: Raymond Andrews Reviewed Date: 06/07/2023 At the time of the inspection, I reviewed the Collective Ambient Receiving Water Quality Monitoring Study, dated April 2022. Record: Other - Quality Assurance Project Plan (QAPP) Review Certification - AKG528353 AOC: Yes Ref #: RA1-RR-009 Reviewed By: Raymond Andrews Reviewed Date: 06/07/2023 At the time of inspection, I reviewed the facility's annual QAPP certification, signed February 2, 2023. I found that although the review certification was signed and dated, the facility did not check the box indicating the certification had been completed. Record: Other - Best Management Practices (BMP) Plan Review Certification - AKG528353 AOC: Yes Ref #: RA1-RR-008 Reviewed By: Raymond Andrews Reviewed Date: 06/07/2023 At the time of inspection, I reviewed the facility's BMP Plan review certification, signed February 2, 2023. I found that although the review certification was signed and dated, the facility did not check the box indicating the certification had been completed. Record: Other - 2022 Notice of Intent (NOI) - AFG528353 AOC: No Ref #: RA1-RR-007 Reviewed By: Raymond Andrews Reviewed Date: 07/07/2023 At the time of the inspection, I reviewed the facility's 2022 NOI to discharge under the APDES permit, AKG528000. Record: Other - EPA's Integrated Compliance Information System (ICIS) Database AOC: Yes Ref #: RA1-RR-006 Reviewed By: Raymond Andrews Reviewed Date: 07/17/2023 Post inspection, I reviewed information in EPA's ICIS database from July 2018 through June 2023. I found the facility did not submit monitoring data on their Discharge Monitoring Reports (DMRs) for the monitoring periods ending July 8, 2021, and April 30, 2022. Record: Other - Best Management Practices (BMP) Plan - AKG528353 AOC: No Ref #: RA1-RR-005 Reviewed By: Raymond Andrews Reviewed Date: 06/07/2023 At the time of inspection, I reviewed the facility's BMP plan. The copy I reviewed didn't have the date of creation and was unsigned. The BMP plan also appeared to be missing: 1. Facility plans, drawings, or maps. 2. Purpose of the BMP Plan. 3. Statement of BMP Objectives. Record: Other - Quality Assurance Project Plan (QAPP) - AKG528353 AOC: Yes Ref #: RA1-RR-004 Reviewed By: Raymond Andrews Reviewed Date: 06/07/2023 At the time of inspection, I reviewed the facility's QAPP. The copy I reviewed didn't have the date of creation and was unsigned. The QAPP also appeared to be missing: 1. Number of samples, analytical detection & quantification limits, precision & accuracy. 2. Map with sampling points. 3. Qualification & training of monitoring personnel. 4. Contract lab information. (2.9.9.5) Table 3 of the QAPP shows a total residual chlorine (TRC) holding time of 15-minutes. Table 6 shows a TRC holding time of 1-minute. A holding time of 15-minutes is the correct holding time. I suggested analyzing TRC and pH, which also has a 15-minute hold time, at the time of collection. 4 of 8 Silver Bay Seafoods - Kodiak Plant AKG528353 AKR06AF77 Record: Other - Stormwater Pollution Prevention Plan (SWPPP) and SWPPP Map - AKR06AF77 AOC: Yes Ref #: RA1-RR-003 Reviewed By: Raymond Andrews Reviewed Date: 06/07/2023 At the time of the inspection, I reviewed the facility's SWPPP, dated January 1, 2023. The copy I reviewed was unsigned. The SWPPP and the SWPPP map were missing components as noted in the Areas of Concern, below. Facility personnel said the facility discharges through a single outfall but there are two outfalls shown on the SWPPP map. Record: Other - Facility Quarterly Visual Inspection - AKR06AF77 AOC: No Ref #: RA1-RR-002 Reviewed By: Raymond Andrews Reviewed Date: 06/07/2023 At the time of inspection, I reviewed a random Quarterly Visual Inspection report, dated September 24, 2022. Record: Other - Facility Routine Monthly Inspection Reports - AKR06AF77 Ref #: RA1-RR-001 Reviewed By: Raymond Andrews AOC: No Reviewed Date: 06/07/2023 At the time of inspection, I reviewed a random Monthly Facility Inspection, dated August 3, 2022. SECTION IV - Sampling Activities No sampling was conducted. SECTION V - Areas of Concern Area of Concern may not be in sequential order. The presentation of Areas of Concern does not constitute a formal compliance determination or violation. AOC Reference #: RA1-OC-FD Opening Conference Permit Requirement Permit AKG528000, Part 2.2.5.8, "All effluents discharged to waters of the U.S. must meet the limits found in Table 2." Permit AKG528000, Part 2.2.5.8, Table 2, "Final Effluent Limits Applicable to All Permittees" indicates the facility must monitor pH. 40 CFR, Part 136, Table II shows TRC and pH must be analyzed within 15-minutes of collection. AOC: The facility was not analyzing total residual chlorine (TRC) or pH within 15-minutes of collection. AOC Reference #: RA1-OC-FD Opening Conference Permit Requirement Permit AKR06AF77, Part 7.1.2, "If discharges authorized by this permit commingle with discharges not authorized under this permit, any required sampling of the authorized discharges must be performed at a point before they mix with other waste streams." AOC: The facility collects stormwater samples after the water has co-mingled with process wastewater. AOC Reference #: RA1-RR-006 Records Review: Other - EPA's Integrated Compliance Information System (ICIS) Database Permit Requirement Permit Part 2.2.4.11.1, "The permittee must submit a DMR for each month by the 15th day of the following month." AOC: The facility did not submit monitoring data on their Discharge Monitoring Reports (DMRs) for the monitoring periods ending July 8, 2021, and April 30, 2022. 5 of 8 Silver Bay Seafoods - Kodiak Plant AKG528353 AKR06AF77 AOC Reference #: RA1-RR-008 Records Review: Other - Best Management Practices (BMP) Plan Review Certification - AKG528353 Permit Requirement Permit Part 2.10.2, "The permittee shall review the BMP Plan whenever process changes occur. At a minimum, the permittee shall document annual review of their BMP Plan." AOC: The review certification was signed and dated; however, the facility did not check the box indicating the certification had been completed. AOC Reference #: RA1-RR-009 Records Review: Other - Quality Assurance Project Plan (QAPP) Review Certification - AKG528353 Permit Requirement Permit Part 2.9.3, "A permittee shall document annual review of their QAPP." AOC: The review certification was signed and dated; however, the facility did not check the box indicating the certification had been completed. AOC Reference #: RA1-RR-005 Records Review: Other - Best Management Practices (BMP) Plan AKG528353 Permit Requirement Permit Part 2.10.4.2, "The BMP Plan must include the following information and management practices at a minimum... Facility plans, drawings, or maps." Permit Part 2.10.4.4, "The BMP Plan must include the following information and management practices at a minimum...Statement of BMP Purpose." Permit Part 2.10.4.5, "The BMP Plan must include the following information and management practices at a minimum...Statement of BMP Objectives." AOC: At the time of inspection, I reviewed the facility's BMP plan. The BMP plan also appeared to be missing: 1. Facility plans, drawings, or maps. 2. Purpose of the BMP Plan. 3. Statement of BMP Objectives. 6 of 8 Silver Bay Seafoods - Kodiak Plant AKG528353 AKR06AF77 AOC Reference #: RA1-RR-004 Records Review: Other - Quality Assurance Project Plan (QAPP) AKG528353 Permit Requirement Permit Part 2.9.2, "The permittee must develop and implement a facility-specific QAPP for all monitoring required by this permit. The QAPP must be developed and implemented within 60 days of receiving authorization under this general permit..." Permit Part 2.9.9, "At a minimum, the QAPP shall include..." Permit Part 2.2.9.1, "...Details on number of samples...analytical detection and quantitation limits...precision and accuracy requirements..." Permit Part 2.9.9.3, "...Maps indicating the location of each sampling point." Permit Part 2.9.9.4, "...Qualification and training of monitoring personnel." Permit Part 2.9.9.5, "At a minimum, the QAPP shall include...Name, address, and telephone number of all laboratories used by or proposed to be used by the permittee." AOC: At the time of inspection, I reviewed the facility's QAPP. The copy I reviewed did not have the date of creation and was not signed. The QAPP appeared to be missing: 1. Number of samples, analytical detection & quantification limits, precision & accuracy. 2. Map with sampling points. 3. Qualification & training of monitoring personnel. 4. Contract lab information. AOC Reference #: RA1-RR-003 Records Review: Other - Stormwater Pollution Prevention Plan (SWPPP) - AKR06AF77 Permit Requirement Permit Part 5.2.3.3, "Provide a map showing...the size of the property in acres...locations of all existing structural control measures...locations of all storm water conveyances including ditches, pipes, and swales...locations of all storm water monitoring points...locations of storm water inlets and outfalls, with a unique identification code for each outfall..." AOC: At the time of the inspection, I reviewed the facility's SWPPP, dated January 1, 2023, and the SWPPP map. The facility's SWPPP uses a site diagram in place of an actual map. The map diagram appeared to be missing: 1. Size of site in acres 2. Locations of stormwater structural controls. 3. Stormwater conveyances. 4. Locations of stormwater monitoring points. 5. Complete outfall names for both outfalls. The number for one outfall was cut off. Additionally, facility personnel said the facility had a single outfall, but two outfalls are shown on the map. The SWPPP appeared to be missing: 1. documentation of the evaluation for the presence of non-stormwater discharges. 2. Information required in the "Monitoring and Inspection" section. The missing sections were: a. Locations of sample collection. b. Numeric control values. c. Procedures for performing the three types of inspections i. Routine ii. Quarterly iii. Comprehensive. SECTION VI - Closing Conference I held a closing conference with facility personnel at 03:40 PM (PT) on 06/07/2023. During the closing conference, I discussed my observations and Areas of Concern I identified during the inspection. Observations and Areas of Concern have not yet been evaluated for a formal compliance determination 7 of 8 Silver Bay Seafoods - Kodiak Plant AKG528353 AKR06AF77 SECTION VII - Follow Up Post inspection, the facility provided me with some missing information and documents correcting some of the noted Areas of Concern. SECTION VII - List of Appendices 1. Appendix 1 - Photo Log 8 of 8 APPENDIX 1: Photo Log All photos were taken by Lead EPA Inspector, Ray Andrews, during the inspection. Photos were not manipulated beyond minor cropping for sizing and labels or callouts to draw attention to the subject of the photo. All photos taken during the inspection are included in the Photo Log; however, no photos are included in the inspection report because none directly support an Area of Concern. P1010773 - Monthly Facility Inspection Form, August 3, 2022, page 1 P1010774 - Monthly Facility Inspection Form, August 3, 2022, page 2 P1010775 - Monthly Facility Inspection Form, August 3, 2022, page 3 P1010776 - Monthly Facility Inspection Form, August 3, 2022, page 4 P1010777 - Monthly Facility Inspection Form, August 3, 2022, page 5 P1010778 - Monthly Facility Inspection Form, August 3, 2022, page 6 P1010779 - Quarterly Visual Assessment, September 9, 2022, page 1 P1010780 - Quarterly Visual Assessment, September 9, 2022, page 2 P1010781 - Quarterly Visual Assessment, September 9, 2022, page 3 P1010782 - Quarterly Visual Assessment, September 9, 2022, page 4 P1010783 - Best Management Practices (BMP) Plan, cover page P1010784 - Best Management Practices (BMP) Plan, page 2 P1010785 - Quality Assurance Project Plan (QAPP), cover page P1010786 - Quality Assurance Project Plan (QAPP), annual review page P1010787 - Stormwater Pollution Prevention Plan (SWPPP), revised January 1, 2023, cover page P1010788 - Stormwater Pollution Prevention Plan (SWPPP), revised January 1, 2023, Table of Contents page