Document Xzw053BYgBMJe9oOOzmxOjdMw
Interoffice Communication
To R. E. Lehmkuhl From c. L. Miller
Date November 25, 1980
Subject
WEEKLY PRODUCTION REPORT - ABERDEEN - WEEK ENDING 11/23/80 WEEK NO. 47
Production MM Lbs. - 5 Days - 11/19/80 thru 11/23/80 Last 5 Days Month to Date Year to Date Previous Month
Resin (A 6 BC) Compound (A BC) Dry Blend Plasticizer
4.90 .72 .43 .17
21.08 2.56
2.33 .83
235.37 40.59 21.87 9-77
26.40 4.80 4.21 1.22
Safety
There was 1 minor first aid recorded during this period.
Resin Unit (A BC Grade)
Production
Forecast MM Lbs. !November
Last 7 Days, M Lbs ./C.D. Last 7 Days, % of Budget . Current Rate, % of Budget
980
109 110
Budget Forecast 11/20/80 Forecast 11/24/80
27.0 27.5 27-5
Vinyl production for the week averaged 980 M pounds per day. Major items affecting production were an agitator seal replacement on 741 reactor and maintenance of the old reactor module dump Sweco.
Compound Unit (Customer Grade)
Product ion
Forecast MM Lbs. November
Last 7 Days, M Lbs./C.D. Last 7 Days, % of Budget
107 65
Budget Forecast 11/20/80 Forecast 11/24/80
4.9 3*6 3-6
Line I operated 2 days averaging 69 M pounds per day. Line III operated 5 days averaging 99 M pounds per day. Line V operated 3 days averaging 37 M pounds per day. Line III rates were affected by 2 seal changes and quality control on
18031 CB 50.
Plasticizer operated 3 days averaging 56 M pounds per day.
DTH 000051577
R. E. Lehmkuhl Weekly Production Report - Aberdeen November 25, 1980 Page 2
Dry Blend Unit
Product ion
Forecast MM Lbs. November
Last 7 Days, M Lbs./C.D. Last 7 Days, % of Budget
55 62
Budget Forecast 11/20/80 Forecast 11/24/80
2.65 2.60 2.60
Dry Blend operated 3 days 16 hours per day averaging 129 M pounds per day with no major operating problems.
0 </
C. L. Miller
jf
REL'S OFFICE TO COPY: HRF, ELK, SKS, MS, RGR ABERDEEN COPIES: CRM, PEM, JRM, RGG, JEM, MPB, JEB, RDJ, RAF, TBD