Document Xz7j7KYRLao9D7yq0mQw8MyNG

DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS Sub-Contract No. 71^8-llj8?, dated: March 30, 1967 Change Order Number u Subject: Pipe Insulation Date of Change Order: September 29, 1967 location: Armco Steel Corporation - Middletown Works - Middletown. Ohio Sub-Contractor: Owens Corning Fibergias Corporation 2987 Exon Drive Cincinnati. Ohio ii52i;l DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes: (A) Authorized premium time for work performed on July 8, 1967, July 15, 1967 and July 22, 196'?. Increase - $ 1,$06.28 :0ST ACCOUNT NO. 7lli8-70i{-j63. $1 CHANGE IN COMPENSATION: Total estimated amount increased from: $ 28?28 to $ 2Sn,6u6.$6 CHANGE IN COMPLETION DATE: None Except as herein expressly modified, said Su :-Contract as heretofore amended and all the terms and conditions roof shall remain unaltered and in full force and effect and shall 3; 'x't - - tc all the work performed hereunder. / nr*iPTED: GWENS CORNING FI55RGLAS CCR (Sub- Contractor)' 3y----/-s---/-----P--a--u--l---C--.---G--a--h-n^ . s Title Contr. & Sal^sT*'En? \> -V gimeees, inc. Armco Steel Corporation or) /ern L. Frankson ~ Pro u- E0P:prl KEN 010762 INTER-OFFICE MEMORANDUM 4b TO AT Vern L. Franks on Wo M. Schuck DATE PROM December 21, 196? E. 0. Potts_^ COPIES TO See Distribution AT Middletown, Ohio JOB NO. 711*8 SUBJECT Sub-Contract No. 711*8-11*85 - Change Order No. 5 Owens-Coming Fiberglas Corporation Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. EOP sprl cc - with attachment ARMCO KAISER F. Wo Barnes (2) P. R. Smith J. S. Lotz Reading File D. A. Daly G. L. Roberts C. W. Graff H. C. Boucher (2) E. J,, Denner (2) S. Ustel B. Scott A. L. Gordon Co Billings F. No Norton M. Do Wilson So M. Iyon L o ti o Gill ett R. J o Wolf W. Dui'i Ro Do Sahiberg Central File Reading File KEN 010763 INTER-OFFICE MEMORANDUM r TO Vern L. Frankaon AT H. W. Borneaan OATS PROM copies to See Distribution AT subject JOB NO. Sub-Contract No. 7100-11*85 - Change Order No. 13 Owens-Corning Fiberglas Corporation July 10, 1968 Donald K. Carlson Middletown 7100 Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. DKCsprl cc - with attachment -- AHMC0 KAISER F. W. Barnes (2) F. R. Smith J. S. Lots Reading File D. A. Daly G. L. Roberts C. W. Graff H. C. Boucher (2) E. J. Denner (2) C. Mandell B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Iyon L. J. Gillett R. J. Wolf - Wr-Fi Sort R. D. Sahiberg Central File Reading File .O I KEN 010734 1 DEVIATIONS FRCM OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS Sub-Contract No. 71QQ-1U85, dated: March 30, 196? Change Order No. 13 Subject: Pipe Insulation____________ Date of Change Order: May 27, 1968 Locations Armco Steel Corporation - Middletown Works - Middletown, Ohio Sub-Contractor: Owens-Coming Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio I4.52UI DESCRIPTION OF CHANC-E: Pursuant to the provisions of Article 3 of the General Terms and Conditions, the Sub-Contract Total Compensation is increased in accordance with the following described changes in The Work or corrections to the compensation previously set forth: (1) It is mutually understood and agreed that Sub-Contractor failed to allow for the cost of insulation materials for the fittings of the 163 lb. steam line as required by Special Provision No. 2 of Exhibit "E" (Item 1 of Exhibit T'B" refers to insulation materials being furnished for straight-runs of piping only) and that a compensation lump sum increase is hereby granted. Sub-Contractor's Invoice No. 25961; dated February 8, 1968, in the amount of $9,663.95 is not in accordance with the Sub-Contract, and is cancelled in its entirety. Price Increase .....$ 1;,832.00 (2) Additional costs incurred during delays beyond that which could reasonably be anticipated in obtaining Contractor-furnished insulation material for the 165 lb. steam line. Price Increase .....$ 2,070.00 (3) Additional costs incurred during erecting of scaffolds, hoisting of materials and performance of other overhead work due to interference from operation by others of Electric Overhead Travelling Bridge Cranes to an extent beyond that which could reasonably be anticipated by the Sub-Contractor. Price Increase .....$ 10,062.50 (It) Costs incurred that were not included in the unit prices because respective changes in the estimated quantity of high, inaccessible work and the estimated quantity of.low, accessible work changed the ratio of the two types of work that was incorporated into the Sub-Contract unit prices. Price Increase .................. $ 6,900.00 KEN 010735 Owens-Corning Fiberglas Corp -2- Sub-Contract No. 7100-11:85 (C.O. #13) DESCRIPTION OF CHANGE: Continued (5) ' Additional costs incurred because piping was released as ready for insulation work more intermittently (including numerous move-ins and move-outs in the same area) than the Sub-Contractor could reasonably anticipate. Price Increase .................. $ 2,587*50 (6) Over-time premium costs (plus 11.% insurance and taxes) for . installing insulation on 165 lb. steam line runouts and headers at night or on Saturdays because areas were inaccessible during regular working hours while bridge cranes were operating (straight-time costs, overhead and profit included in Sub- Contract unit prices). Work performed January 29 through February 1, 1968; February 5th, 6th, 8th, 10th, 12th, 19th, 2Uth, and 27th through 29th. (Reference: Sub-Contractor's letter of April 17, 1968) Price Increase .................. $ 3,675.80 TOTAL LUMP SUM PRICE INCREASE THIS CHANGE ORDER. . . . $ 30.127.80 It is mutually understood and agreed that the lump sum price increases stated above for Item No. (2) through (5) represent a full settlement of all of Sub-Contractor's claims summarized in Sub-Contractor s letter of February 16, 1968. CHANGE IN COMPENSATION: Total estimated amount increased from: $ 31<U,U07.73 to $ 37U.535.53 CHANGE IN COMPLETION DATE:. None Except as herein expressly modified, said Sub-Contract as heretofore amended and all the terms and conditions thereof shall remain unaltered and in full force and effect and shall apply to^ll the work performed hereunder. ACCEPTED: AUTH&K&ZED: <&> JgSSER ENGINEERS, INC. > CWENS-CORNING FIBERGLAS CORPORATION _^&??ent for Armco Steel Corporation (Sub-Contractor) <\otContractor) Br J/fyfA By // Paul C. Gahn u7 Title Contracting S Sales Engineer TitleVice President DKCtprl KEN 010736 INTER-OFFICE MEMORANDUM TO Vera L. Frankson AT H. W. Borneman COPIES TO See Distribution DATE FROM AT JOB NO. SUBJECT Sub-Contract No. 7100-llj.85 - Change Order No. 12 Owens-Corning Fiberglas Corporation June 13, 1968 E. 0. Potts ' Middletown 7100 Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. E0P:prl cc - with attachment AflMCO KAISER F. W. Barnes (2) P. R. Smith J. S. Lotz Reading File D. A. Daly G. L. Roberts C. W. Graff H. C. Boucher (2) E. J, Denner (2) S. Ustel B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Lyon L. J. Gillett R. J. Wolf Wi Pr Bort R. D. Sahiberg Central File Reading File KEN 010737 DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS Sub-Contract No. 7100-11*85, dateds March 30. 1967 "Change Order No. 12 Subjects Pipe Insulation______ Date of Change Order: May 6, 1968 Locations Armco Steel Corporation - Middletown "Works - Middletown. Ohio Sub-Contractors Owens-Corning Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio l*52liL DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes: (1) Remove insulation, salvage, and replace with same if possible ll:" - 165# over head steam line in the Hot Strip Mill. E.W.O. #7 ACCOUNT NO. 711*8-70l*-89l*.5l INCREASE - $ 1,025.89 (2) Insulate gas furnace exhaust duct as directed by Contractor. ACCOUNT NO. 711:8-501-610.51 INCREASE - $ 162.70 (3) Instil ate V plant air line and instrument tube bundle in trench and up to pusher pulpit. ACCOUNT NO. 711*8-701-1*61*.5l INCREASE - $ 1,353-58 (1*) Insulate air drop lines to reduce noise. (Clarifier Pump House) ACCOUNT NO. 7106-701-1*61*. 51 INCREASE - $ 1,693.96 (5) Insulation rework in oil cellar (Hot Strip Mill.) ACCOUNT NO. 7H*8-70l*-89l*.5l INCREASE - $ 805.88 (6) Insulate blowdown piping for personnel protection at all bag houses. ACCOUNT NO. 711:8-701*-765.51 INCREASE - $ 1,210.27 (7) Expose two (2) flanges on the water supply to two (2) condensate pumps so temporary start up screens can be removed.. Repair insulation damaged on steam inlet piping to steam turbines on condensate pumps. ACCOUNT NO. 711*8-70l*-89l*.5l INCREASE - $ 233.61* KEN 010738 Owens-Corning Fiberglas Corp. -2- Sub-Contract No. 7100-1U85 (C.O. #12) DESCRIPTION OF CHANGES Continued (8) Repairing and replacing tom-off pipe covering flanged valve and pipe covering at grating repair on air heater #1 boiler. Repairing and replacing pipe covering at #1 I.D. fan turbine and grating repair. 5tb Floor. Repairing and replacing pipe covering on 165# steam at desuper heater. 3rd Floor. Repair and recover damaged pipe covering at four (lx) water punps.. ACCOUNT NO. 7lU8-51xO-89Uo5l INCREASE - $ 761.10 (9) Repair of steam line and fittings to condensate turbine. 3rd Floor Replace insulation of entire fuel oil heater at Boiler #3. Repair on 20" - 10# steam line. 5th Floor Replace and repair pipe covering at F.D. fan 5th Floor - #2 boiler. Repair on F.D. Fan #1 boiler. Replacing and furnishing insulation on fuel oil heater. Boiler #3 Repair of lx" steam and 8" exhaust lines from F.D. fan. Boiler #2 Replace and repair pipe covering on B. & W. pump. Repair and replace V steam and 8" exhaust lines from F.D. fan. Boiler #2 ACCOUNT NO. 71ix8-5hO-89lx.5l INCREASE - $ 1,888.82 (10) Remove pipe covering at condensate steam turbine. 3rd Floor Replace pipe covering near feedwater punps. Replace and repair pipe covering on llx" - 165# Steam supply at boiler #1 Replace and repair pipe covering on 10" - 1x25# steam supply. Boiler #1 Replace and repair pipe covering at condensate tanks. 3rd Floor ACCOUNT NO. 711x8-5UO-89ix.5l INCREASE - $ 6,502.20 TOTAL INCREASE...................... $l5.638.0ix CHANGE IN COMPENSATION? Total estimated amount increased from? $ 328.769.69 to $ 3lxlx,1x07-73 CHAN IN COMPLETION DATE? None KEN 010739 Owens-Corning Fiberglas Corp -3- Sub-Contract No. 7100-lu8$ (C.O. #12) Except as herein expressly modified, said Sub-Contract as heretofore amended and all the terms and conditions thereof shall remain unaltered and in full force and effect and shall apply to all the work performed hereunder. ACCEPTED: OWENS-CORNING FIBERGLAS CORPORATION (Sub-Contractor) : By /s/ Paul C. Gahn ------------------- AUTHORIZED: KAISER ENGINEERS, INC. Agent for Apico Steel Corporation (Contractor) ^sV D. A. Daly________________ Title Contr. & Sales Engr. Dept. ' /Title Manager of Projects EOPsprl # KEN 010740 INTER-OFFICE MEMORANDUM TO Vem L. Frankson AT H. W. Borneman COPIES TO See Distribution SUBJECT Sub-Contract No. 7100-11*85 Owens-Corning Fiberglas Corporation NO. May 10, 1968 E. 0. Potts Middletown 7100 Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. EOPiprl cc - with attachment ARMC0 . KAISER T. R. Foley (2) P. R. Smith J. S. Lotz Reading File D. A. Daly G. L. Roberts C. W. Graff H. C. Boucher (2) E. J. Denner (2) S. Ustel B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Lyon L. J. Gillett R. J. Wolf W.. F i Port R. D. Sahlberg Central File Reading Pile KEN 010741 DEVIATIONS FROM OR ADDITIONS TO SUB-CG'iTRAGT A. ID SPECIFICATI G?5 Sub-Contract No. 71CS-lu55v dated2 March 28- 196? Change Order No. 11 Subject: Ploe j-ncnlatuon Date of Change Order Acril 23. 19-3 Locations Armco Steel Corpcrauion - Middlstown Korks - Middletown, Chic Sub-Contractors Owens-Coming Fiberglas Corporation 29S7 Exon Druvs Curcuma xL, uruo DESCRIPTION 0? CHANGES .Pursuant to the provisions of Article 8 of the General Terms and Cond: .tions, Sub-Contractor shall perform The Work In accordance with the fc` .lowing changes: (1) 3A" dia. x 1" thickness of ins-elation - steam condensate - 700 lin. ft. S1.13/lin. ft. ACCOUNT NO. 7lU8-70u-l*65.51 INCREASE - $ 791.CO (2) 6" dia. x 1" thickness of Insulation - steam condensate - 100 lin. ft. G $2.30/lin. ft. ACCOUNT NO. 7lk5-70k-k6$.5l INCREASE - $ 230.00 (3) 8" dia. x 1" thickness of insulation - steam condensate - 150 lin. ft. S $2.97/lin. ft. ACCOUNT NO. 71U8-70U-U65.51 ~ INCREASE - $ bn5.50 (1;) 10" dia. x 1" thickness of insulation - steam condensate - 120 lin. ft. $3.58/lin. ft. ACCOUNT NO. 7i!;8-70li-ii65oi INCREASE - $____ 1-29.60 TOTAL INCREASE. .$ 1.896.10 CHANCE IN COMPENSATIONS Total estimated amount increased froms $ 326.373.59 to $ 328.769.69 CHANGE IN COMPLETION DATEs Non; Except as herein expressly modified, said Sub-Contract as heretofore amended and all the terms and conditions thereof shall remain unaltered and in full force and effect and shall apply to all the work performed hereunder. A AUTHORIZED: SO KAISER ENGINEERS, INC, CHENS-CORNING FIBERGLAS 0 GRP ORATION. (Sub-Contractor) / s/ Agent fcr Armco Steel /orncrauicr. (Contractor) By /s/ Paul C. Gahn By /s/ Vern Title Cor.tr. & Sales Ensr SO? sprl KEN 010742 INTER-OFFICE MEMORANDUM TO AT COPIES TO subject Vern L. Frankson W. M. Schuck / / tb DATE x PROM See Distribution H \ js\ \Z. ~ i + v v. % VC'V ^ ------- ^ AT JOB NO. Sub-Contract No. 7l!i8-ll|85 - Change Order No. 7 Owens-Corning Fiberglas Corporation January 18, 1968 E. 0. Potts, ,| Middletown, Ohio 71U8 Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. EOPsprl cc - with attachment ARMCO KAISER F. W. Barnes (2) P. R. Smith J. S. Lotz Reading File D. A. Daly G. L. Roberts C. W. Graff H. C. Boucher (2) E. J. Denner (2) S. Ustel B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Lyon L. J. Gillett R. J. Wolf -- .TJ R. D. Sahlberg Central File Reading File KEN 010743 DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS Sub-Contract No. 71U8-1U85. dated: March 30. 1967. Change Order No. _7____ Subject: Pipe Insulation Date of Change Order: January 12. 1968 Location: Armco Steel Corporation - Middletown Works - Middletown, Ohio Sub-Contractors Owens-Corning Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio U52ltl DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes: (A) Authorized premium time for work performed in accordance with Sub-Contractor's invoices attached: Invoice No. Date Amount Account No. 969 ' 970 971 972 937 938 939 968 12-1-6? 12-1-67 12-1-67 12-1-67 11-2U-67 ll-2li-67 11-2U-67 12-1-67 $lU2.lU $338.75 $35U.67 $228.2U $U85.07 $312.08 $2UU.30 $570.93 7lU8-5kO-l*60.5l 71U8-5U0-U60.51 71U8-5U0-U60.51 7lU8-5iiO-h6o.SH 71U8-70U-U65.51 7lU8-70U-U6.$L 71U8-70U-U65.51 71U8-70U-U65.51 TOTAL INCREASE - $ 2.876.18 CHANGE IN COMPENSATION: Total estimated amount increased from: $ 287.lliO.lt7 to $ 290.016.6$ CHANGE IN COMPLETION DATE: None Except as herein expressly modified, said Sub-Contract as heretofore amended and all the Terms and Conditions thereof shall remain uanltered and in full force and effect and shall apply tqjall the work performed hereunder. ~o5\ ACCEPTED: AUTHORIZED: f^KAISER ENGINEERS, INC. OfTEHS-CORNING FIBERGLAS CORPORATION')\V AAcrgnen+n.t for UArrwmec'/io Steel Corporation (Sub-Contractor) fv ,;j (Contractor} By /s/ Paul C. Gahn____________ By /s/ Vera L. Franks on Title 'Contr. & Sales Eng. Dept. Title Manager - Procurement E0P:prl KEN 010744 INTER-OFFICE MEMORANDUM TO Vein L. Frankson AT W. M. Schuck DATE FROM COPIES TO See Distribution AT JOB NO. subject Sub-Contract No. 711i8-l2i85 - Change Order No. 6 Owens Corning Fiberglas Corporation Januaiy 1J>, 1968 Mddletowni^OfcfcoT - ..... 71U8 /X ... <c>,T' ,cis \ cx Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. EOP sprl cc - with attachments ARMCO KAISER F. W. Barnes (2) P. R. Smith J. S. Lotz Reading File D. A. Daly G. L. Roberts E. J. Denner (2) C. W. Graff H. C. Boucher (2) S. Ustel B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Lyon L. J. Gillett R. J. Wolf -W.- F-.~Bort----R. D. Sahiberg Central File Reading File KEN 010745 DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS Sub-Contract No. 71U8-1U85. dated; March 30, 1967 Change Order No.__ 6 Subject: Pipe Insulation_______ Date of Change-Order December 27. 1967 Location: Armco Steel Corporation - Middletown Works - Middletown, Ohio Sub-Contractor: Owens Corning Fiberglas Corporation 2907 Exon Drive Cincinnati, Ohio U52U1 DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes: 1. Remove and replace insulation of steam line at Column 57-D. ACCOUNT NO. 71U8-70U-89U.51 Sub-Contractor's Invoice #l6l$8 dated November lU, 196? INCREASE - $ '8U.95 2. Remove and replace insulation at Columns U3, U3.20 and U3-30. ACCOUNT NO. 71U8-70U-89U.51 Sub-Contractor's Invoice #16156 dated November lU, 1967. INCREASE - $ 267.72 3. Remove and replace insulation on temporary U" steam line at Column 1-C. ACCOUNT NO. 71U8-70U-89U.51 Sub-Contractor's Invoice #16159 dated November lk, 1967. INCREASE - $ 93.U5 U. Authorized premium time for work performed on November U, 1967 and November 7, 1967. ACCOUNT NO. 7llj.8-5U0-U60.5l Sub-Contractor's Invoice #16157 dated November lU, 1967. INCREASE - $ 1,088.71 5. Authorized premium time for work performed on October 23, 1967 and October 28, 1967. ACCOUNT NO. 71U8-5UO-U60.51 Sub-Contractor1s Invoice #16160 dated November lU, 1967. INCREASE - $ 1,059.08 TOTAL INCREASE ------------ $ 2,593.91 CHANGE IN COMPENSATION: Total estimated amount increased from: $ 28U.5U6.56 to $ 287.lUO.U7 CHANGE IN COMPLETION DATE: None KEN 010746 Owens Corning Fiberglas Corp -2- Sub-Contract No. 7lk8-lU85 (C.O. #6) Except as herein expressly modified, said Sub-Contract as heretofore amended and all the terms and conditions thereof shall remain unaltered and in full force and effect and shall apply to all the work performed hereunder. ACCEPTED: r's> c'-'O ^ AUTHORIZED: ' OWENS-CORNING FI3ERGIAS CORPORATION TSub -Cont ractor) [.J'f- 3y /s/. Paul C. Gahn _________ KAISER ENGINEERS, INC. Agent for Armco Steel Corporation (Contractor) By /s/ Vprn T.. FranV.qnn Title Contr. & Sal ge Eng. PgTvh. Title Manager - Procurement EOP:prl KEN 010747 INTER-OFFICE MEMORANDUM TO Vern L. Frankson AT W. M. Schuck date FROM January 15, 1968 E. 0. Potts /-T-s COPIES TO See Distribution at Middletown, Ohio job no. 71)48 SUBJECT Sub-Contract No. 71U8-1U85 - Change Order No. 6 Owens Corning Fiberglas Corporation Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. EOP sprl cc - with attachments ARMCO KAISER F. W. Barnes (2) P. R. Smith J. S. Lotz Reading File D. A. Daly G. L. Roberts E. J. Denner (2) C. W. Graff H. C. Boucher (2) S. Ustel B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Lyon L. J. Gillett - R. J. Wolf__ _ W. F. Bort R. D. Sahib erg Central File Reading File ken 010748 DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS Sub-Contract No. 71U8-1U85, dated: March 30, 1967 Change Order No.__ 6 Subject: Pipe Insulation_______ Date of Change Order December 27. 1967 Location: Armco Steel Corporation - Middletown Works - Middletown, Chip Sub-Contractor: Owens Corning Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio U52U1 DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes: 1. Remove and replace insulation of steam line at Column ft-D. ACCOUNT NO. 71U8-70U-89U-51 Sub-Contractor's Invoice #16158 dated November lU, I96". INCREASE - $ '8U.95 2. Remove and replace insulation at Columns U3> U3.20 and U3.30. ACCOUNT NO. 71U8-70U-89U.51 Sub-Contractor's Invoice #16156 dated November lU, 1967. INCREASE - $ 267.72 3. Remove and replace insulation on temporary U" steam line at Column 1-C. ACCOUNT NO. 7ll|8-70li-89J*.5l Sub-Contractor's Invoice #16159 dated November lU, 1967. INCREASE - $ 93.U5 U. Authorized premium time for work performed on November U, 1967 and November 7, 1967 ACCOUNT NO. 7lU8-5h.0-U60.5l Sub-Contractor's Invoice #1615? dated November lU, 1967. INCREASE - $ 1,038.71 5. Authorized premium time for work performed on October 23, 1967 and October 28, 1967. ACCOUNT NO. 71U8-5U0-U60.51 Sub-Contractor's Invoice #16160 dated November lU, 1967. INCREASE - $ 1,059.08 TOTAL INCREASE ------------ $ 2,593.91 CHANGE IN COMPENSATION: Total estimated amount increased from: $ 28U.5U6.56 to $ 287.lUO.U7 CHANGE IN COMPLETION DATE: None KEN 010749 Owens Corning Fiberglas Coip. -2- Sub-Contract No. 71U8-1U85 (C.O. #6) Except as herein expressly modified, said Sub-Contract as heretofore amended and all the terms and conditions thereof shall remain unaltered and in full force and effect and shall apply to all the work performed hereunder. ;'=\- s) ry ACCEPTED: ,^ AUTHORIZED: /'X1 OWENS CORNING FI3ERGIAS CORPORATION (Sub-Contractor) X..CJ ^'\v KAISER ENGINEERS, INC. Agent for Armco Steel Corporation (Contractor) By /s/ Paul C. Gahn --ZsZ_Yera,,!*. Irankscm Title Contr. & Sales En?. Dent. Title Manager - Procurement EOP:prl KEN 010750 INTER-OFFICE MEMORANDUM TO Vem L. Frankson AT W. M. Schuck DATE PROM COPIES TO See Distribution AT SUBJECT JOB NO. Sub-Contract No. 7lU8-lU8j> - Change Order No. 3 Owens Corning Fiberglas September 8, 1967 E. 0. Potts__ Middletown 711*8 Attached is a manually signed copy of subject Change Ord Conformed copies are being distributed. EOPiprl cc - with attachment AHMCO KAISER F. W. Barnes (2) P. R. Smith J. S. Lotz Reading File D. A. Daly Q. L. Roberts C. W. Graff H. C. Boucher (2) E. J. Denner (2) S. Ustel B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Iyon L. J. GLllett R. J. Wolf H.. R. D. Sahiberg Central File Reading File KEN 010751 DEVIATIONS FROM OR ADDITIONS TO SOB-CONTRACT AND SPECIFICATIONS Sub-Contract No. 71h.8-llj.85, dated March 30. 1967 Change Order Number __ 3 Subject: Pipe Insulation______ Date of Change Order August 28. 1967 Location: Armco Steel Corporation - Middletown Works, Middletown, Ohio Sub-Contractor: Owens Corning Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio Ii5>2lil DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes: (1) Insulate two (2) weld joints of ric-wil pipe. Insulate one (1) expansion pit. This work is located between anchor pit No. hi and east side of hot strip mill. Extra Work Order No. 1 COST ACCOUNT NO. 7lU8-70h-h65.5l Increase - $ 98.15 (2) Insulate one (l) weld joint and patches of ric-wil pipe. This work is located south of fuel oil pit No. 1. Increase - $ 82.06 Extra Work Order No. 2 COST ACCOUNT NO. 7lU8-70h-h65.5l (3) Insulate of U" - 165# Temporary steam line. This work is located at columns 1 and 2, "Cn line in the hot strip mill furnace aisle. Increase - $ 181.98 Extra Work Order No. 3 COST ACCOUNT NO. 71h8-70h-h65.L (ij.) Remove all ric-wil insulation and replace with new for anchor pits #hl, #33, #32 and #26. This work is located in the steelmaking- area. Increase - $ 2,8Ii7 33 Extra Work Order No. h COST ACCOUNT NO. 710li-701-89h.5l (5) Remove all ric-wil insulation, salvage and replace with same for steam expansion pit No. 29. Increase - $ 62il.89 Extra Work Order No. 5 COST ACCOUNT NO. 710l*-701-89U.5l (6) Remove all ric-wil insulation, salvage and replace with same for steam expansion Pit No. 33. Increase - $ 339.37 Extra Work Order No. 6 COST ACCOUNT NO. 710li-701-89li.5l TOTAL INCREASE------------$ 1.190.78 KEN 010752 Owens Coming Fiberglas -2- Sub-Contract No. 71U8-1U85 (C.O. #3) REFERENCE: Sub-Contractor's Invoices No. 15713, No. 1571U, No. 15710, No. 15715, No. 15711, and No. 15712 all dated August 2, 1967. CHANGE IN COMPENSATION! Total estimated amount increased from: $ 278.9U9.50 to $ 283.lUO.28 CHANGE IN COMPLETION DATE:- None Except as herein expressly modified, said Sub-Contract as heretofore amended and all the Terms and Conditions thereof shall remain unaltered and in full force and effect and shall apply to all the work performed hereunder. ACCEPTED: AUTHORIZED: TjA. fvKAISER ENGINEERS, INC. OWENS CORNING FIBERGLAS CORPORATION CV-Agent for Armco Steel Corporation (Sub-Contractor) VC\ (Contractor) By /s/ Paul C. Gahn w Title .<xy Contracting & SalesAEngineer By /s/ Vern L. Frankson Title Manager - Procurement ECP :prl ken 010753 INTER-OFFICE MEMORANDUM TO Vem L. Franksan AT W. M. Schuck DATE FROM COPIES TO See Distribution AT JOB NO. SUBJECT Sub-Contract No. 71i*8-li;8!? - Change Order No. 8 Owens-Coming Fiberglas Corporation February 28, 1968 Donald K. Carlson Middletown 71Jj8 -------- Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. DKCsprl cc - with attachment ARMCO KAISER F. W. Barnes F. U. Fanning P. R. Smith J. S. Lotz Reading File D. A. Daly G. L. Roberts C. W. Graff H. C. Boucher (2) J. L. Geiger C. R. Schwalen S. Ustel B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Lyon L. J. Gillett R. J. Wolf W. -Fi Bart. R. D. Sahiberg Central File Reading File KBN 010754 nTOTTATlQNS FRCH OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS Sub-Contract No. 711*8-11*85# dated: March 30. 1967. Change Order No. 8 Subject: Insulation of Slab Mil & Date of Change Order February 13. 1968 Soaking Pit Piping Location: South Area, Middletown Works, Armco Steel Corporation Sub-Contractor: Owens-Corning Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio 1*521*1 DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall furnish all labor, supervision, materials, supplies, transportation, tools, services, equipment, and rigging necessary to insulate the following additional piping systems for the lump sum prices shownj all in strict accordance with the amendments contained herein to Exhibit "A" and Exhibit "E": (1) 165 p.s.i. Steam Service System for Slab Mill. ACCOUNT NO. 7lU6-70U-U6j. LUMP SUM PRICE - $ 11,730.00 (2) 50 p.s.i. Steam Service System for Slab Mill. ACCOUNT NO. 71U6-70U-U65. LUMP SUM PRICE - $ 3,925.00 (3) 165 p.s.i. Steam Service System for Soaking Pits. ACCOUNT NO. 71U3-70U-U65 LUMP SUM PRICE - $ 7,695.00 (U) Fuel Oil "Bundle" System for Soaking Pits. ACCOUNT NO. 71U3-708-U65 LUMP SUM PRICE - $ 5.369.00 TOTAL LUMP SUM PRICE INCREASE...............................$ 28,719.00 It is mutually understood and agreed that the following specifications and drawings are hereby incorporated into the list of "Plans, Drawings and/or Specifications" - Exhibit "A": 1. Armco Steel Standard Insulation Specification No. ACS - 1*00 - 35. 2. Kaiser Engineers Slab Mill & Soaking Pits Piping Insulation Specification No. 711*6 (5-1*), dated January 9, 1968, and Addendum No. 1 dated January 18, 1968. PAGE 1 of 1* KEN 010755 Owens Corning Fiberglas -2- Sub-Cor.tract No. 7lk8-lk85 (C.O. //8) 3. Contracto r's Drawings: SLAB MILL Drawing No. Rev. 6311 ko 63III1I .63111*2 'o31lUU 6311U5 6311k6 6311U7 6311^1 631160 631562 631575 631576 631595 631597 5 y h<s k k 3 5 0 6 8 6 2 5 631598 k 631609 631610 631615 631616 63163k 631635 631636 631638 6316^1 6316U2 631656 631659 631662 631667 9 7 k 6 5 8 8 3 k k 2 2 k 6 SOAKING PITS 637031 63765k 637655 637656 637658 637659 637660 637671 1 1 Xt* X10 5' X* 2 1 Description Pump Room Piping Arrangsaent Pump Room Piping Arrangement Punp Room Piping Arrangement Oil Skimmer Piping Details Oil Skimmer Piping Details Oil Skimmer Piping Details Pump Room Heating and Ventilating Office Heating and Ventilating Steam Plow Diagram Basement Oil Lube Piping Scarfing Machine High and Low Pressure Piping Scarfing Machine High and Low Pressure Piping Steam Mains Plot Plan Scarfer and Mill Low Pressure Details Scarfer and Mill Low Pressure Details Service Piping Plan and Sections Service Piping Plan and Sections Steam Supply Header in Trusses Steam Supply Header in Trusses Basement Services Basement Services Basement Services Basement Services Basement Services Basement Services Sump Pumps and Steam Syphons Sump Pumps and Steam Syphons Steam to Air Filtration Unit Steam Anchors and Support Steam Flow Diagram Service Piping Arrangement Service Piping Arrangement Service Piping Arrangement Service Piping Details Service Piping Details Service Piping Details Steam Sump PAGE 2 of h KEN 010756 Owens-Corning Fiberglas -3- Sub-Contract No. 7lii8-lli8$ (C.O. #8) It is mutually understood and agreed that the following modifications or clarifications are hereby incorporated into the ''Special Provisions" Exhibit "E" and apply to Change Order No. 8: (A) Sub-Contractor shall furnish the necessaiy insulation materials for fittings, valves, etc., insulating cement for closing laps, sizing (lagging adhesive and preparation for painting by others), tie wires, bends, expansion joints, insulation supports, and all other materials, as required for proper installation thereof, and as directed by the Contractor, for the Slab Mill and Soaking Pit piping systems referred to herein. (B) The systems referred to herein include: 1. Steam systems and sub-systems, including supply and return headers, risers, service drops, steam tracers valve boxes, and where required, condensate returns, and other miscellaneous systems. 2. Fuel oil supply, fuel oil return, and the steam tracer (for maintaining fuel oil at 125 F), insulated as a "bundle". (C) Contractor, Sub-Contractor, and others will be working in the areas involved in this work and these areas will be congested. In this connection, storage space adjacent to the work site will be limited and such storage must be closely coordinated with the Contractor. (D) Sub-Contractor shall provide all required off-loading, handling, hoisting, material and equipment protection, to include weather protection for material in outside storage, rigging, scaffolding, picks, ladders, and all other equipment necessary for the proper installation of the work. (E) It is anticipated that Sub-Contractor can commence field work on a specified portion of The Work when this Change Order is awarded, and that subsequent work will be scheduled intermittently by Contractor with several "move-ins" required. The work will proceed on several systems concurrently, as programmed by Contractor, and Sub-Contractor shall "man" the work in accordance with priorities established by such programming. Completion dates for systems and/or sub-systems will be established by Contractor as required by the testing and operating schedules agreed to by Owner. In this connection, close coordination with Contractor shall be required of Sub-Contractor in order to achieve a realistic work sequence to meet such dates. Completion date for the work described in this Change Order is scheduled for July 17, 1968. PAGE 3 of U KEN 010757 Owens-Coming Fiberglas -1*- Sub-Contract No. 712*8-lk85 (C.O. #8) (F) Work on 3" - 16f$ steam service drops for Item #3, Soaking Pits, along column line "Y", terminates at valve at elev. liiO'-O" as shown on Drawing No. 637658, Rev. 5* Detail No. 3/637655*56. (G) Work on fuel oil bundle service drops for Item #h, Soaking Pits, along column line ,rY", terminates at valve at elev. lUO'-O'* as shown on Drawing No. 637658, Rev. 5* Detail No. 3/637655*56. (H) Work on fuel oil bundle for Item #U, Soaking Pits, begins inside building line near column point "Y-2.5" at termination of 16*," diam. conduit. Work in fuel oil pipe pit is not included in this Change Order. (I) Steam condensate piping shall be covered for personnel protection only. (Within 7'0" of floors and platforms) Insulation of flash tanks is deleted. It is mutually understood and agreed that due to the increase in scope of this Sub-Contract and to avoid any possible conflict with Owner's cost accounting system (project number prefixes) this Sub-Contract is hereby changed from the number designation "712*8-11*85" to "7100-11*85"* and shall be so designated in all subsequent correspondence, and payment reports. CHANGE IN COMPENSATION: Total estimated amount increased from: $ 290,016.65 to $ 318.735.65 CHANGE IN COMPLETION DATE: July 17* 1968. for the work described herein and March 29. 1968, for all other Sub-Contract work; the latter change pursuant to Article 15 of the General Terms and Conditions. Except as herein expressly modified, sqid Sub-Contract as heretofore amended and all the terms and conditions ther^rf^,shall remain unaltered and in full force and effect and shall apply to the work performed hereunder. ACCEPTED: ^ ,<S> OWENS-CORNING FIBERGLAS CORPORATION (Sub-Contractor) OCT By /s/ Paul C. Gahn /v) AUTHORIZED: KAISER ENGINEERS, INC. Agent for Armco Steel Corporation (Contractor) By /s/ Robert E. Bernard_________ Title Contr. & Sales Eng. Dept. Title Vice - President DKC:prl PAGE k of 2* KEN 010758 INTER-OFFICE MEMORANDUM TO Vem L. Frankson AT W. M. Schuck DATE PROM COPIES TO See Distribution AT SUBJECT JOB NO. Sub-Contract No. 7100-1^85 - Change Order No. 9 Owens-Corning Fiberglas Corporation March 1, 1968 E. 0. Potts^-. Middletown 7100 Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. E0P:prl cc - with attachment ARMCO KAISER J. . Neumann (2) P. R. Smith J. S. Lotz Reading File D. A. Daly G. L. Roberts C. W. Graff H. C. Boucher (2) E. J. Denner (2) S. Ustel B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Lyon L. J. Gillett R. J. Wolf W. F-.-Bog R. D. Sahlberg Central File Reading File KEN 010759 DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AMD SPECIFICATIONS Sub-Contract No. 7100-lM3$ dated: March 30, 1967- Change Order No. _9 Subject: Pipe Insulation Date of Change Order February 22, 1968 Location: Arwco Steel Corporation - Middletown Works - Middletown, Ohio Sub-Contractor: Owens-Corning Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio h&bX DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes: (A) Install insulation required for steam, condensate and fuel oil piping at fuel oil tanks above ground, in pipe tunnel under slab yard and in Fuel Oil Pit No. 1. ACCOUNT NO. 71l4.8-5l8-24.65.51 INCREASE - $ l,6gg.00 REFERENCE: Sub-Contractor's letter dated January 17, 1968. CHANGE IN COMPENSATION: Total estimated amount increassd from: $ 318,735.6$ to $ 320,390.65 CHANGE IN COMPLETION DATE: None Except as herein expressly modified, said Sub-Contract as heretofore amended and all the terms and conditions thereof shall remain unaltered and in full force and effect and shall an^f to all the work perx'onned hereunder. ACCEPTED: <5^ AUTHORIZED: OK. CWENS-CORNING FIBERGLAS CORPORATION (Sub-Contractor) By /s/ Paul C. Gahn KAISER ENGINEERS, INC. Agent for Armco Steel Corporation (Contractor) Ey /s/ Vem L. Frankson Title._____ Contr. & Sales Eng. Title Manager - Procurement E0P:prl KEN 010760 INTER-OFFICE MEMORANDUM TO Vern L. Franks on AT W. M. Schuck DATE FROM October 6, 1967 ^ COPIES TO See Distribution AT JOB NO. SUBJECT Sub-Contract No. 71U8-1U85 - Change Order No. h Owens Coming Fiberglas Corporation ` 'T` Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. EOPsprl cc - with attachment AHMCO KAISER F. W. Barnes (2) P. R. Smith <J. S. Dots Reading File D. A. Daly 0. L. Roberts C. W. Graff H. C. Boucher (2) E. J. Denner (2) S. Ustel B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Iyon L. J. Gillett R. J. Wolf Wy Frr-Boyfe R. D. Sahiberg Central File Reading File KEN 010761 DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AND SPECIFIC!?! ONS Sub-Contract No. 711t6-l2i8g, dated: March 30, 1967 Change Order Number _l_ Subject: Pipe Insulation Date of Change Order: September 29, 19o7 Location: Armco Steel Corporation - Middletown Works - Middletown, Ohio Sub-Contractor: Owens Corning Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio ij52Ul DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes: (A) Authorized premium time for work performed on July 8, 1967, July 1?, 1967 and July 22, 196'7. Increase - $ 1,?06.28 COST ACCOUNT NO. pi CHANGE IN COMPENSATION: Total estimated amount increased from: $ 2fi.VJ.10.25 to 28h,6h6.$6 CHANGE IN COMPLETION DATE: None Except as herein expressly modified, said Sub-Contract as heretofore amended and all the terms and conditions thereof shall remain unaltered and in full force and effect and shall apply tc all the work performed hereunder. ACCEPTED: GAINS CORNING FIBERGLAS CCRPCRA" (Sub-Contractor! By /s/ Paul C. Gahn AW' ^ V` ' Title Contr. & SalesT"Sn-?. V- V1 .. . } '-.`Afc. ... \ .J .. * ^ \ V.#Ji t ;'7r. U.,1^ '"'VL'^'DC T'h*' ;:t. for Armco Steel Corporation (Contractor) Dr /$/ Vsrn L. Frankson Ti.tlo Mans tor E0P:prl KEN 010762 INTER-OFFICE MEMORANDUM TO Vem L. Franks on AT W. M. Scbuck DATE PROM December 21, 1967 E. 0. Potts.^ COPIES TO See Distribution AT Middletown, Ohio JOB NO. 71U8 SUBJECT Sub-Contract No. 71U8-1U85 - Change Order No. 5 Owens-Corning Fiberglas Corporation Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. EOP sprl cc - with attachment ARMCO KAISER F. W. Barnes (2) P. R. Smith J S. Lotz Reading File D. A. Daly G. L. Roberts C. W. Graff H. C. Boucher (2) E. J. Denner (2) S. Ustel B. Scott A. L. Gordon C,, Billings F. No Norton M. Do Wilson So M. Iyon i* o o Gxllett R. Jo Wolf Wo-Po Bmt Ro D. Sahiberg Central File Reading File KEN 010763 DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS Sub-Contract No. 7lU8-llt8$, dated: March 30. 1967, Change Order No.__ Subject: Pipe Insulation______ Date of Change Order December 7. 1967 Location: Armco Steel Corporation - Middletown Works - Middletown, Ohio Sub-Contractor: Owens Corning Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio l;52lL DESCFJPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes: (A) Delete insulation work required for S.E.P. #39, for new underground Duel system located west of new 86" Strip Mill. (This work performed by others). DECREASE - ($100.00) ACCOUNT NO. 71i:8-5l8-U65.5l REFERENCE: Sub-Contractor's letter dated October 21;, 1967. CHANGE IN COMPENSATION: Total estimated amount increased from: $ 281t.6U6.S6 to $ 28U.gli6.g6 CHANGE IN COMPLETION DATE: None Except as herein expressly modified, said Sub-Contract as heretofore amended and all the terms and conditions thereof shall remain unaltered and in full force and effect and shall apply to all the work performed hereunder. ACCEPTED: AUTHORIZED: fA sS ' ,r\ KAISER ENGINEERS, INC. OVENS CORNING FIBERGLAS CORPORATION " 'jS Agent for Armco Steel Corporation (Sub -Contractor ) ~ (Contractor) 3y /s/ Paul C. Gahn By /s/ Vem L. Frankson TitleContr. & Sales Eng. Dent. Title______________ Manager - Procurerv^rp prl KEN 010764 INTER-OFFICE MEMORANDUM TO AT COPIES TO Vem L. Frankson W. M. Schuck C. W. Graff (2) H. C. Boucher (3) See Distribution DATE FROM AT JOB NO. subject Owens Corning Fiberglas - Change Order No. 2 Sub-Contract No. 7lU8-lU8$ August 2, 1967 MiddletoWu^^i ' ti V}V VJ"' i c ,,co " V. s-6055 ,"</ Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. SSSsprl cc - with attachment ARMCO KAISER F. W. Barnes (2) P. R. Smith J. S. Lotz Reading File D. A. Daly G. L. Roberts E. J. Denner J. Mainier S. Ustel B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. lyon L. J. Gillett - Oakland R. J. Minarcini - Oaldand W, Ps-Bcrtr-'- Oakland R. D. Sahiberg - Butler Central File Reading File 44 i '-9 \ KEN 010765 DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS SUB-CONTRACT NO. 7lU8-llj85 DATED: March 30. 1967 CHANGE ORDER NO. __2 SUBJECT Pipe Insulation DATE OF CHANGE ORDER July 2h, 1967 LOCATION: Arxnco Steel Corporation - Middletown Works. Middletown. Ohio SUB-CONTRACTOR: Owens Corning Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio Uj&ljl* 1 2 DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes: COMPENSATION: The Contractor having directed the Sub-Contractor to perform extra work not included in the original scope of this Sub-Contract hereby warrants additional compensation for items of work in amounts as follows: 1. Furnish Labor Only to insulate three (3) weld joints and two (2) S. E. P.'s in 16" Diameter Line all located within Hot Strip Mill between column lines C & E. (a) All material to be furnished by Ric-Wil. (b) All patching of damaged Ric-Wil casing - by others. (c) Sealing of weld joints - by others. LUMP SUM PRICE - $525.00 2. Furnish Labor Only to insulate sixty-eight (68) weld joints, sixteen (16) steam expansion pits and five (5) expansion joints in anchor pits. Material to be furnished by Ric-Wil. Also, furnish labor and material to insulate pipe and fittings in six (6) anchor pits and two (2) steam valve pits. Includes: 16" line from South end of new strip mill to steam valve pit No. 3* 10" line from steam valve pit No. 3 to anchor pit PH-3 and 12" line from steam valve pit No. 3 to anchor pit No. 56 at pickle line. All as shown on Ric-Wil Drawing No. 6315 sheets #7, #8 and #9. Excludes: Tl) Line from roll shop to pickle line at top of sheet #7 (2) All patching of damaged Ric-Wil casing - by others. (3) Sealing of weld joints. By others. LUMP SUM PRICE: 16" Diam. Line 10" Diam. Line 12" Diam. Line TOTAL $ 1,700.00 $ liOO.OO $ li.750.00 $ 6,850.00 KEN 010766 Owens Corning Fiberglas -2- Sub-Contract No. 711i8-lli85 (C. 0. #2) 3. Furnish Labor Only to insulate one hundred and thirty-five (135) weld joints and S. E. P. No. 3? for new fuel oil system located West of new 86" strip mill. Work limited to piping shown on Ric-Wil Drawings D-7i0i7, #1 and #2, D-72i?8 and B-65U9. All material to be furnished by Ric-Wil. Exclude! (1) All patching of damaged Ric-Wil casing - by others. (2) Sealing of weld joints - by others. LUMP:SUK PRICE $3,375.00 TOTAL NET INCREASE THIS CHANGE ORDER - $ 10.750.00 INTERNAL ACCOUNTING INFORMATIONS COST ACCOUNT NUMBERS:- 710U-710-li65.5l 71ij.8-70l4.-Ai.65.51 71U8-518-14.65.5l TOTAL $ 14,750.00 $ 2,625.00 $ 3,375.00 $ 10,750.00 CHANGE IN COMPENSATION Total Estimated Amount Increased From $268,199.50 ________________ To $278,9L9.50 CHANGE IN COMPLETION DATE None EXCEPT AS HEREIN EXPRESSLY MODIFIED, SAID SUB-CONTRACT AS HERETOFORE AMENDED AND ALL THE TERMS AND CONDITIONS THEREOF SHALL REMAIN UNALTERED AND IN FULL FORCE AND EFFECT AND SHALL APPLY TO ALL THE WORK PERFORMED HEREUNDER. ACCEPTED: AUTHORIZED: KAISER ENGINEERS, INC. OWENS CORNING FIBERGLAS CCSR?ORATION^ Agent for Afmco Steel Corporation (Sub-Contractor) 'TTr>i "(Contractor) By /g/ Paul C. Gahn * > - By /s/ D. A. Pair Title_____ Contr. & Sales EngT' -A Title Project Manager SSS:prl KEN 010767 DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS SUB-CONTRACT 711*8-11*85 DATED* March 30. 1967 CHANGE ORDER NO. One SUBJECT Inmil,ation DATE OF CHANGE ORDER May 2. 1967 LOCATION* Hot Strip Mill and Boiler House - Armco Steel Corporation Middletown Works Middletown. Ohio SUB-CONTRACTOR* Owens-Coming Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio 1*521*1 DESCRIPTION OF CHANGE: Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changes* For all Type "B" (Calcium silicate) insulation in the Hot Strip Mill, in lieu of specified 6-ounce canvas with field sizing, substitute {las cloth jacketing with factory applied sizing* For all pipe insulation in the Waste Heat Boiler House, in lieu of specified 8-ounce canvas with field siting, substitute glas doth jacketing with factory applied sizing. In the event the factory is unable to provide either of the above substitutions, the original specifications will apply* Also, the 165# steam line insulation already purchased by Contractor on a separate order will be installed as originally specified except those sizes which require field application of jacketing shall . receive pre-sized glas cloth. REFERENCES* Sub-Contractor's letters of April 21, 1967 and April 26, 1967* CHANGE IN COMPENSATION None CHANGE IN COMPLETION DATE None EXCEPT AS HEREIN EXPRESS!! MODIFIED, SAID SUB-CONTRACT AS HERETOFORE AMENDED AND ALL THE TERMS AND CONDITIONS THEREOF SHALL REMAIN UNALTERED AND IN FULL FORCE AND EFFECT AND SHALL APPLT TO ALL THE WORK PERFORMED. HEREUNDER. ------------------------- ------------------------- --------------------------------------- --------------------------- ACCEPTED* -------------NJ AUTHORIZED* OWENS-CORNING FIBERGLAS CORPORATION (Sub-Contractor) KAISER ENGINEERS, INC. Agent for Armco Steel Corporation (Contractor) ' By /s/ Paul C. Gahn^vV "K5 Title Cqntr. fe Sales Engineer By /b/ Vern L. Frankson Title Manager - Procurement KEN 010768 INTER-OFFICE MEMORANDUM TO Vem L. Frankson AT W. M. Schuck DATE FROM copies TO See Distribution at job no. Sub-Contract No. 7100-1U85 - Change Order No. 10 Owens-Corning Fiberglas Corporation March 28, 1968 E. 0. Potts Middletown, Ohio 7100 Attached is a manually signed copy of subject Change Order. Conformed copies are being distributed. EQP:prl cc - with attachment AHMCO KAISER F. W. Barnes (2) P. R. Smith J. S. Lots Reading File D. A. Daly G. L. Roberts C. W. Graff H. C. Boucher (2) E. J. Denner (2) S. UsteL B. Scott A. L. Gordon C. Billings F. N. Norton M. D. Wilson S. M. Lyon L. J. Gillett R. J. Wolf Wt Sort R. D. Sahiberg Central File Reading File KEN 010769 DEVIATIONS FROM OR ADDITIONS TO SUB-CONTRACT AND SPECIFICATIONS Sub-Contract No. 7100-11*8$, dated! March 30, 1967 Change Order No. 10 Subjects Pipe Insulation Date of Change Order March 19. 1968 Locations Armco Steel Corporation - Middletown Works - Middletown, Ohio Sub-Contractors Owens-Corning Fiberglas Corporation 2987 Exon Drive Cincinnati, Ohio 1*521*1 DESCRIPTION OF CHANGES Pursuant to the provisions of Article 8 of the General Terms and Conditions, Sub-Contractor shall perform The Work in accordance with the following changess (A) Remove, salvage and re-insulate pusher drive and west flume on lube oil #1*, so electric heat tracers be installed. ACCOUNT NO. 711*8-l*l*l-89l*.51 Sub-Contractor's Invoice #25931* dated January 21*, 1968. INCREASE - $ l*,l*26.2l* (B) Insulate twenty-seven (27) weld joints in 12" - 16$# steam line between roll shop and pickle line as shown on ric-wil drawing #0315, sheet #7. Insulate two (2) additional weld joints in 16" - 1*25# steam line (not shown on drawings). Remove and re-insulate S.E.P. #1*1 on ric-wil line east of the hot strip mill. E.W.O. #8 ACCOUNT NO. 7101*-710-1*61*.5l Sub-Contractor's Invoice #25937 dated January 21*, 1968. INCREASE - $ 1,137.1*2 (C) Insulate lV condensate line from fuel oil heaters approximately one (1) ft. beyond the steam trap. E.W.O. #10 ACCOUNT NO. 711*8-70i*-l*6$.5l Sub-Contractor's Invoice #25935 dated January 21*, 1968 INCREASE - $ 91.63 (D) Insulate the furnace cooling water bypass manifold located south west of the clarifier punp house. E.W.O. #11 ACCOUNT NO. 7ll*8-5lii-i*6i*.5l Sub-Contractor's Invoice #25936 dated January 21+, 1966. INCREASE - $ 398.71* (E) Insulate water line going into the slab yard #1 pulpit. Insulate pipe and an additional valve on lube oil #1* near storage tank. E.W.O. #9 ACCOUNT NO. 7ll*8-4l-89l*.5l Sub-Contractor's Invoice #2591*5 dated February 7, 1968 INCREASE - $ 250.91 KEN 010770 Owens-Coming Fiberglas -2- Sub-Contract No. 7IOO-IJ48S (C.O. #10) DESCRIPTION OF CHANGE s Continued (F) Insulate duct work from air conditioning unit to pulpit in slab yard. E.W.O. #lU ACCOUNT NO. 711i8-28l-k30.L Sub-Contractor's letter dated January 30, 1968 INCREASE - $ 178.00 . TOTAL INCREASE...............................$ 6,lt82.9l* CHANGE IN COMPENSATION? Total estimated amount increased from: ' $ 320,390.6$ to $ 326.873.59 CHANGE IN COMPLETION DATES None Except as herein expressly modified, said Sub-Contract as heretofore amended and all the terms and conditions thereof shall remain unaltered and in full force and effect and shaj-fe^apply to all the work performed hereunder. rvs* ACCEPTED s OWENS-CORNING FIBERGLAS CORPORATION (Sub-Contractor) vC=' By /s/ Paul C. Gahn ________ AUTHORIZEDs KAISER ENGINEERS, INC. Agent for Armco Steel Corporation (Contractor) By /s/ Vem L. Franks on Title Contr. St Sales Eng. Dept. Title Manager - Procurement ECPsprl KEN 010771 TO AT COPIES TO Vern L. Franks.on W. M. Schuck Co W. Graff Ho C. Boucher (3) See Distribution from June 1, 1967 Donald K Carlson at Middletown JOB NO. 7lll8 SUBJECT Sub-Contract No. 7lhQ-lkQ$ Owens-Corning Fiberglas Corporation, for Insulation ,.*SL Attached are the only pages that have been revised since my transmittal letter of April 17, 1967. Also attached is a conformed copy of the signature, page. , Copies are being distributed of couplets manually signed documents. DKCsprl cc - with attachment ARMGO KAISER F0 W. Barnes (2) Po R. Smith Jo S. Lotz Reading File D. A. Daly Go L. Roberts E. Jo Denner Wo Woodcock S. UsteL Bo Scott A. L. Gordon Co Billings F. No Norton Mo Do Wilson So Mo Iyon Lo Jo Gillett - Oakland Ro Jo Minarcini - Oakland Mu Fg "Bui Oakland Ro Do Sahlberg - Butler Central File Reading File KEN 010772 INTER-OFFICE MEMORANDUM TO L. J. Gillett AT Oakland, California COPIES TO See Distribution ^ /A (+en -faf-n/e C-CpyJ DATE April 1?, 1967 FROM i. 1 irxson //XXTT'. ---Middletown, Ohio , VV;-0-'. hr- ,\ / ' \ YJOB iWt33M SUBJECT Sub-Contract No. 71U8-1U85 Owens-Coming Fiberglas Corporation Piping & Equipment Insulation Estimated Prices $268,199.50 ------ ARMCO Wo Mo Schuck PcRo Smith Lotz 5Hr,, Barnes Reading File Attached for legal review and management signature are five (5) copies of subject Sub-Contract, as well as an additional copy for you to retain in your files. Also attached! Wire of Award dated March 30, 1967 Fully Approved Recommendation dated March 28, 1967 Owens-Coming Proposal on signed K.E. Form dated February 20, 1967 The Contract is identical to Proposal documents with the following necessary changes and appropriate improvements: (1) Item I of Compensation .supersedes Annex "B" (lump sum for Boiler House Piping and Equipment) (2) We have re-organized Compensation Annex "A" because Sub-Contracts Engineer, Mr. Carl Gilmer, has slightly changed quantities of piping insulation. He has also established quantities for metal jacketing of piping, and for insulation of Equipment and Vessels. The latter item is now shown as a new Section X rather than being shown in the nextto-last column of Piping Sections I - IX. There was no definitive basis for this item being included in any piping schedules since there is no relationship between areas of equipment insulation to lineal feet or area of piping insulation, jacketing, etc. Relatively small quantities of three new piping items have been established by Mr. Gilmer and the attached supplementary proposal of April 13, 1967, confirms these three pricing items. In order to confirm the mutual understanding of how the estimated total price was calculated, we have e:xplained in Special Provision No. 11, Mr. Gilmer's estimates and allowances, and the various categories of unit prices where no quantities were inserted. (3) The Sub-Contractor requested that Special Provision No. 12 be inserted and we have agreed. This is same billing agreement as on several other contracts of this type. Insulation material must be ordered about eight (8) weeks in advance of need so tbat-completion schedule can be met KAISER D. A. Daly G. L. Roberts C,, Gilmer J. O' Donnell Vern L. Frankson C. W. Graff H,, C. Boucher S. Ustel L. H. Kash A. L. Gordon F. P. Kennedy - F. N. Norton M. D. Wilson S. M. Lyon -- R. J. Minarcini - Oakland- W. F, Bort - Oakland R. D. Sahlberg - Butler Central File Reading File KEN 010773 < I i ] i SUB-CONTRACT Sub-Contract No. 711*8-11*85 March 30, 1967 This Sub-Contract is made pursuant to a Contract between Armco Steel Corporation (hereinafter called "Owner"), and Kaiser Engineers, Inc. (hereinafter called "Contractor"), Agent for Armco Steel Corporation, whereby Contractor agreed with Owner to furnish engineering, construction and other services relating to the expansion and modernization program at Owner's Middletown Works, Middletown, Ohio, Contractor and Owens-Corning Fiberglas Corporation (hereinafter called "Sub contractor") hereby agree that the following work shall be performed by SubContractor for the compensation and upon the terms and conditions hereinafter set forth on Face Sheets "A" and "B" of the Sub-Contract and including Articles 1 through 37 of the General Terms and Conditions attached to and made a part of this Sub-Contract. WORK TO BE PERFORMED: Furnish all labor, supervision, material, supplies, transportation, tools, services, equipment and rigging necessary to install only the Owner-furnished insulation for the 165 p.s.i. steam service, and to furnish and install other insulating materials, field-applied metal jacketing, and weather-proofing required for the 165 p.s.i. steam service, and to furnish and install insulation, metal jacketing, weather-proofing and anti-sweat protection on piping, vessels and machinery, where required, on all service systems, all in strict accordance with, or to be inferred from. Exhibit "A", all such work being hereinafter sometimes called "The Work". PLANS, DRAWINGS AND/OR SPECIFICATIONS: Attached hereto as Exhibit "A" and by this reference made a part hereof. ITEMS TO BE SUPPLIED BY CONTRACTOR: As per list attached hereto marked Exhibit "B", and by this reference made a part hereof. LOCATION OF WORK: New Hot Strip Min, and Waste Heat Boiler House in South Area of Owner's Middletown Works, Middletown, Ohio. WORK TO COMMENCE: As of the date of this Sub-Contract, with field work to commence on date specified in Contractor's Notice to Proceed to be issued to Sub-Contractor. WORK TO BE COMPLETED: Time is of the essence of this Sub-Contract, and all work shall be completed by Sub-Contractor as soon as due diligence and good practice will permit, but in no event later than November 3, 1967, or such extended conpletion date as may be applicable in accordance with and pursuant to the provisions of Article 1$ hereof. FACE SHEET "A" KEN 010774 Sub-Contract No. 7lU8-lli85 Page 1 of 7 COMPENSATION ANNEX "A11 Section Is Steam 0# - Type "B" Insulation Pipe Insul. Size Depth Price of Insul. per lin. ft. Estd. Lgth.-Am't. ft. / $ Price of intisweat per Lin. ft. UNIT PRICES Price of Metal Weather Jacketing proofing per per lin. ft. sq. ft. Estimated Metal Jacket. Area-Am't. sq. ft. / $ h" ih" $l.lt3 80'/$ nli.Uc $ 1.13 $ .96 i" ih" $1.33 80'/$ 122 M $ 1.19 $1.10 2" 2" $2.26 80'/$ 180.8C $ 1.76 $1.59 $1.11: $1.02 $ .78 U0/$ JU5.60 JUo/$ iiO.80 Uo/$ 31.20 2k" 2" $2.38 80'/$ 190.UC $ 1.83 $1.83 $ .72 U0/$ 28.80 k" 2k" $3.U5 200'/$ 690.OC $ 3.23 $2.30 $ .60 100/$ 60.00 6" 2k" $U.l5 100'/$ Ui5.oc $ U.20 $2.U8 $ .58 50/$ 29.00 8" 2k" $U.77 100'/$ U77.0C $ U.65 $2.93 $ .58 50/$ 29.00 12" 3" $8.U3 100*/$ 8U3.0C $10.20 $3.96 $ .58 50/$ 29.00 lii" 3" $9.30 200'/$1 .900.0C $10.75 $U.18 $ .58 100/$ 58.00 SSTIMATED TOTAL PRICE $1*. 933.00 $351.liO Section II: Steam 50# - Type "B" Insulation 3/k" Ik" $l.Iiii 200'/$ 288.00 $ 1.15 $ .96 1" . ik" $1.33 300'/$ 1*59.00 $ 1.19 $1.10 1^" ih" $1.60 300'/$ U80.00 $ 1.23 $1.19 lV Ik" $1.65 h00'/$ 660.00 $ 1.28 $1.19 2" 2" $2.25 1200*/$2 .700.00 $ 1.76 $1.59 3" 2" $2 .l8 200'/$ U96.00 $ 1.93 $1.83 h" _ 2V 8" 2k" $3.U5 $L.77 100'/$ 3U5.00 $ 3.23 100'/$ U77.00 $ li.65 $2.30 $2.93 12 3" $8.Wi 100'/$ 8U11.00 $10.20 $3.96 ESTIMATED TOTAL PRICE $6,7U9.00 $l.lli $1.02 $ .96 $ .96 $ .78 $ .72 $ .60 $ .58 $ .58 100/$ll]i.00 100/$102.00 100/$ 96.00 100/$ 96.00 100/$ 78.00 100/$ 72.00 100/$ 60.00 100/$ 58.00 100/$ 58.00 $73U.QQ KEN 010776 Sub-Contract No. 71k8-lud5 COMPENSATION ANNEX "A" Section III: Steam 165# - Type "B" Insulation Page 2 of 7 Pipe Size Price to Install Owner Insul. furnished Depth Insul. Estimated Lgth.-Am't. ft. / $ UNIT PRICES AntiSweat Insul. per lin. ft. Weather proofing per lin. ft. Metal Jacketing per sq. ft. Estimated Metal Jacket. Area-Am't. sq. ft. / $ k" lk" 3/k" Ik" 1" lk" $ .93 $ .93 $ .99 1800'/$1,67U.00 $ 1.13 l500/$l,395.00 $ 1.15 5200'/$5.lU8.00 $ 1.19 $ .96 $ .96 $1.10 $l.lh $l.lli $L. 02 200/$228.00 200/$228.00 200/$20h.00 lk" lk" $1.02 600'/$ 612.00 $ 1.23 $1.19 $ .96 100/$ 96.00 Ik" lk" $1.02 7000'/$7,lli0.00 $ 1.28 $1.19 $ .96 100/$ 96.00 2" 2" $1.20 61i80'/$7.776.00 $ 1.76 $1.59 $ .78 100/$ 78.00 3" 2" $1.28 35oo'/$U,U8o.oo $ 1.9U $1.83 $ .72 100/$ 72.00 k" 2k" $1.55 2h00'/$3,720.00 $ 3.23 $2.30 $ .60 100/$ 60.00 6" 2k" $1.76 120'/$ 211.20 $ U.20 $2.U8 $ .58 5>0/$ 29.00 8" 2k" $2.09 600'/$l,25U.00 $ U.65 $2.93 $ .58 100/$ 58.00 12" 3" lk" 3" $U.ll $U.66 1200'/$U,932.00 $10.20 l800'/$8,388.00 $10.7U $3.96 $U.l8 $ .58 $ .58 ioo/$ 58.oo 100/$ 58.00 1 ESTIMATED TOTAL PRICE $1^6,730.20 $1,265.00 For any footages of insulation for the above pipe service required in excess of amount furnished by Contractor/Owner (quantities shown in lith column above), the following Unit Prices will apply (all Sub-Contract prices except those in 3rd & Uth columns above encompass "furnishing and installing"): Pipe Insul. Size X Depth k" X ~w X X 351 X iw X O *1 X lk" lk" 2" ESTIMATED TOTAL Unit Price $l.ii3 $17113 $1.53 $1759 IT33 $2.7^ 'S Estimated Lgth. -Am't. ft. / $ 200'/$ 286.00 200'/$ 290.00 200'/$ 306.00 100'/$ 159.00 700'/$!,155.00 rp68'/$l,503.00 $3,6?.00 Pipe Insul. Size X Depth 3" X 2" k" X ~~W' 6" X ~~W' 8" X ~~W' 12" X V> IF1- X 3" Unit Price $2.U8 $3.U5 $.15 $k.77 $8.ii3 $9.50 Estimated Lgth. -Am't. ft. / $ 350'/$ 868.OC 2L0'/$ 828.OC C0 l6o'/$ 763.2C 00 200'/$!,900.0C $U,359.20 KEN 010777 Sub-Contract No. 71U8-1U85 Page 3 of 7 COMPENSATION ANNEX "A11 Section I?i Steam 280# - Type "B*1 Insulation UNIT PRICES pipe Insul, Size Depth Price of Insul. per lin. ft. Estimated Lgth. -Ain't. ft./-$ Antisweat Insul. per Lin. ft. Weather proofing per Lin, ft. Metal Jacketing per sq. ft. 3/lt" 1" 2s" $ 2.75 $ 2.83 120'/$ 330.00 5oo'/$i, lag,oo $ 2.30 $ 2.U0 $1.59 $ .77 $ .77 lV ^L 3" 3" $ 3.Oil $ U.02 200'/$ 608.00 200'/$ 80iu00 $ 2.53 $ 3.35 $1.83 $2.30 $ .70 $ .61 U" 3" 6" 3" $ It. 50 $ 5.50 500'/$2.2g0.00 $ 3.76 100'/$ gfo.oo $ It. 59 $2.57 $2.68 $ .58 10*' lU" $6" U" $10.68 $lU.U6 100'/$!.068,00 $ 7.96 100'/$!,14*6.00 $13.20 $3.76 $U.62 $ .58 $ .58 ESTIMATED TOTAL PRICE $8.1*71.00 Section V: Steam & 1*25# - Type "B" Insulation Estimated Metal Jacket. Area-Axn't. sq. ft. / $ 100/$ 77 .00 100/$ 77.00 100/$ 70.00 100/$ 6U.00 100/$ 58.00 100/$ 58.00 100/$ 58.00 100/$ 58.00 $520.00 3A" 2k" 1" 2V' Ik" 2g Ik" 2?s 2" 3" 3" U" 3" 6" 3" .10" ...as!'-. $ 2.75 $ 2.83 $ 2.87 $ 3.05 $ 3.ll* $ 1*.02 $ U.ii9 $ 5.50 $10.68 2oo*/$ 55o.oo $ 2.30 5oo*/$i,ia5.oo $ 2.1*0 100'/$ 287.00 $ 2.1*3 300'/$ 915.00 $ 2.53' 800/$2,512.00 $ 2.60 200'/$ 80l*.00 $ 3.35 100'/$ 14*9.00 $ 3.76 ioo'/$ 55o.oo $ 1*.70 100'/$1.068.00 $ 7.96____ $1.59 $1.59 $1.59 $1.83 $1.83 $2.30 $2.57 $2.68 $ .77 $ .77 $ .77 $ .70 $ .70 $ .6U $ .58 $ .58 -JL,58.... 100/$ 77.00 100/$ 77.00 100/$ 77.00 100/$ 70.00 100/$ 70.00 100/$ 61*. 00 ioo/$ 58.oo 100/$ 58.00 100/$ 58.00 KEN 010778 Sub-Contract No. 71U8-1U85 COMPENSATION ANNEX "A" Section Vs Steam @ 1|25$ - Type "B" Insulation - (continued) *ipe Size 12" Instil. Depth li Price of Insul. per lin. ft. Estimated Lgth.-Am't. ft./ $ Anti sweat Insul. per Lin. ft. $13.18 100'/$1.3l8.00 $12.00 Weather proofing per lin. ft. $U.39 1U" k" $lU.U6 100*/$1.UU6.00 $13.20 $U.62 16" hk" 2li" hk" $17.20 $23.60 200/$3,Uii0.00 120'/$2.832.00 $15.75 $20.96 $5.26 $6.88 ESTIMATED TOTAL PRICE $19.218.00 Page 1* of 7 Metal . Jacketing per sa. ft. Estimated Metal Jacket. Area-Am't. 80. ft./ $ $ .58 100/$ 58.00 $ .58. 100/$ 58.00 $ .58 ioo/$ 58.oo $ .58 100/$ 58.00 $918.00 Section VI: Steam Condensate - Type ."S" Insulation y 1" $ 1.08 1200'/$1.296.00 ""$"":8o 1" 1" $ 1.17 l800'/$2,106.00 t -.85 'iy 1" $ 1.28 I800/$2,30ii.00 $ .99 2" 1" $ l.liO 3600'/$5.0U0.00 $ 1.02 3" 1" $ 1.59 lli00/$2,226.00 $ 1.12 12" 1" $ U.liO 20'/$ 88.00 $ 3.52 16" lk" $ 7.50 100'/$ 750.00 $ 6.U8 2h" .lk" $10.95 Uo/$ J4.38.0c $ 9.U3 ESTIMATED TOTAL PRICE $liu2U8.00 ifTS9 $ .814 $ .96 $1.10 $1.37 $3.37 $3.96 $5.63 1019 $1.26 $1 .lU $1.02 $ .86 $ .58 .... $ .58. $ .58 100/$lli9.00 100/$126.00 100/$llU.00 100/$102.00 100/$ 86.00 0/0 100/$ 58.00 0/0 $635.00 KEN 010779 Sub-Contract No. 711i8~lU85 Page 5 of 7 COMPENSATION ANNEX "A" Section VII? Lube Oil & Morgoil - Type "0" Insulation ?ipe Size Insul. Depth Price of Insul. per lin. ft. Estimated Lgth.-Ain't, ft. / $ Price of Antisweat per lin. ft. UNIT PRICES Price of Weather proofing per lin. ft. Metal Estimated Jacketing Metal Jacket. per Area-Am't. SQ. ft. sq. ft. /$ V 1" $ ,8U 350'/$ 29U.OO $ .80 $ .69 $1.U9 100/$lU9.00 3/U" 1" $ .86 800'/$ 688.00 $ .81* $ .69 $1.U9 500/$7U5.00 1" 1" $ .88 900'/$ 792.00 $ .87 $ .81; $1.26 100/$126.00 iV 1" IV 1" $ .92 $1.01 200/$ 18U.00 900'/$ 909.00 $ .90 $ .99 $ .8U $ .96 $1.26 $l.lli 100/$126.00 100/$llU.00 2" 1" $1.05 900'/$ 9U5.00 $1.02 $1.10 $1.02 100/$102.00 2V 1" $1.10 60'/$ 66.00 $1.09 $1.19 $ .96 50/$ Ii8.00 r 1" ii" 1" $1.15 $1.38 2600'/$2,990.00 $1.12 5000/$6,900.00 $1.3U $1.37 $1.59 $ .86 $ .78 100/$ 86.00 100/$ 78.00 6" 1" $L.80 U000! /$7,200.00 $1.73 $2.06 $ *61i 100/$ 6U.OO 8" 1" $2.26 1700'/$3,8U2.00 $2.23 $2.57 $ .58 100/$ 58.00 10" 1" $2.75 752'/$2,068.00 $2.69 $2.68 $ .58 100/$ 58.00 12" 1" $3.20 125'/$ U00.00 $3.15 $3.19 $ .58 100/$ 58.00 16" iV $6.62 200'/$l,32li.00 $6.U8 $3.96 $ .58 100/$ 58.00 20" $8.17 200'/$l963U.00 $7,96______ $U.78 $ .58 100/$ 58.00 ESTIMATED TOTA][ PRICE $30,236.00 $1,928.00 Section VIII % Fuel Oil - Type "0" Insulation As" -Jail__ $1.10 VE77* -ift" "tuIE 1" $1.17 IP7*" IV $1.32 2" IV $1.37 3" IV $1.52 it" $1.72 6" Pv w "$2.15 $2.56 ^V $3.15 ESTIMATED TOTAL PRICE 600'/$ 660.00 200'/$ 228.00 200'/$ 23U.OO 300'/$ 396.00 1200'/$l,6Ui.00 100'/$ 152.00 200'/$ 3iiii.00 300'/$ 6ii5.00 100'/$ 256.00 500'/$l,575.00 $1.13 $1.15 31.19 $1.26 $1.37 $1.50 $1.69 $2.12 $2.50 $3. Oil $6,13U.OO ------------- $ .96 $ .96 $1.10 $1.19 $1.37 $1.59 $1.83 $2.30 $2.U8 $2.93 $L.1U SBL.lli $1.02 $ .96 $ .86 $ .78 $ .72 $ .60 $ .58 $ .58 KEN 010780 100/! mu. 00 Too/i mil.00 Too7i 102.00 Too7i ; 96.00 Too7i 86.00 39.00 100/s i 72.00 100/! 6o;oo ~Too7i ; 58.00 Too7i 58.00 $79?.00 ---------- Sub-Contract No. 711*8-li*85 Page 6 of 7 COMPENSATION ANNEX "A" Section IX; Service 0 - 300 F. Miscellaneous Systems. Insul. as required Pipe Size Insul. Depth Price of Insul. per lin. ft. Estimated Lgth.-Am't. ft. / $ 1" $ .80 0 3A" 1" $ .81* 0 1" 1" $ .86 0 iy 1" $ .90 0 h" 1" $ .99 0 2" 1" $1.03 0 3" 1" $1.12 0 It" 1" $1.3lt 0 6" 1" $1.73 0 8,: 1" $2.23 0 10" 1" $2.69 0 12" 1" $3.13 0 lit'' 1" $3.59 0 ESTIMATED TOTAL PRICE -0- o CO. CO Price of Antisweat per lin. ft. $ .86 $ .90 $ .99 $1.03 $1.12 $L.3l* $1.73 $2.23 $2.69 $3.15 $3.59 Price of Weather proofing per lin. ft. Metal Jacketing per sq. ft. Estimated Metal Jacket Area-Am't. SQ. ft./$ $ .69 $1.1*9 0 $ .69 $1.1*9 0 $ .81* $1.26 0 $ .81* $1.26 0 $ .96 $1.11* 0 $l.io $1.02 0 $1.37 $ .86 0 $1.59 $ .78 0 ? $2.06 $ .61* 0 $2.57 $ .58 0 $2.68 $ .58 0 $3.19 $ .58 0 $3.37 $ .58 0 -0- KEN 010781 Sub"Contract No. 71L8-1L35 Page 7 of 7 COMPENSATION ANNEX "A" Section X; Insulation cf Equipment, Vessels and Machinery (cross-referencsd to types of insulation per Sections I through IX) Insul. Depth *-Price per sq. ft- Est. sq- ft. Est. total price i" $2 .<9 0 0 Ik" A It-' -1*659......... $5lU8.00 2" $3-21 200 $ 628.00 2k" $3.35 100 $ 335.00 3" $3.U7 5Q _ $ 173.50 3k" $L.60 0 0 h" $u.72 0 0 f cx>w 1____ hk" 0 0 ESTIMATED TOTAL FRIG hi -.Q * Sections T T PRICES PER SQUARE FOOTi Sections IV k V Sections VI & IX ? _:uions VII & VIII $3.06 $3.18 . ... $2.59 $2.. 65 _ $U.36 $U.U8 $U.60 $U.?2 $U.83 010782 VCEN Sub-Contract No. 711:8-11:85 EXHIBIT "A" FLANS. DRAWINGS AND/OR SPECIFICATIONS The following specifications and drawings are hereby incorporated: 1. Kaiser Engineers Hot Strip Mill Specification No. 71U8 (5-5), "Piping and Equipment Insulation" dated January 27, 1967. 2. Dravo Corporation Specification (#M822-CF17), "Hot Strip Mill Waste Heat Boilers - Thermal Insulation", dated January 27, 1967, (Add. No. 1 correction on page 1). 3. Contractor's Drawings (subject to revision as design progresses): 601308 601325 60131:2 601350 601356 601358 601359 601363 601361: 601366 601371 601383 601381: 601390 601395 601396 601399 6011:05 601115 601H6 6011:20 601U21 6011:23 601U21: 6011:31 6011:36 6011:37 60114:0 6011:51 6011:51: 6011:76 601511: 601515 601516 601523 601521: 601527 601529 60153U 601539 60151a 6015U3 601514: 6015U5 6015U8 601550 601551 601551: 601555 601556 601575 601581: 601595 601598 601603 60160U 601622 601623 601625 601655 601656 601685 601686 601687 601688 601689 601690 601691 601692 601699 601700 601703 601708 60172U 601727 601730 601731 601732 601733 601767 601771 601810 601818 601819 625603 629971 629977 629979 629981: 629990 629991 629992 629998 629999 630000 630001: Page 1 of 2 ken o'10783 H H H H w w numva f- EXHIBIT "A" -2- Sub-Contract No* 711*8-11*85 U. Dravo Corporation Drawings (Waste Heat Boiler House)* Number Rev* 6210.77 6210.78 6210.79 6220L80 6210.81 6210.82 6210.83 6210.8k 6210.85 6210.86 6210-88 6210.89 - 3 2 3 '3 3 3 3 3 3 3 3 3 Number 6210L90 6210.91 621*203 621*205 621*206 621*207 621*210 621*211* 621*232 621*233 621*231* 621*235 Rev* 3 3 i* 3 2 3 2 2 3 1* 3 5 Number 621*236 621*237 621*238 621*239 621*21*0 621*21*1 621*21*2 621*21*3 621*21*1* 621*21*6 621*21*7 621*21*9 - Rev* 2 1* 2 5 5 5 1* 1* 3 1* 1* Number 621*252 621*255 621*260 621*261 621*262 621*265 621*273 621*271* 621*275 621*276 621*277 621*278 5. Manufacturers' drawings of Turbines in Waste Heat Boiler House* Drawing No. Manufacture Service Number of Turbines C-10075 C-10078 IE106100 IE106133 LD106808 RIll*7l*93 X619821* Terry Steam Turbine'Obi Terry Steam Turbine Co* Worthington Coip* Worthington Corp* Worthington Corp. Worthington Corp* Elliott Co. Service Vet*r, Puap Driver Emerg. Make-up Water, Puqp Drive I* D* Fan Drive F. D. Fan Drive Boiler Feed, Pump Drive Condensate Supply Prop Emergency Generator 1 1 3 3 2 1 1 6* Manufacturers' drawings of Tanks and/or Equipment in Waste Heat Boiler House: Drawing No, Manufacture Description 1!?0107 150189 0186A25 Fll*8ll*2A Cochrane Division Cochrane Division Stacey Mfg* Co* Cochrane Division Flash Tanks Flash Tank Condensate Tank Jet Tray Deaerator KEN 010784 Sub-Contract No* 711|8-lti85 EXHIBIT "B" ITEMS TO BE SUPPLIED BT THE CONTRACT CR 1. The following pre-formed, single layer, calcium silicate, with 6 or 8 ounce factory applied canvas jacketed insulation for straight run pipe in steam service of 165 pounds at 500F. will be furnished, at the Contractor's warehouse, to Sub-Centreeter: Pipe Size Lineal Feet Thickness Hi" 12" 8" 6" li" 3" 2" lk" Ik" 1" 3/lin k" 1,800 1,200 660 120 2,U00 3,500 6,U80 7,000 600 5,200 1,500 1,800 3" 3" 2^" 23g" 2" 2" lk" lk" l?s" lk" lk" 2. Electrical power, ItliO volt 3 phase, 110 volt single phase at Contractor's distribution panels. 3, Potable water at area or areas designated by Contractor. k Sanitary facilities as located by Contractor. 5. Water required for the work at points designated by the Contractor. 6. Furnish and Install in the Waste Heat Boiler House (through Babcock St Wilcox Coapany and/or other sub-contractors to Contractor/Owner) * (a) Insulation and lagging of Boilers #1, #2 and #3 and all vessels and equipment furnished by Babcock St Wilcox. (b) Insulation of all ducts, stacks, and breeching. (c) Insulation and lagging of all forced and induced draft fans. 7* Furnish Insulation and lagging materials for the twelve (12) turbines listed under Item No. U of Exhibit "A" (Installation of Insulation by Sub-Contractor). KEN 010785 f Sub-Contract No. 7lU8-Ui85 EXHIBIT "C" GENERAL WORK SCHEDUIE 1. It is anticipated that Sub-Contractor can commence field work on/or about April 17, 1967, and that subsequent work will be scheduled by Contractor as the systems or parts thereof are rd. eased for insulating. 2. It is further contemplated that the work will proceed on several systems concurrently, as programmed by Contractor, and Sub-Contractor shall "man" the work in accordance with priorities established by such programming. In this connection, it is assumed that the work will proceed intermittently, with several move-ins required prior to completion. 3. Completion dates for systems and/or sub-systems will be established by Contractor as required by the testing and operating schedules agreed to by Owner. In this connection, close coordination with Contractor shall be required of Sub-Contractor in order to achieve a realistic work sequence to meet such dates. li. Completion date for the work is scheduled for November 3, 1967. KEN 010786 rn Sub-Contract No* 711(8-11(85 EXHIBIT "E" ( SPECIAL PROVISIONS 1. The following Special Provisions (la, lb, 1c and Id) relate to Condensation Item No. 1 - Lund Sum Amount for Waste Heat Boiler House Insulation! (a) It is mutually understood and agreed that the perimeter of the Waste Heat Boiler House agrees with the limits of the Dravo Cozporation design contract as set forth on Bravo drawings incorporated in Exhibit "A" hereof, with the following exception* The note on Bravo Drawing No. 621(178 pertaining to the design perimeter of Elevation rLSU'C" conflicts with the elevations of the insulation work shown on Bravo Brewing Numbers 62U2U0 and 62U21&. This conflict is hereby resolved by directing, by this reference, that the latter two drawings govern except that the 2n Fuel Oil Return from the Slab Furnace shown on Drawing Number 62ii2li0 is not to he insulated under this Sub contract. (b) It is mutually understood and agreed that the first fourteen (lU) drawings listed under Item No. u of Exhibit "A", Drawing Number 621177 through Number 621(191 are "General Arrangements", for reference only, and that dimensions of the work within the Waste Heat Boiler House are shown on the Bravo drawings listed under Item No. hi also Item No. 5 and 6 of Exhibit "A"; as amended herein. (c) It is mutually understood and agreed that The Work includes furnishing and installing insulation on the three (3) Fuel Oil Heaters, Type No. 1U-10-3K30, manufactured by the American Scback Co., and shown on Contractor's Drawing No. 621(238 (621(183 for reference only). (d) It is mutually understood and agreed'that Item No. 2 of Exhibit "A", the Dravo Insulation Specification, is hereby modified as follows: Wherever manufacturers are named in the Dravo Specification, these shall be construed as a reference and guide to other manufacturers' equivalent products. The Sub-Contractor is restricted to furnishing insulation which is manufactured by one of the manufacturers named in Kaiser Engineers Specification No. 711(8 (5-5) which is Item No. 1 of Exhibit "A". 2. The following Special Provisions (2a, 2b, 2c, 2d and 2e) relate to Compensation Item No. 2 - Estimated Amount for Hot Strip Kill Insulation, other than Boiler .House, per Unit Prices of Compensation Annex "A", Sheet Nos. One through Seven: KEN 010787 I ..... - ,, JU*. EXHIBIT "E" -2- Sub-Contract No. 7lU8-ll:85 2. continued: (a) It is mutually understood and agreed that it is the primary Intent under Compensation Itan No. 2 that Sub-Contractor shall install on the 165# Steam Line the quantity of Owner-furnished piping insulation set forth in Item No. 1 of Exhibit nBn hereof, and shall furnish and install all necessary insulation materials for fittings, valves, etc., insulating cement for closing laps, sising (lagging adhesive and preparation for painting by others), tie vires, bands expansion joints, insulation supports, metal jacketing, and all other materials, as required for proper installation thereof. It is further intent of this Sub-Contract that Sub-Contractor shall furnish and install all other insulation, anti-sweat protection, metal jacketing, weather-proofing, and personnel protection for systems requiring such materials, all as shown on the drawings, as described herein, and as directed by the Contractor, for the Hot Strip Mill and its ancillary facilities. (b) It is mutually understood and agreed that the drawings and Annex "A" furnished herewith are for the express purpose of generally describing the systems involved, illustrating conditions at the various elevations giving details pertinent to the work and information required to develop a unit price. They are in no way to be construed as being the extent of the work or limiting the work. The Sub-Contractor will be furnished drawings approved for construction as they become available. (c) It is mutually understood and agreed that the systems referred to herein include, but are not limited to, (1), steam systems and sub-systems, 0 p.s.i., 10 p.s.i., 50 p.s.i., 165 p.e.i., 280 p.s.i. and h2S p.s.i., including supply and return headers, risers, service drops, steam tracers, valve boxes, heat-exchangers, traps, and where required, condensate returns, flaBb-tanks, condensate,tanks, emergency water storage tanks, deaerator tanks, steam atomising piping, and other miscellaneous systems; (2), Lube oil systems and sub-systems, where indicated, including lube screw-downs, pedestals, service drops, headers and risers, reducing stations, and storage tanks; t3),' Horgcdl systems-and;;pub-systems, where indicated except in the oil cellars, including supply and return lines, branchfeeders, pumps and by-passes, headers, risers, and service drops) (10, Fuel oil systems and sub-systems, where indicated, including supply and return headers and utility drops; and (5), All other systems in which the operating temperatures of that particular service approach the dew-point, resulting in a condensation problem-- such systems to receive anti-sweat protection only in the areas designated by Contractor. ken 010788 EXHIBIT "E" -3- Sub-Contract No 711:8-11:85 2. continued: (d) It is mutually understood and agreed that measurement for payment will be per lineal foot for pipe insulation, weather-proofing, and anti-sweat protection and per square foot for insulation on equipment and vessels and for metal jacketing, complete and in place, in accordance with the specifications and drawings. Linear measurements will be made along the center line of straight runs and over the insulation outside of all bends, and will include all insulated valves, flanges;- tees, ells, and other fittingB. Metal jacketing will be measured per square foot, in place, without allowance for laps. The area of pipe jacketing will be the product of the measured circumference of the finished jacketing and the linear measurement thereof, taken as above. Measurements of area will be made over the outside of the insulation on vessels and equipment and will exclude all uninsulated areas in excess of one square foot. In addition to the linear measurements above, the following table of equivalence for insulated fittings and valves will be allowed: Each pair of flanges - 3 feet Each mitered ell-exclusive of flanges - 2 feet - preformed ells shall be used, where practicable. Each Tee-exclusive of flanges - 2 feet Each cross-exclusive of flanges - 2 feet Each valve-exclusive of flanges - 2 feet Each valve bonnet - 3 feet Bends exceeding radius of long radius ell - 1.5 times the linear measurement. (e) It is mutually understood and agreed that the Estimated Amount of $170,71:9.50 for Compensation Item No. 2 was derived as follows: ("Sections" referred to are shown on Compensation Annex "A" pages One through Seven): (1) Sub-total of lith Column of Section III (Install Owner-furnished Pipe Insulation for 165# Steam) $ 1:6,730.20 (2) Sub-total of schedule at bottom of page 2 - Section III (Furnish & Install Pipe Insulation for 165# steam) $ 8,058.20 (3) Total of Sub-totals of lith Column of Sections I, II and IV through VIII (Furnish & Install Pipe ' Insulation) $ 89,989.00 (li) Total of Sub-totals of 8th Column of Sections I through VIII (Furnish & Install Metal-Jacketing) $ 7,150.U0 (5) Sub-total of lith Column of Section X (Furnish & Install Insulation on Equipment, Vessels and Machinery) $ 6,281:.50. KEN 010789 r EXHIBIT "E" -it-- o Sab-Contract No. 711*8-11:85 2(e) continued: (6) A116vance:for Section H (no specific quantities or Sub-totals estimated for any column) $ 5>298.30 (7) Allowance for table of equivalance in Special Provision No. 2 (d) of Exhibit "E" (flanges, ells, tees, crosses, valves, and bonnets, and bends) - approximately $% of (1), (2) and (3) * $ 7,238.90 TOTAL ESTIMATED AMOUNT $170.71:9. $0 The above Total Estimated Amount does not reflect estimated total prices or allowances for the following categories of Unit Prices shown under Compensation Annex "A", but which Unit Prices are nonetheless applicable to whatever quantities are developed from approved for construction drawings to be issued pursuant to Special Provision No. 2a: (a) Anti-Sweat Insulation (quantity presently indeterminable but will be relatively insignificant) (b) Weather-Proofing (quantity presently Indeterminable but will be small amount) (c) Insulation of Equipment, Vessels and Machinery in accordance with Sections IV through IX Contractor does not guarantee the accuracy of any of its estimated quantities or allowances,' and Sub-Contractor agrees not to plead misunderstanding or deception because of any such inaccuracy. It is mutually agreed that the Unit Prices are firm and not subject to adjustment irrespective of variations between actual quantities and estimated quantities. 3. It is mutually understood and agreed that Contractor and other sub-contractors, will be working in the areas involved in this work and that these areas will be congested. In this connection, storage space adjacent to the work site will be limited and such storage must be closely coordinated with Contractor. 1*. It is mutually understood and agreed that Sub-Contractor will provide all required off-loading, handling, hoisting, material and equipment protection, to include weather protection for material in outside storage, rigging, scaffolding, picks, ladders, and all other equipment necessary for the proper installation of the work. 5. It is mutually understood and agreed that "the value of work done and materials furnished by Sub-Contractor*1 as referred to in Article 18 'Terms of Payment" of the Sub-Contract General Terms and Conditions shall be construed to include the actual purchase cost of materials required under the Sub-Contract which are delivered and unloaded by Sub-Cbntractor during each month irrespective of whether the material is installed in such month. KEN 010790 KEN 010732 ID6+iT-/J0+i