May 4, 1973 Status - PCE Environmental Control Progi-am
J. R. Savage - B2SL
COMPANY CONFIDENTIAL
CC: G . L. Bratsch
W. C. Engman M. R. Foresman P. E. Heisler G. A. Hippe P. B. Hodges - E1SF A. E. Leisy/J. Grant D. C. Otto W. R. Richard - T3A
I. PCB Level in Sewers
April losses at .95 #/day from operating departments and the incinerator are 10$ lower than last month, In spite of continued heavy rainfall. The Waste Treatment influent losses of 7.5 #/day is 30$ lower than last month. The effluent remained about the same at 5.9 #/day.
A. Aroclor Department. PCB losses from the department increased to .77 #/day from .56 #/day of last month.
B. Incinerator decreased to .11 #/day from .^9 #/day of last month. High losses of last month were due probably to start-up.
C. Waste Treatment Plant. Influent losses averaged 7.5 #/dat about 30$ lov/er than last month. During this period the Rip Track washed 22 PCB tank cars.
D. Waste Treatment Effluent. The level of losses remained about the same at 5.9 #/day.
II. Project Status
*
''
Project 3956 "Alteration to HC1 Distribution System". EDC now 6/1/73.
Project M38 'Reduce Water Flow to Sewer". Design complete
but no EDC as yet for installation.
Project 8020 "HC1 Off Gas Scrubber".. Equipment is on order, detail design EDC 6/15/73. No EDC as yet for installation.
IN tO RCV 11-65
DSW 353177 STLCOPCB4085368
J. R. Savage ' Status - PCB Environmental Control Program
Pg 2
5/V73
WGK
III. Program Status
.
..
1. HC1 Off-gas". When the C/S department was down
for extensive repairs, HC1 was sewered after
passing through the C/S scrubber. The waste
.
water analysis from Department 217 remained at the
lower limit of detection of PCB while this was
in progress. It is however impractical to operate
in this way for short, unplanned, periods making it
necessary to continue co-ordination of the
production of the two departments. The sewering
valve opened 113 times due to overpressure.
2. Blow Tank Off-gas. No change pending completion of Project 7^38.
3. Rip Track Washes. 22 cars were washed during the month and the accumulation in the settling tank
increased to 2,500 gallons. Effluent analysis from this tank indicates continued good control.
. Department sampling has reverted to continuous sampling following a mechanical problem with the proportional to flow instrumentation.
C. F. Buckley