Document X7rqLMgZ4nwNj6r7w81xBbjax

ABD00081206 * To: P. J Kober Interoffice Communication From: Date: Subject: K. W. Birck January 14, 1988 Subpart V Compliance Project Training VIS1A Installation of the Subpart V Compliance project has been completed. The next and final step is operator training which must be completed by 01-31-88. Attached is an outline of the information that will be discussed with each vinyl operator, chief lead and supervisor. They will be asked to sign a training sheet signifying that they have been told and understand each item on the outline. I will coordinate the training schedule with JME. If you have any questions or comments, please contact me so that they can be included in the training. nrs attachment cc: JF, JWW, RAF, DFJ, JME, VEM, JEN, TFL File: 8.1.10