Document X7Lbe0Y9ZYRx934y3Jko0616K
SAFETY - A. H. Sather
Occupational' Injuries
Injuries Treated
1979 March
1979 Year-to-Date
1978 Year-to-Date
First Aid Medical Cases Lost Workday Cases (days) Lost Time
Injuries By Department
0 1
1(4) 0
6 1
1 (4) 0
12 1 0 0
Vinyl Operations Compound Operations Maintenance Laboratory Receiving and Warehouse Office
14 00 02 00 00 12
0 C 5 1 0 0
Injury Types
Cuts and Abrasions Eye Injuries Bums Bruises Sprains Strains Other
12 02 02 02 12 00
5 n
3 3
o o
Of the two doctor cases which occurred during the reporting period, one occurred while a compound utility was in a stable kneeling position during a propane fire training exercize. The resultant back muscle strain and subsequent light duty requirement was probably due to tension related overexertion as this was the injured's first fire training experience; the other injury (laceration and bruise) occurred when a vinyi operator caught his right thumb between a pipe wrench handle and a centrifuge gearbox housing while changing a shear pin.
As of March 31, 1979, the Plant operated 310,407 manhours or 237 days without a disabling injury.
On March 22, 1979, the Plant experienced its first medical case of 1979. This terminated a record of 166 days operating time without an injury which required medical treatment.
Plant Fire Trainirig
All plant fire training was initiated early in the reporting period. Training was temporarily suspended in order that a program on lifting be developed and completed in the plant. Fire training will resume upon completion of the lifting training program. A total of 121 employees have received training.
DTH 000043672 *
Lead Standard
The plant progress with regards to the OSHA Standard on inorganic lead exposure continues per the plant's Compliance Plan. A sampling plan was developed and circulated for review and comment in early April. An AFE was submitted to upgrade the color weigh room and to improve the ventilation system per the recommendations of a ventilation consultant - John Kane, of Louisville, Kentucky.
Several provisions of this standard have been stayed by the U.S. Court of Appeals for the District of Columbia. Provisions which remain in effect include: Permissible Exposure Limit, Exposure Monitoring, Respiratory Protection, Protective Clothing and Equipment, Housekeeping, Industrial Hygiene Facilities and Practices (except renovation and/or construction of new facilities). Medical Surveillance and Removal, Training, Recordkeeping, and Observation of Monitoring.
VCM Compliance
Activities with regards to cpmpliance include: Completion of Annual Medical Surveillance for all employees (including 138 blood lead tests), and routine personnel monitoring.
A total of sixty-seven (67) samples were taken with six (6) indicating exposures of 1.0 ppm or greater. The distribution of results and a brief explanation of overexposures is shown below.
Range (ppm)
Number
Percent
0.0 - 0.5 0.5 - 1.0 1.0 - 5.0
5.0+
55 82.09 6 * 8.96 4 5.97 2 2.98
67 160.00
Of the six (6) overexposures, one occurred while a mechanic was working on a dryer centrifuge, one to a lead operator in the control room (see note below) and the four (4) remaining are under investigation. Two (2) of the employees whose overexposures are under investigation have indicated that they wore a respirator during the monitoring period.
Due to transcient contamination of fresh air to the control room by VCM, an electrically operated damper has been installed in the fresh air inlet duct. .Whenever the Honeywell monitor senses VCM in the control room above 5 ppm, an alarm is activated and an operator manually operates the switch to close the damper.
DTH 000043673
vinyl - E. L. Kieschnick
March had 31 .accounting days (Y.T.D. is 90 accountingdays). .
Production
Month
Y.T.D.
Standard
1. Total Production, MM #*s 2. Production Rate, M #'s/C.D. 3. Charging, Rx B.A.'s/C.D. 4. Total Charges
5. Reactor Stream Factor, % 6. Drying Rates, Average #'s/Hr. 7. Dryers, Stream Factor, %
26.3 849
22.1 686
90.8 5698
88.7
69.9 777
19.8 1781
85.5 5406
85.5
The vinyl department production increased from 22.4 MM lbs. in February to 26.3 MM lbs. in March. The increase in production is a result of increased productivity from the reactors due to items described below. The dryer per formance continues to be good.
a
The increase in production is primarily a result of a reduction in chem'wash and swirl frequency on the 5425 and the elimination of swirl in the production of 5385.
Reactor downtime was taken during the month to:
1. Brush the condensers on D-30Q, D-400, D-500, and D-600. The condenser was brushed on D-300 and D-500 while the reactors were down for a seal change and agitator gearbox repair, respectively.
2. Remove a coarse batch from D-600 reactor. The problem was traced to the suspending agent charge system and has been resolved.
Resin Quality Summary
Resin Type
Prime Pounds
"BC" Grade
Grade
% of Total Production
5305 5385 5425 5465 Sifter Overflow
1,269,250 ' 21,262,707
2,858,485 496,620
42,750 74,250 40,350
274,660
0.16 0.28 0.15
1.04
TOTAL
25,887,062 157,350 274,660
1.63
Quality performance for the month of March was 98.37% customer grade with 0.59% "BC" and 1.04% "H" grade. Items completed during the month to improve quality were:
1. Installation of air filter in the air utilized to aerate the 5425 blend tank. This has improved the quality of air and removed a significant contamination source.
DTH 000043674
2. Modification of the dryer operation procedures limiting the maximum inlet temperature. This has not only lowered the contamination but has also reduced'the. dryer cleaning frequency.
3. Installation of an improved blend tank aeration system in the blend tanks
utilized for 5305 production which will lower the residual VCM in the
dried product,
>
The variable cos.t variance for the vinyl department was $49.9 M with $49.6 M due to price and $0.3 M due to efficiency. The major price variance was $64.0 M on VCM. The only major efficiency variances were ($40.0 M) on VCM and $18.7 M on combined initiators.
The raw material requirement for the month was 1.02981 pounds VCM/pound PVC versus a 1.01960 standard. Four coarse batches in the old module and a severe foaming problem from 742 reactor were the primary contributors. A modification to the suspending agent charge system in the old module will minimize the potential for coarse batches. The foaming from 742 is a result of shell'side fouling on the 742 condenser which will be chemically cleaned the first week in April',
DTH 0000436
COMPOUND - C. R. Miller
.March had 31 accounting days.
Compound Production
Month
#'s/Day
Y.T.D.
Line I, M Pounds Line III, M Pounds Total, M Pounds
1,584 3,594 5,178
63 116 167
4,130 8,208 12,338
Line I operated twenty-five days during the month at an average rate of 63 M pounds per day. Major items affecting productivity were number of product changes. (20 products - 43 hours total), maintenance on the Banbury conveyor (12.4 hours) and a power outage on the control panel (10.4 hours). Pro duction included new compounds 35031 for ITT Automative and 34431 Black for Pirelli Cable.
Line III operated thirty-one days averaging 116 M pounds per day. The only major item affecting productivity on Line III was the number of product changes (14 products - 28.2 hours).
Quality performance for flexible compound was 1.9% of which 76% was due to mill scrap. The remaining off-grade consisted of 24 M pounds of 18031 Clear Blue for gels and resin contamination. "BC" production for the month was 0.9%.
The raw material requirement for flexible compound was 1.00773 pounds raw materials/pound of compound versus a 1.01296 standard (Y.T.D. is 1.00789).
The variable cost variance for compound was $29.8 M with $16.3 M due to price and $13.5 M due to efficiency. The only major efficiency variance for the month was $19.9 M due to combined colors. The only major price variance was $27.9 M for Synpron 1438.
Dry Blend
Month
#1 s/Day
Y.T.D.
Total Production, M Pounds
1,483 212 12,669
Dry Blend operated seven days during the month at an average rate of 212 M pounds per day. Dry Blend production was limited by dry blend sales and inventory control programs. Production during the month included the reprocessing of 41 M pounds of off-grade dry blend. .
Quality performance for the month was 100% customer grade. Reworking of off-grade material at a 3% level continued through March.
*
The raw material requirement for dry blend was 1.00406 pounds raw materials/ pound of dry blend versus a 1.00321 standard (Y.T.D. is 1.00301).
The variable cost variance for dry blend was ($38.6 M) with $2.5 M due to price and ($41.2 M) due to efficiency. Variance due to product mix was ($14.7 M). The large efficiency variance reported reflects an error in the end of the month area inventory. A correction will be made next month.
DTH 00004367
Plasticizer
Month
#1 s/Day
Y.T.D.
Total Plasticizer, M Pounds
936 62 .2,971
The plasticizer unit operated- fifteen days during the month at an average of 62 M pounds per day. Plasticizer production consisted of DOP, 610-P and TOTM plasticizers. VRP production for the month was 84 M pounds.
The raw material requirement for plasticizer was 1.11616 pounds raw materials/ pound of plasticizer versus a 1.10482 standard (Y.T.D. is 1.13240).
The variable cost for plasticizer was $1.2 M with ($1.6 M) due to the price and $2.8 M due to efficiency. The only major price variance was ($10.3 M) for phthalic anhydride. There were no major efficiency variances for the month.
* DTH 000043677
MECHANICAL - S. J. Vincent
Vinyl r Area- I
The large reactor condensers that were cleaned this month were all in the old module. They were D^-300, D-400, D-500 twice, and D-600. Some of the other work completed in the old module follows. All rupture discs were replaced and the relief valves tested on D-300, 400, 500, and 600. The chem wash spray heads for D-400, 500, and 600 were removed and cleaned. The reactor seal on D-300 reactor failed and had to be repaired. Several reactor valves were replaced on D-400 and D-500 reactors. The valves replaced were the condenser valve, the recovery valve, the evacuation valve, the main dump valve, and the VCM charge valve on D-400 and then on D-500 the chem wash valves to the reactor and the condenser valve were replaced. The fresh VCM receivers level device was calibrated. The control instrumentation for D-500 was calibrated and they were calibrated twice on D-600. There was a coarse batch in D-600 reactor at the end of the month with a significant accumulation of resin in the reactor. Extensive work was required to prepare, clean, and place this reactor back in service.
There were no large reactor condensers cleaned in the new module. The rupture discs were replaced and the relief valve was pressure tested on 741 reactor. The chem wash spray head for 744 was removed and cleaned. The evacuation, recovery, and catalyst valves were replaced on 741 reactor. The evacuation and recovery valves were replaced on 744 reactor. A major problem developed with the new unit seal oil system. The flow could not be maintained through the filters with the gear pumps subsequently over heating and failing. The seal oil system was bypassed and service water was placed on all the seals on March 19. Several panel lights were repaired in the control room. The Sweco exhaust fan motor was removed and repaired.
The vinyl dryers continue to operate satisfactorily after the installation of the new anti-chatter devices. The rotating assembly and gearbox were replaced on number two dryer. The units removed on changeout were rebuilt. The exhauster drive motor was replaced on number two dryer, also. Two dryers were given PM checks. The trunion roller and bearings were replaced on number four. A new process sampler was also installed on number four dryer sifter. Electric power was installed on a new vibrator for number six chute. The motor on one of the small blend tanks was repaired. Several silo level indicators and blend tank level transmitters were repaired and calibrated. The torque controllers on two'dryers were calibrated. A safety guard rail was installed on the roof around the collectors in the V-10 dryer building. The installation of the day collector handrails was completed for all dryers.
\
One of the emission recovery system compressors was rebuilt with a new shaft and mechanical seals. Mechanical seals were replaced on three recovery compressors. One of the old module vacuum pumps was dismantled and cleaned.
Motors were removed and repaired on one vacuum pump and two compressors in old recovery system. Two of the 490 Corken compressors were rebuilt. The mechanical seals were replaced in both of the VCM transfer pumps at the tank
farm. The suction screens were pulled and cleaned twice on both VCM charge
pumps in the old module. The mechanical -seals wer.e also replaced in .the old
' ''
' DTH 000043678
unit RVCM pump and one of the slurry pumps. All the valves going into the "A" vacuum pump were replaced to try to define continuing problems in this . recovery system.
Both of the tecoyery condensers in the old unit were cleaned. A new drain bypass line was installed in the emission recovery system. The knockout drums and receivers were opened to remove resin restrictions. Numerous rupture discs continue to be replaced throughout the unit. A three way control valve was replaced on the incinerator. All Honeywell monitoring points were checked and verified.
Compound, Dry Blend, Plasticizer, and Storage Silos - Area II
The cooling water piping to the Line III product blower was revised. The top roller on the Line III scrap conveyor was replaced. The mechanical joints on the two laboratory mills had to be rebuilt. The dump valve on one of the line I blenders was repaired. A steam leak list was developed for compound and the leaks corrected. The motor on one of the dicers was removed and repaired.
The service water piping to the dry blend basement was rerouted. The service elevator corftro'ls were relocated for the installation of the new access ramp for raw materials. The dry blend basement sump pump was rebuilt. A vacuum cleaning connection was installed on the' screener deck. A new stub shaft was installed on the drive end of one of the blenders. During the dry blend shutdown, five motors were also pulled and repaired.
The two plasticizer blowers were rebuilt. The mechanical seal was replaced in the phthalic anhydride transfer pump. The catch tank was revised to hold filter socks. The rupture disc was replaced on one of the reactors. The inert gas generator installation was completed. An air purging system was installed on the alcohol unloading lines. A coil leak in one of the reactors was also repaired.
A new water line was installed to the truck scale. The fresh air piping to the VCM unloading rack was revised. An engine was replaced in one of the plant fork trucks. The new silo sampler was installed on one of the truck loading resin silos. Several painting projects were completed. The manway covers were repaired on three large silos. One knife valve was repaired.
Utilities
. The air dryer heater elements were replaced in one of the V^IO air dryers. One of the rental diesel air compressors was returned to the supplier. An air filter was installed on the air supply to one of the large blend tanks.
All the plant air receiver relief valves were tested and also the relief valVe on the water softeners. A new water meter was installed on one of the main city supply lines to the plant. The air conditioning and refrigeration program the history, and equipment vibration program, and the lubrication program are continuing. A sonic testing device is being used to develop data for a leak detection program primarily for process valves.
Nineteen valves were rebuilt for the vinyl unit. Several tools were repaired. Several bicycle repairs were completed. The installation of the new steam fired vaporizers is continuing with an estimate of completion.in April.
DTH 000043679
New cable and a new motor were installed on the polishing pond aerator. Number six air compressor motor was removed and repaired. One of the water.valves .in the boiler system was rebuilt..
Planning
The planners work involved processing 42 inyoice registers and processing 31 invoices for payment. Planning work and material was ordered for 31 separate projects. The change over of all backlog work to th.e new Maintenance Management System was completed. Supervisory coverage was also provided by the planner.
Miscellaneous
There were 520 maintenance, 23 revision, no safety, and 68 service to operations work orders received during the month. The following is a breakdown of maintenance work orders by priority;
E A B C Shift Mechanic
TOTAL
Number
262 160
9 56 33
520
Percent
50 31
2 11
6
100
During this reporting period 625 maintenance, 36 revision, 4 safety, and 91 service to operations work orders were completed. 30.5% of the time was spent on non-scheduled work.
Preliminary work has been completed for implementation of the MMS at Aberdeen. Supervisory meetings were conducted to familiarize employees with the program. The official changeover to MMS will occur on April 1, 1979.
. DTH 000043680
PERSONNEL - J. L. Carter EMPLOYMENT During March there were two temporary new hires, Debra Lindsey, Steno Clerk and Clyde Rhea, Temporary Contractor Guard. TO/FROM LEAVE OF ABSENCE None. TRANSFER/PROMPTION None. RETIREMENTS None. TERMINATIONS. Two hourly employees, Willie C. Burley, Painter-Insulator-Carpenter "A", and Percy Carothers, General Helper. DEATH/DISABILITY None. OTHER - CASUAL LABOR There was one (1) casual labor employee on payroll during this month. Total hours worked were 55.75.
DTH 000043681
. Aberdeen, Mississippi
March 1979__________ MONTHLY PERSONNEL REPORT
Salaried Employees Hourly Employees Total Employees Employees (-Hourly)
. 72*. 161 233*
.
Minority Employees -
Salaried Hourly Total
3 63 66
4% 39% 28%
New Employees Terminations
-02
Hourly Min. Hired
-0-
% Min. Hired
-0-
Hourly Min. Term.
-2-
% Min. Term.
100%
DEPARTMENTS PAR # EMPLOYEES MIN. EHP. % MIN. NEW HIRES YTD TERM. YTD TURNOVER
YTD
Warehouse Gen. Plant Maintenance Laboratory Compound
_S_ 10M22-- 18_
9 11 45 22 38
2
22% 0
0 0 *0 0
0
5
45% 0
0
13
9%
27%
7
15% 0
0 1 1 2%
2%
3 14 0 0 0 0 0 0
30
79% 0
0 00 0
0
Vinyl Plasticiser
32 4
32 4
13 41 0 0 0 0 0 0 3 75 0 0 0 0 0 0
Number of Applicants:
Month
3 Year to Date 3.
APPLICANT BREAKDOWN:
# Minority
-0- % Minority
-0-
*6 Female ______2
% Female
66.6%
*Includes one Co-Op Student and two other temporary employees.
Hires (Hourly) :
Month -Q-
Year to Date
Terminations (Hourly) :
Month
2
Year to Date
Overall Turnover
Projected Annual Turnover
_q. 4 13%
DTH 000043662
0
PROCESS ENGINEERING - J. R. McCrimon A* Specialty Compound Line
The plant is continuing to work with Crawford and Russell andCED on the mechanical design of the project. Construction began on March 20, 1979. Current estimated mechanical completion date is September 15, 1979. B. Fire Water Revisions - Phase I Mechanical Engineering for the project is continuing. A request for engineering services from Texas Automatic Sprinkler Co. is being prepared. C. Propane Vaporizer Replacement Mechanical installation of the project was begun in late February. Project completion is still scheduled for mid April, D. Plasticizer Exposure Abatement Mechanical Engineering is continuing. E. Charge Water Heating Improvement Installation is underway and completion is scheduled for the end of April. F. Silo High Level Alarms A prototype was installed on silo 479 and tested. Problems with the Ronan alarm panel in the control room ard being investigated. G. Plant Dryer Debottlenecking 1. Centrifuge Slurry Feed Control
The new one inch control valves have been installed on all the dryers except Dryer No. 7. 2. Remote Dryer Lighting Equipment has been ordered. Mechanical Engineering is continuing. Projected completion is projected for the end of July. 3. V-10 Transfer System Mechanical Engineering is proceeding on the mechanical design for this project. Equipment is'on order. Project completion is scheduled for the end of July.
. DTH 000043684
H. Silo Isolation Valves The valves for this project are on order.
I. Plant Yield Study The use of the continuous sampler to determine the amount of resin in the effluent to the plant waste treatment system is continuing.
J. Automatic Plasticizer Weighup System The process design for this project has been modified to incorporate changes in the sequencing operation. The need for these changes are necessary to better define tie-ins to the existing system. Panel delivery is scheduled for the end of July.
K. QMS Addition System The process design for an automatic OMS addition system for the new module was completed and reviewed. A cost estimate will be made for the project.
L. Emission Recovery System A process design for the installation of an additional vacuum pump and to improve liquid control in the system was prepared. A definitive estimate is being prepared by the Mechanical Engineering Group.
M. Plant Air System A process design for an additional air compressor 'is being prepared.
, DTH 000043685
ENVIRONMENTAL HEALTH - J. R. McCrimon
I. Particulates .
The exhausts from two of the resin dryers were sampled for particulates.
The rental vacuum cleanup system has been evaluated and found to work well. A purchase order was issued for the unit. Engineering is underway to add options to the unit.
II. Water
BOD and COD levels were within NPDES permit limitations in March. An application for renewal of our current NPDES permit was submitted and storm water runoff sources were included.
PED personnel were in the plant to run a source sampling program to define flow rates and loadings from the various areas of the plant. This data will be used to determine the effect of increased plasticizer production and resin expansion on the plant waste water treatment system.
Methods of eliminating the pond irritant are being investigated. Aerators operated 24 hours per day most of this period.
III. Vinyl Chloride
PED personnel were in the plant to discuss methods to improve EPA compliance.
The plant received a ''show cause" notice from the EPA concerning the two VCM releases from D-300 reactor which occurred in February,
A control room isolation damper was installed in the fresh air duct to the vinyl control room.
In-plant emission testing and leak checking are continuing as specified in the Compliance Manual.
The EPA semi annual report was submitted as required by the regulation. Efforts have been intensified to come closer to compliance 100% of the time.
The Engineering and Work Practice Control Plan was updated and reissued.
IV. General
A permit to construct the specialty compound line was granted by the state and construction is in progress.
DTH 000043686
Flow GPM
Jan. - Ave. Max.
788 948
Feb. - Ave. Max.
756 773
Mar. - Ave. Max.
669 760
Apr. - Ave. Max.
May - Ave. Max.
June - Ave. Max.
July - Ave. Max.
Aug. - Ave. Max.
Sdpt. - Ave. Max.
Oct. - Ave. Max.
Nov. - Ave. Max.
Dec. - Ave. Max.
TABLE I
WATER COMPLIANCE WITH
NPDES PERMIT PARAMETERS
BOD PPM LB./DY.
COD PPM LB./DY.
Sus. Solids
Diss.
PPM LB./DY. o2-
26 246 63 589
37 307
94 781
19 170 6.9-7.3 31 279
30 272 43 380
17 134 24 184
73 656 95 840
61 490 81 621
27 241 6.9-7.9 34 315
26 214 6.9-7,6 45 367
NPDES - Ave. Max.
-
32 387 43 520
- 1390 - 1940
- 605 - 909
6.0
ph 7.5-8.2 7.7-8.0 7.3-7.9
6.0-8.5
% , DTH 00004368r7
ENERGY CONSERVATION - V. L. Thornhill
I. Plant Operations
Total energy consumption for March was 112.1 MMM BTU's. The energy consumption per pound of product increased from 3265 BTU/lb. to 3308 BTU/lb. in March.
II. Plant Energy Conservation Program
A. Steam Leaks
18 of 22 reported steam leaks were repaired during March.
B. Charge Water Heating Improvements
Mechanical design is continuing. Installation of equipment will begin in April.
C. Boiler Burner Replacement
Fabrication and testing of burner units by the vendor was completed in March with shipment pending.
DTH 000043688
ENERGY CONSERVATION DATA
ITEM
1978
1979
Production, MM Lbs.'
March
March
Resin Dry Blend Compound Plasticizer
19.3 3.5 2.9 0.5
26.3 1.5 5.2 0.9
TOTAL
26.2
33.9
Natural Gas
Consumption, MSCF Conversion, BTU/SCF Energy Consumption, MMM BTU
47758 1020
48.713
61659 1020
62.892
Electricirty
Consumption, MM KWH Conversion, BTU/KWH Energy Consumption, MMM BTU
Propane
4.262 10000 42.620
4.9243 10000 49.248
Consumption, M Gal. Conversion, BTU/Gal. Energy Consumption, MMM BTU
6.60 92000
0,607
0 92000
0
Total
Energy Consumption, MMM BTU Energy Consumption , BTU/Lb.
91.940 3509
112.140 3308
Boiler Operating Data
No. 1 No. 2 No. 3
..
Stack Temp.
1978
1979
389 425 412 406 428 452
Avg. % Excess Air
1978
1979
115 100 105 110
61 . .115
DTH 000043689
MECHANICAL ENGINEERING - J. A. Dixon
AFE's Submitted, Approved, and Closed
The following AFE's were submitted and approved during March:
AFE No.
Title
Authorized
9539 9549
Laboratory Equipment Safety Equipment
$31,000 $15,000
There were no AFE's closed to field charges or completion reports issued in March.
Design
Bid packages were prepared for insulation on the Propane Vaporizer Project and underground conduit for the Dryer Operation Improvement Project.
Silo isolation valves are on order. All major equipment for the Dryer Operation Improvement Project is on order.
Contracts were let for the concrete work for the Plasticizer Chemical Exposure Abatement and New Compound Line Projects.
Design work is in progress on the following projects: Dryer Operation Improve ment, Resin Silo Debottlenecking, Plasticizer Chemical Exposure Abatement, Fire Protection Improvements, Vinyl Communications System and Office Expansion.
Construction
1. The Inert Gas Generator Project is complete and ready for startup by the manufacturer's representative.
2. The new fork lift ramp is complete.
3. Installation of an electrically operated damper in the control room fresh air system is complete.
4. Installation of the Plant Emergency Siren System is complete,
5. Installation of the Gaitronics Communication System is complete.
6. The API separator was cleaned during the period.
7. The Phthaiic Anhydride rail spur extension is complete.
8. The railroad bed was repaired on the west spur.
9. Work on the following projects is in progress: Dryer Noise Abatement, Propane Vaporizer Replacement, Dry Blend Silo Alarms, Emergency Lighting System,'Charge Water Heating Improvements, Offsite Electrical and Piping for the New Compound Line.
DTH 000043690
(1) Thru February, 1979 Actual Accounting (2) Thru March, 1979
ABERDEEN AUTHORIZATIONS REIWE
MJTH. CAPITAL NO. DESCRIPTION
912b PVC Reactor Capacity Replacement
111
DATE
AUTII.
APPROVED AFE AWT,
(1) (21 FINAL EXPENDED COMMiTED TOTAL EST. TO DATE TO DATE COST COMP.
UNDER (OVER) AUTM. AMT.
EST.
EST. CLOS. DATE
REMARKS
7/8/76 8,5^7,000- S,130,704 8,189,896 .8,189,896
387,104 , 12/78 3/79 Closed to field charges.
t 9276 9286
Relief Valve Vent Containment Additional Slurry Blend Tank
12/10/76
39,000
12/7/76 290,000
34,499 34,499 282.S46 285,823
34,499 285,823
4,501 4,078
12/78 3/79 12/78 4/79
Closed to field charges. Closed to field charges.
9057 Vent Gas Incineration
4/1/77
275,000
275,876 275,876 275,876
(876) 12/78 4/79 Closed to field charges.
9087 Resin Silo Aeration
S/16/77 280,000
242,054 242,336 242,336
37,664 12/78 3/79 Closed to field charges.
9147 Phthalic Anhydride Exposure Reduction 6/30/77
45,000
40,290 44,039
44,039
961 11/78 2/79 Closed to field charges.
9187 9197
Eaergency Reactor Vent Control Dryer Area Noise Abatement
9/29/77 9/29/77
33,000 45,000
26,331 25,004
33,136 32,629
33,136 45,000
(136) 4/79 6/79 0 6/79 9/79
Installation complete. Installation proceeding.
9227 Plant Emergency Lighting System
10/10/77 65,000
46,056 46,122
65,000
0 6/79 9/79 Installation proceeding.
9237 Heated Plasticizer Addition System 10/11/77 37,000
7,628
8,057
37,000
0 9/79 12/79 Installation proceeding.
9247 Farrell Mixer Feeders
11/21/77 47,000
17,599 20,730
47,000
0 6/79 9/79 Conveyors to be installed.
9257 Resin Transfer Debottlenecking
11/16/77 56,000
28,756 43,147
56,000
0 7/79 10/79 Dust collectors purchased.
9267 Dry Blend Production Expansion
11/23/77 200,000
180,159 197,877
200,000
0 4/79 7/79 Installation complete.
9277 Truck LoadingSafety Revisions
11/28/77 16,000
2,495
4,009
16,000
0 6/79 9/79 Installation proceeding.
9287 Plasticizer Yield Improvement Test
12/5/77
6,000
3,544
3,544
6,000
0 4/79 6/79 One test complete.
9297 Automatic Plasticizer-Stabilizer Weighup System
12/14/77 60,000
873 43,718
60,000
0 9/79 12/79 Design in progress.
93G7 Compound Project Conveying Lines
12/14/77 50,000
20,942 22,211
50,000
0 6/79 9/79 Installation proceeding.
90X8 Critical Spare Equipment
1/31/78
63,000
60,855 63,502
63,502
(502) 12/78 3/79 Closed to field charges.
9028 Misc. Items Under $10,000 9038 Maintenance Equipment 9048 Resin Moisture Analyzers 9058 Laboratory Equipment 9078 Misc. Projects Under $10,000 9088 Replacement Inert Gas Generator 9098 New Compound Line
1/31/78
50,000
2/3/78
18,000
2/24/78
17,000
2/24/78
50,000
2/24/78 166,000
3/28/78
44,000
4/17/78 2,050,000
30,510 48,422
48,422
18,213
17,899
17,899
13,148
13,148
17,000
48,617 48,659
48,659
138,545 158,943
1S8.943
29,668 39,870
44,000
737,710 1,422,669 2,050,000
9108 9138 9148
9158 9168 9178 9188
Boiler Burner Replacement
5/12/78
Plant Guardhouse Improvement
8/14/78
Plasticizer Chemical Exposure Abatement
8/21/78
Fire Protection Improvements-Phase I 9/19/78
Misc. Projects Under $10,000
9/21/78
Propape Vaporizer Replacement
9/21/78
Railcar Resin Heel Cleanup System
10/12/78
170,000 19,000
152,000
176,000 59,000
175,000 55,000
9198 Debottlenecking - Centrifuge Anti-Chatter Devices
9208 Spare Recovery Vacuum Pump 9218 Charge Water Heating Improvement 9228 Dry Blend Silo Alarms 9248 Silo Isolation Valves 9258 Dryer Operation Improvements
11/7/78
70,000
12/5/78 12/8/79 12/13/78 12/14/78 12/14/78
14,000 32,000 25,000 25,000 315,000
9529 Miscellaneous Projects Under $10,000 . 2/15/79
125,000
1,183 18,540
2,670
166,789 18,540 92,298
170,000 18,540
152,000
0 36,927
8,411 3,643
15,194 52,770 105,306 41,523
176,000 52,770
175,000 ssiooo
19,374 63,122
70,000
0 3,263
331 0 0
14,633 31,152
4,201 15,589 74,703
14,000 32,000 25,000 25,000 315,000
0 59.183 125,000
1,578 12/78 3/79 Closed to field charges.
101 12/78 3/79 Closed to field charges.
0 4/79 7/79 Analyzers in service.
1,341 10/78 2/79 Closed to field charges.
7,057 12/78 3/79 Closed to field charges.
0 4/79 7/79 Installation proceeding.
0 12/79 3/80
Offsites electrical being installed. Most material on order.
0 6/79 9/79 Burners shipped.
^
460 11/78 3/79 Closed to field charges.
0 7/79 10/79 Site work in progress.
0 9/79 12/79 Engineering in progress by CED.
6,230 12/78 3/79 Closed to field charges.
0 9/79 12/79 Installation proceeding.
0 5/79 8/79 Fabrication of Satellite hopper in progress.
*
0 4/79 7/79 Equipment being installed.
0 8/79 1 1/79 Vacuum pump on order. 0 S/79 8/79 Installation proceeding. 0 5/79 8/79 Prototype installed. 0 7/79 10/79 Valves purchased. 0 10/79 1/B0 Engineerng and purchasing
in progress. 0 12/70 3/HO Twenty-two project:; approved'.
DTH 000043691
MJTtt. EXPENSE NO. DESCRIPTION
9258 Compound Line I Roof Collapse
(1) Thru February, 1979 Actual Accounting (2) Thru March, 1979
ABERDEEN AUTHORIZATIONS REPORT
DATE APPROVED
' Cl)
(2) FINAL
Aim).
EXPENDED COMMITTED TOTAL EST.
AFE AMT. TO DATE TO DATE COST COMP.
UNDER
COVER) Aim). AMT.
EST. EST. ' COMP. CLOS. PATE DATE
REMARKS
12/13/78 44,000 0 0 44,000
0 4/79 7/79 Insurance clain being filed
I DTH 000043692
LABORATORY - R. B. Martin
' CUSTOMER COMPLAINTS
Customer
Product
Type Complaint
No. Status
Resin Rehau
5385
$
Wet Resin
ARP-030579 Report by ELK
Compound
Tenex Tenex Tenex Croft Emico Tenex Louisiana Wire 8
Cable
18031 19041
15041
17461 14551 18031 34641
Processing Color Streaks Off-Color Processing Off-Color Gassing Cold Bend Test
ACP?021579 ACP-021479 ACP-021679 ACP-021479 ACP-020279 ACP-032179 ACP-022879
Report by CRltf Report by RBM Report by RBM Report by RBM Report by RBM Report by RBM
Under Investigation
WAIVERS RECEIVED
Date
Identification
Product
Customer
Reason
3-1 3-1 3-1 3-1 3-1 3-2 3-2 3-2 3-2 3-2 3-5 3-12
3-18 3-19 3-19 3-21 3-22 3-22 3-26 3-27 3-27 3-27 3-28 3-28
3-28 3-29 3-30
T-2351 C0NX-45706 Bags 00517/00518 PLCX-43216 PTLX-41644 PTLX-42022 Bags 00519 T-2811 T-2479 T-2321 T-2320 PLCX-42680
T-2809 T-2320 CONX-45291 Bags 00518 Miller Truck PLCX-43011 T-2809 C0NX-45268 T-2811 PTLX-41836 PLCX-43231 PTLX-41855
T-2481 T-2810 PLCX-43081 Total 27
5305
Carlon
34431 Gry547 Kaiser
5305
Export
5385 III Simpson
5425
Uniroyal
5305
Carlon
5305
Export
5385 III World of Plastics
5305
Carlon
5305
LCP
5465
Industrial Plast.
5425
Uniroyal
5425 5305 5385 III 5305 VRP 5425 5305 5385 III 5305 80273G 5385 80273G
Athol Hat co Tridyn Uniroyal Heritage Southwire Carlon Charlotte Pipe CarIon Can-Tex Charlotte Pipe Central Foundry
5305 5305 5385
Celanese Piping Uniroyal Simpson
Residual VCM
W. Howell
Mixed Color, Fines
CLS
Residual VCM
GGD
Particle Size
RDJ
Contamination
GGD
Residual VCM
GGD
Residual VCM
GGD
Particle Size
GGD
Residual VCM
GGD
Residual VCM
Customer/GGD
Dry Time
GGD `
Contamination,
GGD
No-flow static
Contamination
RBM
Residual VCM
GGD
No-flow static
ELK
Residual VCM
GGD
Color
GGD
Contamination
GGD
Residual VCM Color "b" value
*
GGD GGD
Residual VCM
RBM
Fusion Torque
RBM
Particle Size
RDJ
Fusion Time, Torque HJH/GGD
Stability Time
Residual VCM
Customer/WH
Residual VCM
RBM
Particle Size
RDJ
- '
* ` . DTH 000043693
QUALITY CONTROL TESTING
Resin
- 612 regular samples, 2716 other in-process'resin samples. Bulk resin shipments total 210 (106 railcars, 104 trucks)
Dry Blend - 147 blenders produced with 92 blenders tested. Adjustment rate for all dry blend was 3.4%, There were 184 other dry blend inprocess samples. Bulk shipments total 25 (railcars 4, trucks 21)
Compound - 826 blenders produced and tested. 233 other in-process samples were received. Adjustment rate for blenders was 1.6%. Bulk shipments total 37 (railcars 16, trucks 21)
Residual VCM in Shipments
A total of 131 shipment samples were tested for RVCM in March, A summary of these results is below:
Product
,5385
5425
5305
Dry Blend
Average ppm VCM
1.1
0.4
12.3
Number of samples 88 10 30
0.9 3
Resin Heat Stability
Fifty-five (55) blends of various resin types were tested for over heat stability.
5385 5425 5305 5465
22 Blends 20 Blends
8 Blends' 5 Blends
Heat stability of all types were good.
Raw Material Testing
Fifty (50) lots of plant raw materials were tested. One shipment of Tribase lead stabilizer was rejected for poor dispersion quality,
Harwick VCP-5217 black powder color concentrate was approved as a replacement for the Harwick 90-PC-02 black paste color concentrate.
PRODUCT DEVELOPMENT AND SERVICE
Date Shipped
Quantity
Product
Customer
3-14 3-14 3-14 3-21 3-21 3-21 3-21 3-30
50 lbs. 50 lbs. 50 lbs. 50 lbs. 50 lbs. 50 lbs. 50 lbs. 50 lbs.
17461 Black
14431 CLBL 50 15041 CLBL 50
5305 5385 I 5425 5465 5385 I
Donnelly Mirror,
Atcoflex, Inc. Atcoflex, Inc. Vinatex England Vinatex England Vinatex England Vinatex England M 8 T Chemicals
Inc.
CJM
CJM CJM AMP AMP AMP AMP HJH
, DTH 000043694
COMPOUND DEVELOPMENT AND SERVICE
Special Compound, Testing
*
Specification tests were run on 7 lots of compound for Western Electric 5 lots of 34861 Gray 546 and 2 lots of 36861 Natural.
Dry Blend
t
Quality control standards were prepared for KGM-3400-172C, a new experimental dry blend.
Customer Complaints
A United Cable (Louisiana Wire and Cable) complaint that 34641 did not pass the cold bend test was investigated. A brittle point test indicated that the shipment was typical of this compound and should have passed the cold bend test when coated on wire.
*
Croft Metals complained'that 17461 3A01 gave extrusion problems. The material performed satisfactorily in the laboratory extruder.
A Tenex complaint concerning 18031 Clear Blue 50 claimed gas bubbles and poor profile surface were present in their extruded product. Laboratory extruded strips showed many gel-like imperfections; however, the surface was not rough and no gas bubbles could be seen.
SPECIAL PROJECTS
RVCM in Slurries
A total of 635 batches out of a possible 672 produced were tested for RVCM. The overall average for the month was 212 ppm VCM with only 1 day exceeding the 400 ppm limit. This month, March, is the best with respect to RVCM since the new reactors were put into service.
Residual Vinyl Chloride in 5305 Drier Samples
A total of 34 samples of 5305 from the drier were tested for RVCM. The over all average was 18 ppm VCM.
EPA-Reactor Opening Study
As part of the reactor opening study and related EPA testing the following samples were analyzed:
Slurries for RVCM Waste Water for RVCM Reactor Opening Air Bag for VCM Incinerator Air Bags for VCM
140 samples 42 samples 51 samples 6 samples
DTH 00004369
SPECIAL PROJECTS (CONTINUED) Yjeld Test Run In support of the Yield Test Run percent solids were measured on 12 total waste water composites 9 blowdown tank samples. Waste Treatment Study In support of the waste water program conducted by engineering in Ponca a total of 84 samples were tested for COD, Ph, and percent solids. In addition 7 samples were tested for BOD by an outside laboratory.
DTH 000043396 %
ORDER ENTRY AND TRANSPORTATION WAREHOUSE - J, C. Coffman S J. E. Mays
Shipment By.Product - M Lbs.
March
Vear-to-Date
Resin Plasticizer Dry Blend Compound
TOTAL
15,709 83
4,906 . 5,222 25,920
48,378 333
13,110 13,292 75,113
Number of Shipments by Mode
R/C O.T. C.C. C.O.T. TOFC CPU TOTAL
Resin - Bulk - Package - Export - Aberdeen
Plasticizer - Bulk
75 85 7
12
11 7
171 8 4 26
i3
22
Dry Blend - Bulk - Package
19 9 2
13 41 57
Compound - Bulk - Package
15 22 16 3 2
37 25 46
Export - Package Back Hauls for March
2 110 145
14
21
2
2 8 49 335
14
Number of Shipments by Month - Y.T .D.
R/C O.T. C.C. C.O.T. TOFC CPU TOTAL
January February March
103 166 101 119 110 145
12 10 21
7 0 2
7 56 351 3 36 269 8 49 335
Material Handling Report
M/Lbs-
T/L
Packaged Resin From Production
Packaged Compound, Dry Blend From Prod.
Transferred From Main to Prairie
Transferred From Prairie to Prairie
Reverse Transfer Resin to Plant
Reverse Transfer Compound to Plant
Shipment From Warehouses
<
Special Packaging
Transferred From Prairie to Main
,
1 ,823 1 ,579
567 932 567 121 3 ,281 162 405 9 ,437
45 39 14 23 14
3 81
4 10 233
DTH 00004369
, LOCATION
MAIN-East
TOTAL M SO. FT.
48
CONOCO TRANSPORTATION I
ABERDEEN WAREHOUSE
CONTENTS Compounds Dry Blend Export Resin Conoco. Resin
3.1 i.-n
.2 .7
{1
ESTIMATED MM POUNDS
ON FLOOR
OPEN TOTAL
5-Q 4.5
9.5
Rnjirie 12-1
12-2
12-3
12
22
21
12-4 12-5
22 21
12-6
12-7
12-8
21
21
21
Compound Dry Blend
1.5 .1
Comn O.G.
2
Raw Materials
.2
Conoco Resin
.
Conoco Resin
.5
Resin O.G.
2.2
Mill Scraps
.
Cmpd 0. G.
.6
Dry Blend 0. G. . .5
Sifter Overflow
.2
Resin 0. G.
.
Conoco
Conoco Conoco
1.5 1.5
1A___LS___ A5
.4 3.1
3.5
2.7
.ft 3.5
1A_____L2_____ LI 3.5
3.5 3.5 3.5 3.5
Total on Hand
'' ' T1 .0 ` 23.fi___ 34.5
Chrysler Resin
(-2.0 )
Total
2D. 9. Motftl Conoco -:___________________ ________________
- : ' .
-.
DTH 000043698
Off-Grade In Storage
Material
Sifter Overflow Resin "BC" Resin "H" Mill Scraps Compound "B" Compound "H" Dry Blend "O.G."
M/Lbjs,
200 1,108 1,142
41 1,111
140 375
Ilk
5 27 28
1 . 27
4 __ 9
TOTAL
4,117
101
Chrysler Storage
Balance, March Transferred during month
2,291 337
56 8
' TOTAL
1,954
48
D. F. Operation
It now appears that our inventory has reached a low level and we are shipping approximately what production is producing. We presently have 4 empty storage warehouses available for future storage. Plans are to have a fifth warehouse empty next month by regrouping some products together.
DTH 000043699
ABERDEEN FIRST-AID CASES I
12 MONTHS MOVING AVERAGE 50 45
40
35
30
25
20
15'
10
5
0
,DTH 000043700
Feb.
ABERDEEN OSHA RECORDABLE INJURIES 12 MONTH MOVING AVERAGE
20
15
10
5
0 DTH 000043701
MONTtfl-Y HOURLY TURNOVER
1C 9 8
7
6 5 4 3 2
1 r
' !#i Pounds
ABERDEEN PUNT PRODUCTION
1979
MM Pounds
350 300 250 200 150 100 50 0
60 50 40 30 20 10 0
70 60 50 40 30 20 10
c
20 15 10 5 0-
ABERDEEN PLANT EFFICIENCY 1979
Standard 1.01960
Standard 1.01300
Standard 1.00320
Standard 1.12080
DTH 000043704
u u l 'JC L H E T Z G E N C Q .
M A D E IN U. S. A.
% Off Grade '
'rjm QUALITY. PERFORMANCE 1979
ABERDEEN PLANT INVENTORIES 1979
CMC S tE T Z S C N CO.