Document VjYJ5qqaORj2R2MxqeLJK295g
subjecti
Environmental Health and Safety Department Policy on Asbestos Removal - Case 48097-1
BELL LABORATORIES
date: October 12, 1981
from
0. Rainer MH 78691
3A-213 x7512
MEMORANDUM FOR RECORD
INTRODUCTION
Maintenance and repair work on aonie of the Bell Laboratories Plant facilities has necessitated that on
occasion asbestos insulation on pipes, boilers, beams, etc. be manipulated or removed. To assure compliance with all applicable state and federal regulations, the following are recommended:
1. All contractors or Bell Laboratories employees
engaged in asbestos handling or removal must comply with the regulations outlined in the Occupational Safety and Health Administration (OSHA) Standard 29 CFR 1910.1001.
2. Disposal of asbestos containing wastes must be
handled in accordance with Environmental Protection Agency (EPA) regulations and Resource Conservation Recovery Act (RCRA) regulations.
OSHA Standards
The present OSHA asbestos standard is two asbestos fibers
per cubic centimeter of air as an 8-hour Time Weighted
Average (TWA).
"OSHA Program Directive #300-16,
requires
that medical examinations be given employees
who have asbestos exposures equal to or exceeding 0.1
fibers per cubic centimeter of air as an 8-hour TWA.
Handling Asbestos Containing Insulation
Before working with material that is thought to contain
asbestos, the material must be analyzed to determine if it
in fact does contain asbestos. It is not possible by
visual inspection to ascertain whether or not insulation
contains asbestos.
If insulation materials are to be
analyzed, please contact the Environmental Health and
Safety Department for instructions on the correct method
of sampling.
LLA 001879
ATT-391
2
The primary goal whan handling asbestos containing material is to minimize employee exposure. Insofar as possible, asbestos should be removed or otherwise worked
in a wet state sufficient to prevent the emission of airborne fibers. For example, workers should continually mist or spray the layers of insulation with water if they are being removed.
Employees engaged in the removal or demolition of asbestos
insulation or coverings must be provided with respiratory
protection and with protective clothing.
Generally,
workers wear disposable coveralls including a hood.
Respirators must be ttXOSH/MESHA approved and be marked
accordingly.
Caution signs must be provided and displayed at each location when airborne concentration of fibers may be in excess of exposure limits. Signs must be posted at such a distance from the location so that employee may read the sign and take necessary protective steps. Work areas should be roped off and signs posted to prevent inadvertant exposure to personnel not working in the area.
All work areas where asbestos is being manipulated should be enclosed within plastic drapes. Floors should also be covered. Upon completion of the work tasks, all enclosure materials should be removed and disposed of in accordance with the applicable regulations. Any asbestos containing wastes mist contain caution labels that are affixed to the
bag containing the waste.
After completion of all job tasks work areas should be vacuumed with an approved vacuum cleaner containing a HEPA filter which will remove 99.97% of particles with a diameter of 0.3 micrometers or greater. An alternative to vacuuming is to wet mop the affected area.
COSCLUSIOSS
The Environmental Health and Safety Department is available to review contractor work practices and BTL work practices to insure compliance with all applicable
regulations. This department is also available to monitor BTTI, employees who have a potential asbestos exposure or
answer any asbeitos related questions.
Copy to See next page
LLA 001880
3
Copy to Medical Directors Industrial Hygienist All Safety Committee Chairpersons
R. B. Aljoe C. D. Briggs M. H. Brown L. Cheskin L. K. Jurskis C. J. Lind P. Lutzky C. H. McGould
H. Muehler
W. J. Schreitoeis M. M. Weiss G. M. Wilkening P. B. Wyszkowski