INTER-COMPANY MEMO PLAINTIFFS EXHIBIT KJRC-82 \ TECHNOLOGY AND ENGINEERING J- Holv/iS________________ DATE: TO: FROM: SUBJECT: October 20, 1992 Doyle Palmer Kathy Young File 14.11.2 Dayna Dieringer - KRC File Mike Shea J.D. Hofer Chester Packebush Larry Koester - JBE&C Pat Baker FCC/Cumene DCS Project Asbestos Insulation Identification cc: Joe Harris - KRC CC Asbestos Abatement Joe Harris and I had a telephone conference regarding the identification of possible asbestos insulation in the FCC/Cumene units. I had provided Joe the suspect list provided by JBE&C (see attached), developed during the field verification phase of preliminary engineering. Joe has indicated that most of the list has all ready been checked. The remainder should be completed soon and he will provide us a list of positives to better enable the team to schedule abatement activities during cutover. K016630