Document VG6Eg1LdnkDEnEwMJvRd9gRRw
* UNITED STATES
ENVIRONMENTAL
PROTECTION
AGENCY
REGION 1
BOSTON, MA 02109
Dated as shown by electronic signature
Mr. Jameson Hill
Site Operator
Hampstead Pickleball Club
45 Danville Rd.
Hampstead, New Hampshire 03841
Dear Mr. Hill:
On April 17th, 2024, the U.S. Environmental Protection Agency performed an inspection of Hampstead
Pickleball Club (" Site ") regarding compliance with the National Pollutant Discharge Elimination System
(" NPDES ") program of the Clean Water Act (" CWA "). A copy of the inspection report is enclosed with
this letter. Provide responses and submissions to each numbered item below regarding the Site within
30 days of receipt of this letter to Karissa Oakes of my staff at oakes.karissa@epa.gov.
1. During the inspection, Mr. Hill explained to EPA inspectors that certain disturbed areas at the
time of the inspection (photos 1-2) would be stabilized by hydroseed within approximately a
week. Provide an update, with photos, of the stabilization measures taken at this area of the
Site.
2. Part 1.5 of the 2022 Construction General Permit requires the posting of a sign or other notice
of your permit coverage at a safe, publicly accessible location in close proximity to the Site.
Provide a photo of the sign posted in a place where it may be viewed from the public right of
way for the remainder of time the Site maintains an active permit status.
Legal issues may be directed to Jeff Kopf, Senior Enforcement Counsel, at (617) 918-1796.
Digitally signed Sincerely,
by ALEX
Date: 2024.06.10 Alex Rosenberg, ROSENBERG
09:01:41 -04'00'Acting Manager Water Technical Unit 1
Enforcement Compliance Assurance Division
ENCLOSURES
Inspection Report and Photo Album for April 17, 2023, EPA Inspection
cc: Ridgely Mauck, NHDES
Jeff Kopf, US EPA
Karissa Oakes, US EPA
ED_019088A_00006056-00001