Document VG27G6rXmjMneD5MOQxR1re88
Central w ^Engineering
DISTRIBUTION CEO SECTION MANAGER
CED PROJECT MANAGER
R` SteVenS
A. J. Hejnze
0. R. Bailey J. M. Depp M. Dmytryszyn R. E. Emling F. W. Enoch F. J. Holzapfel R. W. Kaltenrieder F. P. LaBelle R. E. Lenz Russell L. Miller E. Negro
C. L. Parish A. B. Terry
(2)
) deC2319S7
PROGRESS REPORT #4
CEA NO.
AR NO.
1668 Rev.l NA
DATE
12/18/67
PRODUCT
Aroclors
TITLE
Biphenyl & Aroclor - Japan
DIVISION
PLANT
' Organic/lnt11 Yokkaichi,Japan
DIVISION REPRESENTATIVE---------------------- -------- --------------------------------
R. E. Howard R. S. Yates
SCOPE
This project provides for the preparation of a process design package for a plant to produce 5.5 M pounds/year of biphenyl and 10 M pounds/ year of liquid Aroclors at the Yokkaichi, Japan, plant of Monsanto Mitsubishi Kasei (MMK). MMK will handle the detailed mechanical de sign of the new facility based on this process design package.
os**00661
CON F I D E N T I A L
nformation
tPuOicSITnIO^iNniLUiCwCTONiTcAtJunpI CppOrtNPFFIBDTEYNTOIFALMIONNFSOARNMTAOTIOCNOMWPAHNICYHAMNDUSTTHNEORTEBCEIPRIEENPTROISDURCEESDP.ORNESVIBELAELEFDORTOITSUNSAAUFTEHKEOERPIZINEGD APNEDRSODNISS OR SENT OUTSIDE THE COMPANY WITHOUT PROPER AUTHORIZATION.
STLCOPCB4058728
Q< -2-
ProductAroclors___________________________________
I oration Yokkaichi, Japan
Title Biphenyl and Aroclor - Japan____________________ ____________________________
Data Tabulated As Of
November 30. 1967
CEANo. 1668 Rev. 1
AR No.
NA
Appropriation Current Estimate Date of Estimate Expended & Committed Spent This Month Scheduled Completion On Schedule?
MS Not vet approved MS 1730 December 1, 1967 MS 0 MS 0 March 1, 1968
No*
Process Design, % Complete Mechanical Design, % Complete Construction, % Complete % Expended & Committed Design Manpower Construction Manpower
Last Month This Mo. 05 00 00 00 0 0.5 00
* Due to time required on other projects, it is estimated that this design package will be completed on April 1, 1968.
The preliminary scope report dated November 22, 1967 was issued to Organic Division personnel for review.
The estimated cost of $1.6 M which appeared on last month's report was increased by $130 M which reflects a change in the original scope. The present scope includes the production of four Aroclors (in accord ance with the latest sales forecast figures) as opposed to the original scope which provided for only two Aroclors.
Preliminary engineering flow diagrams have been completed for the biphenyl unit and are started for the Aroclor unit. A preliminary overall (suggested) plot plan has also been started. Process design work has started on the pyrolysis furnace/preheater equipment items in the biphenyl unit.
DSW 200665