SOUTHWESTERN INDUSTRIAL CONTRACTORS AND RIGGERS, INC. Formerly: CONSTRUCTION DIVISION, SOUTHWESTERN TRANSFER CO,, INC. 1730 Bassett Ave. P. O. Box 1611 El Paso, Texas 79948 (915) 532-3491 1330 South 26th Place P. O. Box 20865 Phoenix, Arizona 85036 (602)273-1371 LETTER OF TRANSMI TTAL 527 Wyoming Blvd., S.E. P. 0. Bo.x 8057 Albuc^erque, New Mexico 87108 (505) 2F5-7691 f TO: American Smelting And Refining Company P. 0. Box 1111 El Paso, Texas 79999 DATE: December 17,1971 RE e Pipe Quotations ATTENTION: Mr. J. W. English GENTLEMEN: ----------------------SUBMITTAL NO.: WE ARE SENDING YOU ATTACHED DUNDER SEPARATE COVER VIA______ THE FOLLOWING: SHOP DRAYnNGS ^SAMPLES PLANS DESCRIPTIVE LITERATURE copy OF LETTER DATED 0_ Pine Quotations COPIES DATE 1 12/15 1 12/15 1 12/15 NO. DESCRIPTION El Paso Pipe & Supply Grant Supply Company Vinson Supply Company THESE ARE TRANSMITTED FOR REASONS NOTED BELOW: REVIEW AND APPROVAL ^APPROVED AS SUBMITTED ^APPROVED AS NOTED disapproved Gas requested Dfor your use resubmit___ COPIES FOR APPROVAL [^RETURN___ CORRECTED PRINTS REMARKS: Verbally approved 12/16/71 O 1 r>'- Wickes "ar Project Manager ASARCO ELP 0008883 ,, /) S? i'ag e / p x__Pages SOUTHWEST INDUSTRIAL CONTRACTORS AND RIGGERS, INC.-' CONSTRUCTION DIVISION MATERIAL REQUISITION , | JOB: AJA'A/Q.OO , DATE: /2?~/S~ 7/ NO. _f-fsrrzr/s-j7s; s-7s/r>/ x/-'.y . r ^ ssj-i W. >'Vn MIWf _ii_____ /c-eon S PCS. DESCRIPTION /A- /P,/T 3i? 40>tu ..A K<b# S.aSffs.,r- ICi Z A' /<rA d,oAf/^s, Z'-:/' / b /Sb* /fa.. z /'-___ =____ - * * -______ /." 62^. - %z /7 /A S'/C/i-do OJ.^/A -Zee5 " ./ -- - -- z S 4\ dtr/? - Ao *?a* 6" , fft -- <=// -.ZZ*zA 7'. & 2- JZ . > 2/ 1/'f 300_0,^ /7_A Scr_d d<?u/>_//;./><' * . A %Z/2*." -*" --- --- ----- 2 ,^2^.. V < . sX*>'-^. ___ ( A SZ^ 3o A'S"l - A^,<sthCS< A Ml &'* ^><dA Al-)3 &t>rB /3/&c '7>>L 3 ^44//:c ) 264 & c rsf _?/ C?" Se,/>*?> 7 332-4sc? 4-/ .1 f------ ---\r-------- V. 4i ASARCO ELP 0008884 SOUTHWEST INDUSTRIAL CONTRACTORS AND RIGGERS, INC.-' CONSTRUCTION DIVISION MATERIAL REQUISITION r | NO. PCS. M 4 JOB:_ 7>y. . - rz? ^K/r. -- - X "s-y/Z>AJ . , ______________________________" DESCRIPTION r~y<rx.t/ssf/td <&**-*/* /: '<A^/T cTeZ .?Q4 S/s / ft r cJ(7 /- / / -- /?/ -- A" - - DATE: /ZV/-7/ ____________________ 7, 3r" /f 3.55" 2-70 /c %"x //t 3/4 X 4" - y 3'-^" ~ - ~ ~' C'J. 4J 2^ /r' f:/4 - ________ __ \ -- .----------------- ----- --...................... ---............. ...............* .Il_I-- a .. _ 1 ft . ASARCO ELP 0008885 Qi. , SOUTHWEST INDUSTRIAL CONTRACTORS AND RIGGERS, INC.-' CONSTRUCTION DIVISION MATERIAL REQUISITION l f JOB: r__________ NO. PCS. /Z IZ 47-^r" DESCRIPTION ?//>, . s/Jp/d/css 'gisc y>'; /4s- ' DATE: /?-//-7/ r - /'H 4* /, 79 a*. - A 77.*- ?/. -& ZJ. & .21 yj- 4- . ^ " ^ 7?f, '<^5r>/7//rTVZf Me/*' yJrot ?/{> d/&ryo> -- ' V_ /0<3- ' / *' \X 3- c/Z "> /z- ^ (^k'/ sii!f,/>(?- 27.9 /S'f/r/s? & ."V ai *o '//f // J /<?/) /os<z<?c z1............ IZ- */<?" 12- 4**" ' -Do - ' 2 '47<Z<s-. 2*t>4jze~' Zf 5/ _/2r_ /2- /?- 3^ 7 --------------------------------------- ^ 9/ c . 7_^~/,^4-jz^ y S <Z ,--'Z ^ / / Y/ ~7~b4-<i<- L j/u o1* 4't*- /r*f r. i7 ^ - ---- -- -- --~ * ASARCO ELP 0008886 ta&o / ul / i SOUTHWEST INDUSTRIAL CONTRACTORS AND RIGGERS, INC. /0// * JOB: CONSTRUCTION DIVISION REQUISITION FOR MATERIAL | r D*ATE: /Z-/A-7/ NO. PCS. DESCRIPTION <r- /V't' B^oo^ S.u), 9c'&//s & /`/z` / / '/z " J-e c -- z / ,fz" ^ / 2 y: / ^z. /i/ & j^/e- r%' 7.$ ///Z. / " /TV /jh/t?* - ^ Lo /.//, j\f> ...... /3~$3 >?.. z-/;.^ & - r^ : .. r r /,y , (}*' //// '' 7wpr (/ r 1 1 ASARCO ELP 0008887 Page / of 3 Pages SOUTHWEST INDUSTRIAL CONTRACTORS AND RIGGERS, INC.-' CONSTRUCTION DIVISION * MATERIAL REQUISITION JOB: AJS'/j/^CT) <___________ l DATE: //-//- // NO. _____f-J/Jrr:iur*//rj~js-i Sss ?/ /o > s*;).''f .- ^ /f^ny.J^0 / .<j* / / > y --. <- // / / s /Y/>C..*< -V-^^ . C`/v/.v* ...J^CQXJ... ' PCS. DESCRIPTION /z'"' xzz - ja*7 f'7 _______/<a> * Z &" /<ro* /A V/ ,<r:-r . 4'7 #' /2 /Sb// /-foz. i-- /j>^9 z _.&a_/_'_______-______ ^ / ^__ r m______________ ___________________ /r 4?'"' 5/2/)-sfo Z/W - / <5YA" -- -- -- -- * C~ S t * s* l,,i fz '* 3fV fcJC 3" .5^/. ^ /^.W-AV/iT Z" -- -- /viL 7 . .x ri 2''- 5'GOD*~ ZTZ, jzW s /' ____ ___ ____ / /_____ - __2 ^ a *- %" - - -- o< </ //Z. -- -- -- V*. 9- .7 </ ^ 3^ Z& _2/4t ' ~~?-<7~Y<L, jir ?i ^ ! . ............. :__---_ ASARCO EUR 0008888 ku SOUTHWEST INDUSTRIAL CONTRACTORS AND RIGGERS, INC.-' CONSTRUCTION DIVISION MATERIAL REQUISITION I JOB: r__________ DATE: /2-//-Y/ NO. PCS. /Z -/Z tz * ^' rr*r ' ''' S-~7JSSJ& >*1? Zl.X/. rrss/r* cz &s.** DESCRIPTION S/'Z* 2.9e . 7' /rcss Stye see, ?4r ' /** t-Do- /<* * /i 3J. Hsj /<? ^ 6" . '[ e 'JJZ WeyJfnr &>/> &/r*/r7> -- {?<, ^r C >- r zy*tr /*& /r~ S')' \z- 2/z e^iy* f sine.if..ft-279 /&ey/yjs . C '//f// s /e?s) ris^'c ZJV M Yi /D_ _--^yi- (Z- Ste" * -/?*- ' j> * 7 4^" _? < 9 11 '> z? V 33 2'* ' fi- /2/2- ^Z * Zfrj n r?Z //s/te, (T-fZ/asm ? - ,<* O/^" __ <s / ^ ___ ' - ?3- 1 2jJ // ^ //' ;--- ----- ------------------------------------------------------------------ \l 11 1 it * * `H ASARCO ELP 0008889 JOB:_ SOUTHWEST INDUSTRIAL CONTRACTORS AND RIGGERS, INC.-' CONSTRUCTION DIVISION MATERIAL REQUISITION \ r DATE: /2V/-7/ " 7Z> NPOCS. . <Z~o DESCRIPTION .. /%** ~/<rX. t fafh c. o3~ /o c-* ': <r<s .s'O'j s/s M &' 4 /si * / ftr cJs? -- - sDs/^ - .../ r? ' 3i/. (2 ' 7 "> ft-'l *24 %"x 4'Viil./rg/ujcY/;72. n/.</$ d @ //z lit* 4" - - . - . -- ,7L ?2 %> y 3s/4" - - -- . vr" S!^ // -/6 LT"o -h-J- 0(Lt> In^ * i / / 1 ...... - .... n- lp=r=- ; ASARCO ELP 0008890 J/HiC A-' -- Page / 01 i SOUTHWEST INDUSTRIAL CONTRACTORS AND RIGGERS, INC. CONSTRUCTION DIVISION MATERIAL REQUISITION JOB: MSdCQ,________ ^ I r * DATE: 7/ NO. PCS. /Z'" /o. Z &,e DESCRIPTION /So*S.O. jT/fS/.&>* S.o/stfye * .i<rod ^ ^ *v- viv^ .id..'________ /S', A ' JC ^ <ths 7*& 7 Z //5Z rf u-> b 3" /Sb* uf</u, //*$, A" - - r' ' ?< -- / 71' ~ ?C7 ?, .52^ ^ kJ^/J Aect - / ff,f -- --- r v : t- i/s tcZ & /* *jf !>47S 4f** ^ 46* US'/M f/c - '3'* 7 - -/ - -- 7 ** ,ol * H &7 _x_ --2''- 360&*` 73. "_ Sard dau&//;A'?.. __/ ___ / 1 1 i \ fa //^ ^_ --- j 7 3- / '* 7& 7/ u 'f 7- q 2 MX- 20 /2-g3 B 2/ 77" Se./?4a /&//>* '-JS7*/X / f2f *i ---------- 1 ................ .. 11 __ 1\ ASARCO ELP 0008891 SOUTHWEST INDUSTRIAL CONTRACTORS AND RIGGERS, INC. CONSTRUCTION DIVISION MATERIAL REQUISITION '| JOB: DATE: /?-// 7/ NO. PCS. "2, 4 ~ <E^>c/Sr. Coz-t/^/Z.s_______________________________________________________________ DESCRIPTION /?" jr/ctf/zr/Yjc '<&***/* 'r/y /e <r<s? r o'(7 /- x ^/ - ?/ a4 -- 4' - Z>//4 - /. /* ^ </? *- /* & 12--1 %"x ^ /?" giLfStu*/ //z 3/4 * 4" - - ?z %y 3*t4" ' 7>,, rtOr/s <54, ^6. - . V? " . </4 ,r& $z & /* - / --- - -------- ------- -............ ............... i ti ASARCO ELP 0008892 * o ^ 1 11 fo -* ^ SOUTHWEST INDUSTRIAL CONTRACTORS AND RIGGERS, INC. JOB: CONSTRUCTION DIVISION MATERIAL REQUISITION '__________ I r 'DATE: /2-//-V/ NO. PCS. <xr/rtzrcx/.i r/ssrs czgs DESCRIPTION /z 29o ftS5 you t/s- - 7 77 ":f 2/ /Z /z %r______________________ -a*-- .J >* / 77 . 2, & ^/ B Svi'/u/or y './Z zoo*-/; yJrc/ /?,, ^ &/ &/ f//osro>7 '-no- ' /z- S/d <^y/ nr.' 27 f ,&<?<?/*/ __________________ c js/<r,j * /y?sj & /<zoc */#" ' -Do - / 4^7" / o j? ?-s- 3 *7 Jt " // 72 ve - z<1 J= 21 GSssr^ -XL. S/Z * &r/n/7f. //rf/ _ -%,r - T7 -- -J..2 /?- C'C/a/fJt. 0 - --' ___________________ ~~7~Z?//u- C^uc'i <. 7 /&/ &* / z *& /o tS- * / 1^37. 4/ __ r \ \\ ASARCO ELP 0008893 SOUTHWESTERN INDUSTRIAL CONTRACTORS AND RIGGERS, INC. Formtrly: CONSTRUCTION DIVISION, SOUTHWESTERN TRANSFER CO., INC. 1730 Bointt Avt. P. O. Box 1611 El Paso, Texas 79948 (915) 532-3491 1330 South 26th Mac# P. O. Box 20B65 Phoenix, Arizona 85036 (602) 273-1371 ,527 Wyoming Blvd., S.E. 'f.'O.'ijx S057 que, New Mexico 87108 691 February 31972* American Smelting & Refining Company P. 0. Bor 1111 El Paso, Texas 79999 Attn; Mr. J. W. English Re: Converter Gas Acid Plant Purchase of Bolts & Gaskets Bear Sir, The following is a comparison of prices quoted for the bolts and gaskets we need for the installation of piping on this project. Gaskets Bolts TOTAL Grant Supply Company Harrison Bolt & Nut Company Anchor Bolt & Screw Co. El Paso Bolt & Screw Co. El Paso Pipe & Supply Co. 515.27 57U.85 NQ NQ 891.01 1,750.05 1,81*3.00 1,809.00 1,396.20 1,321*. 61* 2,265.32 2,1(17.85 _ _ 2,215.65 HEW/wcs ASARCO ELP 0008894- QUQTATION RANT SUPPLY COMPANY J i PIPE TUBES VALVES FITTINGS FOR INDUrSTRY sI *2413 EAST 2ND * ODESSA. TEXAS 7fcfc> * P. O. BOX 43S5 * PHONE 015) 332- niTF Januanu 21f 7972 SoutkaeAtVin Indu6t/udZ Con&ui<utotu R-igge/u, 1nc.cimiP^T QuotcutLon P. 0. Box 7577 El Pcuo, Te.xcu> 79948 YouA Re.qu.Mt ft .7_______ |_ ATTENTION: Mit. A. M. Ctotfe " ITCH NO. WE ARE PLEASED TO SUBMIT THE FOLLOWING QUOTATION FOR YOUR CONSIDERATION: QUANTITY DESCRIPTION DELIVERY UNIT PRICE TOTAL PR! T 52 2" 150# SPIROFLEX GASKETS .63 32.; 2 15 2-1/2" DITTO .70 10.5C 3 20 3" DITTO .86 17.2 4 78 4" 5 40 6" DITTO DITTO 1.09 85. C 1.57 62.8 6 40 8" DITTO 2.06 82.4 7 17 10" 8 20 12" DITTO DITTO 2.84 4.24 48.2 ' 84.8 9 3 10 6 14" DITTO 2-1/2" 300# SPIROFLEX GASKETS 4.75 .87 14.2 5.2 11 3 3" DITTO ;97 2.9 11 10 13 14 14 7 8 15 ; t 16 2 17 4 4" DITTO 6" DITTO 2-1/2" 600# SPIROFLEX GASKETS 3" DITTO 4" DITTO 6" DITTO 1.17 1.90 .87 .97 *' 1.17 2.12 11.7 26.6 6.9. ..9 - 2.3 8.4. ----------------------- ----------------------------------------------- TERMS_______________________ QUOTATION NUMBER______________________________________________ GRANT SUPPLY COMPANY BY ASARCO ELP 0008895 QUQTATION RANT SUPPLY COMPANY 24 13 EAST 2nd P. O. BOX 4395 ODESSA, TEXAS 797ft PHONE 1915) 332.|j i m. f- DATE. s outko&6te/in InduA&UaJt ContnacAo/u & RXqq &u, Inc SUBJECT. Page # 2 rrcM no. L WE ARE PLEASED TO SUBMIT THE FOLLOWING QUOTATION FOR YOUR CONSIDERATION: quantity DESCRIPTION DELIVERY UNIT PRICE TOTAL PRI u 12 19 8 20 4 21 4 22 2 23 2 24 2 25 2 26 2 27 208 28 60 29 816 30 400 31 376 32 80 33 64 34 176 3" 150H F.F. ASBESTOS KING GASKETS ' .15 1:8, 4" DITTO 6" DITTO .21 1.6. .28 7.7; 8" DITTO 10" DITTO 12" DITTO .40 1M .54 1.01 .80 1.6C 14" DITTO 6" 300H F.F. ASBESTOS KING GASKETS 4" 600# DITTO 5/8 x 3" B-i STUDS 01/2 2H NUTS EACH 315.27 To./ J.O.&1 5/8 x 3-1/4" DITTO 5/8 x 3-1/2" DITTO 3/4 x 3-3/4" DITTO .95 1.90 .35 .70 .30 3^23.02/0 n .60 i 47.ft ?v5523,66/C \ 14.20 ^24.33/C m.53 266%4.46/C p\. 84 3/4 x 4" 3/4 x 4-1/4" 3/4 x 4-1/2" DITTO DITTO DITTO 6/7 * 2^35.40/0 - >& Ll7i 36.33/C eft v 37.27fc 133)00 / 29.06 1 23.85, 3/4 x 4-3/4" DITTO 67* 11^38.21/0 ' 67.25 F.O.B___________________ terms_________________ QUOTATION NUMBER. GRANT SUPPLY COMPANY ASARCO ELP 0008896 QUOTATION ASARCO ELP 0008897 AREA CODE 918 T E . 3-2345 HARRISON BOLT & NUT COMPANY MANUFACTURERS <) 6 13 0 EAST 13TH STREET 0 TULSA. OKLAHOMA 74] t 2 January 19, 1971 Sou'thwestern Industrial Con tractors and Riggers, Inc. Box 161 1 El 1Paso , Texa s 79948 Attenti on: 1*1lr . Clark RE : Quotation Dealr Si r: We aire pleased to s ubmit ouir prices on you:r recent i nqui ry. &S/C.C in. nfd) Stud Bolts to ASTM A 193 (ST."\ W/2 Hex Nuts to ASTMA 194 2H Z,c 1JJ.L 208 5/8 X 3 C Net 21.49 VY.`?o 44. 70 $.3.3? 60 5/8 X 3-1/4 22.09 c/C "75 13. 25 jy.si 816 5/8 X 3-1/2 22.72 185. 40 SS'/.So 400 3/4 X 3-3/4 376 3/4 X 4 32.17 33.04 128. 68 3 </( /V 9*- 124. 23 80 3/4 X 4-1/4 33.91 &Z. v'a 27. 12 So.13 64 3/4 X 4-1/2 34.71 6S./0 22. 27 V/ iw 176 3/4 X 4-3/4 35.67 . 62. 78 // 7-3A. 492 7/8 X 4-1/2 32 7/8 X 5-1/2 46.41 228. 34 y</3.V7 51.14 fs.sv 16. 36 S/.S3 60 1 X 5 71.78 43. 07 48 1 X 6-1/2 82.91 /7S. 39. 80 3 V 4c A" 4/OfiO.Oyr /-- .2 UJ !<- / -e --- Flexi tallic Gaskets Sty!e CG /;/>.ou 936. 00 C*Ch*. /*s /^ ik-ft. 304 Stainless Steel and Asb, Ea Net 52 2" - 150# .72 37. 44 15 2-1/2 - 150# 20 3" - 150# 78 4" - 150# .81 .98 1.22 12. 15 19. 60 95. 16 J I {>ES SHEET AND META L GASKETS ) ALLOY A ND STAINLESS STE EL STUD BOLTS ASARCO ELP 0008898 AREA CODE 918 838-8961 HARRISON BOLT & NUT COMPANY MANUFACTURERS o 6130 EAST 13TH STREET 0 sr TUiIa, OKLAHOMA 74112 Page 2 Southwestern Industrial Contractors and Riggers, Inc Flexitallic GaSkets Style CG EA Net 40 6" - 150# 1.76 40 8" - 150# 2.30 17 10" - 150# 20 12" - 150# 3.18 4.78 3 14" - 150# 5.36 6 2-1/2 - 300# .98 3 3" - 300# 10 4" - 300# 1.09 `1.33 14 6" - 300# ' 2.15 8 2-1/2 - 600# 1 3" - 600# .98 1.09 2 4" - 600# 1.42 4 6" - 600# 2.41 70.40 92.00 54.06 95.60 16.08 5.88 3.27 13.30 30.10 7.84 1.09 2.84 9.64 566.45 1/16 #1400 Asbestos Full face Gaskets C Net 12 3" - 150# 10.80 1.30 8 4" - 150# 4 6" - 150# 4 8" - 150# 14.68 19.32 27.00 1.17 .77 1.08 2 10" - 150# 2 12" - 150# 36.80 54.40 .74 1.09 2 14" - 150# 64.40 1.29 2 6" - 300# 2 4" - 600# 24.20 24.20 .48 .48 8.40 Thank you for your inquiry. 1510.85 Sincerely, HARRISO^BOL^F JNy-f/CO. 'if. F.^5cfn c^,' Ji%/vVtJ-Pres, ALL TYPES SHEET AND METAL GASKETS , ALLOY AND STAINLESS STEEL STUD BOLTS ASARCO ELP 0008899 ARE *'jCp D E 0 18 T E. 345 HARRISON BOLT & NUT COMPANY MANUFACTURERS () 6130 EAST 13TH STREET ^ - .V January 28, 19.71 I Southwestern Industrial Contractors and Riggers, Inc. Box 1611 El Paso, Texas 79948 Attention: Mr. Clark. Re: Quotation - the following to be considered an addendum to our quotation of 1-19-71. Dear Sir; We are pleased to submit our prices on your recent inquiry. Stud Bolts to ASTMA 193 B16 W/2 Hex Nuts to ASTMA 194 Grade 4 C Net 208 5/8 X 3 44.90 60 5/8 X 3-1/4 45.98 816 5/8 X 3-1/2 47.12 400 3/4 X 3-3/4 60.36 376 3/4 X 4 61.92 80 3/4 X 4-1/4 63.48 64 3/4 X 4-1/2 65.10 176 3/4 X 4-3/4 66.66 492 7/8 X 4-1/2 90.14 32 7/8 X 5-1/2 98.54 60 1 X 5 156.86 48 1 X 6-1/2 175.76 93.39 27.59 384.50 241.44 232.82 50.78 41.66 117.32 443.49 31.53 94.12 84.36 1843.00 Thank you for your inquiry. Sincerely, TS/jap ALL. TYPES SHEET AND METAL GASKETS HARRISON BOLT AND NUT CO. Tom Schick, Manager. > STUD BOLTS ASARCO ELP 0008900 Bolt, and Screw 103 N . DOTSY FEDERAL 7-7305 P. O. BOX 008 ODESSA. TEXAS tfAwackvl S&dfonex Sfytcialfy tf" ^Southifestern Ind&strial Cont.T' P<0. Bor 1611 El "Paso, Texas 79948 Date 1--18--72 Quotation No. 1000 Attn: A.M. Clark QUANTITY DESCRIPTION ` -1 Terms: Vfo 10th Prox,- 30 days net FOB American Smelting & Refining Co. El Paso, Texas Shipment 10 days from receipt of order PF10E pEh HUlfflflF Net Price 208 60 316 400 376 80 1?6 492 32 6o 43 5/8 X 3 5/8 X 3 5/8 X 3 3/4 X 3 3/4 X A 4V 4\, X4 Xh 7/8 X 4 X5 1X 5 X6 ASTK A193 B-7 Studs with 2 ASTK A194 Grade 2-H Hex Nut Each.. ........... V/ 23.55 1/4 Ditto jq 24.15 1/2 Ditto /i ,/3 24.76 3/4 Ditto .i- 35.14 Ditto .-7.-; 36.01 1/4 1/2 Ditto Ditto ^v- ,<4L 36.87 6,5 A4 37.73 3/4 1/2 1/2 Ditto Ditto Ditto 'tfs-38.59 9, .71 51.06 o r.?^55.72 1/2 Ditto Ditto / V iM78.20 / to s.3289.15 Total Cost Plus Texas tate Sales Tax Total Cost 48.98 sw 14.49 JSJ . 202.043^3.5 . 140.56.?^ 135.40j&M 29.50 37 s 24.15 vz-i 67.92 n&i 251.22 ys/.l. 17.83 46.92 &b.o 42.79 7?i; 1,021.80 40.87 1,064.72 r-5 / / </ He/ ~/:^r - 4 ><?</ yja-* */, e>o%o. 72.21, All Quotations Subject to Change After W$Days '~J~ -------------- ASARCO ELP 0008901 (f- f7 _sr BOLTS - ALL SYSTEMS ./Vsgrj*-. StuaHk&ts.USAI B16.5 ASTMA 193 v/2 ea. Hex Huts ASTM - A194 Q.TY ' r?j|siZE pR. <L yoTAt- 208 60 816 400 376 80 64 176 492 32 60 48 '5/8" x 3" 5/8" x 3-1/4" 5/8" x 3-1/2" 3/4" x 3-3/4" 3/4" x 4" 3/4" x 4-1/4" 3/4" x 4-1/2" 3/4" x 4-3/4" 7/8" x 4-1/2" 7/8" x 5-1/2" 1" x 5" 1" x 6-1/2" 3i*.-i:sr 3 4- C>c> *ie.4 44,70 S~t .00 ^2.30 S3 AS* 68.t*5 ~lb,4$ /So. IS //ic>. S'S" Cs-V ,IU n f* i 1*2.. ?/ MS . to / & & 7 4o.g //3% ~[oTftL 33T.r7t 14 'ft (*o'H5 SW 21 Paso Bolt & Screw Co. 70o8 Alameda 21 Paso, Texas ASARCO ELP 0008902 SOUTHWESTERN INDUSTRIAL CONTRACTORS AND RIGGERS, INC. Formerly: CONSTRUCTION DIVISION, SOUTHWESTERN TRANSFER CO., INC. T730 Bast.lt Avt. P.O. Box 1611 ' El Paso, Texas 79948 (915) 532-3491 1330 South 261h Plac* P. O. Box 20S6S Phoenix, Arizona 85036' (602) 273-1371 527 Wyoming Blvd., S.E. P. O. Box 8057 Albuquerque, New Mexico 87108 (505) 265-7691 ' REQUEST for quotation EOT AN ORDER BEQUEST# 7 DATE; January 13, 1972 TO: El Paso Pipe and Supply P.O. Box 9858 El Paso, Texas 799^9 * CUSTOMER: ASARCO JOB TITLE:__________ Converter Gas Acid Plant .To receive consideration: 3 copies of your bid must be in our office by January 21, 1972 . FOR SHIPMENT TO: American Smelting & Refining Co. El Paso, Texas SHIPMENT REQUIRED BY: Please submit firm Quotation on Items listed below subject to terms listed herein: ITEM QUANTITY DESCRIPTION Gaskets & Bolts (See attached lists) QUOTE NO.: 32-IND. Quotation must indicate unit price, extension, total, applicable taxes, terms of payment, FOB point, shipping point(s) and best delivery. Quotation must be in accordance with plans and specifications submitted. Deviation or substitutions must be clearly stated in your Quotation. SOUTHWESTERN INDUSTRIAL CONTRACTORS & RIGGERS, INC. A. M. Clark Project Supt. ASARCO ELP 0008903 GASKETS - ALL SYSTEMS SIZE 10" 12" 14" 3" 4" 6" 8" 10" 12" 14" 6" DESCRIPTION I 7. "t^ 150# Type CG Flexitallic Gaskets-spiral wound 304 &n./Stl. $ 1.11/EA Ditto Ditto Ditto Ditto Ditto Ditto Ditto Ditto $ 1.24/EA . $ 1.51/EA /St--' 'd:'Cc $ 1.89/EA $ 2.70/EA. $ 3.55/EA fZ.Zj $ 4.90/EA /*?.:' $ ,7.35/EA ^7^ $ 8.25/EA 300# Type CG Flexitallic Gaskets-spiral wound 304 Stn./sti. $ 1.51/EA' Ditto ,$ 1-68/EA Ditto $ ' 2.04/EA Ditt0 . $ 3.30/EA V 2, ? ^ 600# Type CG Flexitallic Gaskets-spiral wound 304 Stn./sti. $ Ditto /. ;/ $ Ditto Ditto 24- $ $ 1.51/EA 1.68/EA 2.18/EA 3.70/EA 150# Full Face l/l6" Asbestos Gaskets Ditto Ditto Ditto Ditto Ditto Ditto 300# Full Face l/l6" Asbestos Gaskets 60C# Full Face l/l6" Asbestos Gaskets -r i $ .22/EA -.'o $ ' .30/EA LLr, $ . 40/EA 2 $ .56/EA $ .76/EA ; $ 1.12/EA - $ 1.33/EA $ .`50/EA ' $ 1.05/EA (CVl ! c / ASARCO ELP 0008904 BOLTS - ALL SYSTEMS Stud Bolts, USAI B16.5 ASTMA 193 v/2 ea. Hex Nuts ASTM - A194 QTY SIZE_______ |' *'' 208 -5/8" x 3" 60 5/8" x 3-lA" 816 5/8" x 3-1/2" 1*00 . 3/4" x 3-3/4" 376 3/4" x 4" 80 3/4" x 4-1/4" 64 3/4" x 4-1/2" 176 3/4" x 4-3/4" 492 7/8" x 4-1/2" 32 7/8" x 5-1/2" 60 1" x 5" 48 1" x 6-1/2" $ .31/EA $ 32/EA $ 32/EA $ 46/EA $ 47/EA $ ,48/EA $ .50/EA $ .51/EA $ ' $ .'73/EA $ .96/EA $ ,.11/EA A/ -'A: i/ / i t/.. /'' ivir, / , t/J ; "J / , i < a 4>, 'ftf 'h u. :</ TERMS: DELIVERY: F.O.B. POINT: 2% 10 NET 30 DAYS STOCK - EL PASO & HOUSTON, TEXAS AMERICAN SMELTING & REFINING ALL ITEMS SUBJECT TO PRIOR SALE JQR JURTURJJ ^JOR^T^ON CONCERNING THIS QUOTE f PLEASE CALL RICHARD McGRANE, ^ ^ TEMPLE C. SMITH ASARCO ELP 0008905 CONSTRUCTION SPECIFICATIONS FOR STEAM AUXILIARY EQUIPMENT AND PIPING FOR CONVERTER GAS ACID PLANT EL PASO, TEXAS Prepared by Central Engineering Department Design Section ' Date November 17, 1971 ASARCO ELP 0008906 CONVERTER GAS ACID PLANT CONSTRUCTION SPECIFICATIONS Section on Steam Auxiliary Equipment and Piping t r Scope p This section covers the installation of the following: 1. Steam auxiliary equipment. :.* 2. All piping except in the Acid Plant proper. 3. Site clearance required for installing the above. Electrical and instrumentation work related to the above equipment will be covered under separate speci fications . Drawings The following drawings delineating the construction shall be a part of these specifications. EP--17785 Power House-Boiler & Compressor Room-Arrgt. EP--17787 Site Clearance EP--17789 General Arrgt. Deaerator Installation EP--17790 Pipe Rack Plan-Area A EP--17791 Pipe Rack Sections-Area A EP--17792 Oily Condensate Filters-Area B-Plans EP--17793 Oily Condensate Filters-Area B-Sections EP--17794 Deaerator Plan Above Grade-Area C EP-17795 Deaerator Plan Above Elev. 3792'-4 -Area C EP--17796 Deaerator Sections-Area C EP--17797 Air Compressor Plan Above Elev. 3792*-4 -Area D EP--17798 Dump Condenser-Plan Above Elev. 3773'-0 -Area E EP--17799 Power House-Schematic-Modifications ASARCO ELP 0008907 2 EP-17802 Dump Condenser Plan Above Elev. 3798' 7-1/4 -Area E EP-17803 EP-17804 EP-17811 Dump Condenser Piping-Area E-Section A I Dump Condenser Piping-Area E-Sections rB & C t- Steam Drums-Plan-Area F EP-17812 Steam Drums-Section-Area F EP-17813 Converter Hood Piping-Area F EP-17814 Boiler Plans-Above 3773'-0 EP-17815 Boiler Sections-Area G EP-17816 Boiler Sections-Area G EP-17817 Boiler Sections-Area G EP-17818 Spray Chamber-Sections-Area H EP-17819 Pipe Support Details EP-17820 Pipe Support Details EP-17821 Key Plan and General Notes EP-17822 Air Compressor Plan Above Elev. 3773'-6 - Area D EP-17823 Air Compressor Sections-Area D EP-17824 Spray Chamber Piping Plans-Area H EP-17882 Converter Hood Piping Details-Area F EP-17883 Spray Chamber Air Piping & Misc. Details EP-17884 Spray Chamber Water Spray & Piping Arrgt. EP-17885 Spray Chamber-Acid Spray Piping EP-17886 Spray Chamber-Spray Piping & Controls-Schematic EP-17944 Boiler Plan Above Elev. 3883'-0 EP-17945 Steam Trap Details-Sheet #1 EP-17946 Tagged Item List fi Steam Trap Details-Sheet #2 Manufacturer drawings of equipment furnished by Asarco. Drawings of existing installations pertinent to the work. ASARCO ELP 0008908 Work Conditions 3. The Contractor shall do the work herein described furnishing all labor, supervision, tools, equipment and personnel f- facilities. The Contractor shall furnish all materials except as hereinafter described. The Contractor shall remove all demolished materials, equip ment and debris to disposal areas designed by the Plant Engineer. Equipment Furnished by Asarco Asarco will furnish the following equipment as specified in the listed Asarco requisitions. Air Compressor Req. No. CE-71-EP-3 Dump Condenser Req. NO. CE-71-EP-4 Feedwater Pumps Deaerator Valves, Hoses & Nozzles for Spray Chamber Orifice Flanges Condensate Storage PUmps Req. No. CE-71-EP-5 Req. No. CE-71-EP-6 Req. NO. CE-71-EP-9 Req. No. CE-71-EP-22 Req. No. CE-71-EP-23 Boiler Check Valves Req. No. CE-71-EP-24 Spray Chamber Pumps On.hand at Plant. Motors and Motor Starters Exceptions and Changes Requisitions pending. All exceptions or changes in these specifications or drawings shall be approved by the Asarco Project Engineer, and a written record maintained of all such exceptions and changes for sub mission to Asarco on completion of the project. ASARCO ELP 0008909 4. Site Clearance The Contractor shall clear the site as shown on the drawings r for the installation of equipment and piping. This will include the removal of abandoned equipment and piping, the relocation and repiping of existing equipment, and the relocation of piping. Equipment The Contractor shall install all equipment shown on the drawings furnishing all except as listed above, and shall furnish and in stall all supports, structures and foundations required for the satisfactory installation and operation of the equipment. Manufacturer's installation instructions shall be followed in detail. Piping The Contractor shall furnish all material and equipment, including valves, hangers, supports and insulation; and shall fabricate and install all piping, fittings, appurtenances and devices necessary for complete piping system ready for operation. APPLICABLE PUBLICATIONS All piping shall conform to local codes if they are governing, and to the NBFU fire prevention code, as it applies, and Factory Mutual Engineering Corporation Standards. All welding shall conform to the requirements of the latest editions of the "American Standard Code for Pressure Piping" ANSI B 31.1a. Backup rings need not be used. All material furnished and procedures followed in the fabrication and erection of the pipe, valves and associated equipment shall ASARCO ELP 0008910 5 conform to the latest edition of "American Standard Code for Pressure Piping" ANSI B 31.1 and B 31.1a. MATERIALS AND WORKMANSHIP General: Materials of construction, valving and specialties shall be as hereinafter described. Piping Layout: Major piping shall be installed as shown on the drawings. Minor piping not shown on layout drawings shall be laid out in an orderly manner, grouping lines whenever possible and shall follow the diagrammatic layout shown on the drawings. Relocation in the field may be done only with the written consent of the Engineer. The installation shall be neat in appearance, and adequately supported. Every effort shall be made to locate piping and equipment which must be regularly serviced, inspected or tested so that this work may be done as easily as feasible. Lines shall slope in the direction of flow, a minimum of 1/8 inch per foot whenever possible, or as shown on the drawings. Pump piping arrangements shall be in accordance with the standard details shown on the drawings. Piping running through roofs, floors and walls shall pass through sleeves as follows: Floor: Sleeves shall be of standard weight pipe, anchored in floor, flush at bottom and projecting one inch above finished floor, sized to allow 1/2 inch minimum clearance from pipe and insulation, if required. Roof: Sleeves are to be made of galvanized sheet iron fastened to roof, and flashed with galvanized sheet metal. ASARCO ELP 0008911 6. Walls: Sleeves shall be of standard weight pipe, anchored in the wall and flush bn each side of the wall. Sleeve I shall provide 1/2 inch minimum clearance fr<m pipe and insulation if required. Sleeves in exterior walls shall be filled with oakum and caulked after pipe is placed in sleeve. Vertical pipelines, passing through concrete, shall be pro vided with adequate protection to prevent corrosion at point of contact of pipe with concrete. Headroom clearance of 7 ft. 0 in. shall generally be provided below all piping, insulation and appurtenances. Supports, hangers, guides and anchors: The selection of support points shall be made to utilize existing structural steel where feasible. The Contractor shall furnish and erect all hangers, brackets, rods, clips, clamps, plates, channels and other parts required for a complete installation as well as all necessary miscellaneous iron which .may be required to transfer hanger reactions to building steel. All rigid hangers shall be fitted with means of vertical adjustments and suitable locking means shall be provided. All tie rods shall be fitted with adjustment and locknuts. All welded hangers, supports, guide or other attachments shall be of material similar -to the pipe, and shall be subject to the same welding procedure as the pipe. Welded attachments to structural steel shall be such as to allow welding along the flange. Welding across the flange will not be allowed. Precautions shall be taken in piping installation to prevent stresses in piping and overstressing of flange ASARCO ELP 0008912 7. bolting at valves and equipment. Cold springing shall be used in pipe fabrication as shown on the drawings. t Underground Piping: All pipe and fittings shall be carefully handled to avoid damage and shall be inspected for defects before being lowered into the trench. Special care shall be given to handling coated and/or lined pipe to avoid damage.' Any damage to pipe, coating, or lining shall be repaired to the satisfaction of the Engineer before installation. Trenching and Backfilling: The pipe trench shall be excavated along the alignment shown on the plans. Trenches shall be kept to a minimum workable width with trench walls vertical from the bottom of the trench to the top of the pipe. Suitable shoring timbering or sheeting shall be provided where necessary to support the sides of the trench prior to and during installation of the pipe. All shoring, timbering and sheeting shall be removed before backfilling. The open ends of the pipe shall be closed at the end of each day's work, and shall not be opened until work is resumed. After the pipe is laid on suitable fill in the trench, the line shall be backfilled, leaving only the field joints exposed so that the pipe will be protected until tested and accepted by the Engineer. In backfilling the trench around the lines, special care must be taken so as not to injure coatings or displace the pipe and to give it a solid bearing throughout its entire length. The remainder of the backfill above the pipe shall be sufficiently packed to prevent serious settlement. Open trenches across roadways or other areas to be paved shall be backfilled and compacted to a density at least equal to that of the surrounding earth. Sleeves made of steel ASARCO ELP 00089.13 8. pipe shall be used for lines 12 inches and smaller crossing under truck roads and areas where concentrated loads may occur. r In all cases, the sleeves shall be two nominal pipe sazes h larger than the protected line except that minimum clearance / between pipe and sleeve shall be 1-1/2 inches. CLEANING AND TESTING Testing and field inspection shall conform to USASI B 31.1 1955 and B 31.1a - 1965. All lines shall be thoroughly cleaned while disconnected from all equipment. All piping, except low pressure air-, gas and vent lines, shall be tested at 1-1/2 times working pressure of line service. Low pressure air and gas lines shall be tested at 50 psi air and soapy water test. Underground Pipe Covering Underground pipe shall have a protective covering except as hereinafter specified, shall be mechanically applied in a factory or field plant especially equipped for the purpose. Specials and fittings that cannot be coated and wrapped mechani cally shall have the protective coating applied by hand, prefer ably at the plant that applies the covering to the pipe. Joints shall be coated and wrapped by hand. Hand-coating and wrapping shall be done in a manner and with materials that will produce a covering equal in effectiveness to that of the mechanically applied covering. The coating work shall be thoroughly inspected, and any flaws or holidays found shall be repaired by the Con tractor at no extra cost. The pipe covering shall consist of one of the following: Coal-tar Coating and Wrapping: A coat of coal-tar primer, a coat of coal-tar enamel, a wrapper of coal-tar-saturated asbestos felt. ASARCO ELP 0008914 9. a second coat of coal-tar enamel, a second wrapper of coal-tarsaturated asbestos felt, where indicated, and a wrapper of kraft ' paper or a coat of water-resistant whitewash, applied in the b order named and conforming to the requirements of AWWA Standard 203 in all respects as to materials, thickness, methods of application, tests, and handling, except that interior lining will not be required. Joints and fittings shall be coated and wrapped either in conformity with AWWA Standard C203 or with the materials specified in Federal Specification HH-T-30, applied in accordance with the manufacturer's recommendation. Alternate No. 1: Asphalt Coating and Wrapping; A coat of asphalt primer, a coat of hot asphalt enamel, an asphalt-saturated-felt or asphaltsaturated-glass wrapper completely bonded to the enamel applied in the order named and conforming to the requirements of the Asphalt Institute Specification M-l in all respects as to materials,' thickness, methods of application, tests and handling. Alternate No. 2: Extruded polyethylene sheath conforming to Federal Specification L-C-530 and of thicknesses not less than 54 mils. Fittings and joints shall be covered in the manner and with the materials recommended by the applier of the sheath. Pipe Insulation All pipes carrying liquids or gases in excess of 150 F. shall be insulated with a metal reinforced fiberglass blanket, JohnsManville Thermobestos or equal covering all pipes, fittings and valves except as noted on drawings. Insulation shall be applied ASARCO ELP 0008915 10. in accordance with manufacturer's instructions. The insula*- tion shall have a protective covering of 0.010" thickness stain* less steel #304 sheet. Alternate insulation of equaj or better insulating value may be used if approved by Owner's representative. Insulation thickness shall be as follows: 400# steam lines 2-1/2" 400" condensate lines 2" 150" condensate lines 1-1/2" 5# steam lines (6" dia. and larger)1-1/2" (5" dia. and smaller) 1" low pressure condensate lines 1" feed water lines (5" and larger) 1-1/2" (4" and smaller) 1" Pipe Painting and Coding Interior pipe shall not be painted. Exterior non-insulated pipe exposed to the weather shall be given a primer and finish coat in accordance with the general specifications for painting ex terior metal surfaces. Content of piping systems shall be identified according to the Texas State color classification by a colored band completely encircling pipe, at least 8 inches in length (longer where necessary to accommodate full identification labels), painted on pipe or pipe covering in every location where identification labels are required. Pipes which are concealed or in covered pipe trenches need not be identified. Identification labels: Identification shall be accomplished by use of Brady "Quik-Labels" (mastic book) as manufactured by the ASARCO ELP 0008916 11 W. H. Brady Company, Seton Nameplate Corporation, or equal (stenciling is acceptable). Straight lines of pipe shall be i identified at intervals of 20 feet and at least oncefin each room. Piping shall also be identified at a point approximately 'two feet from all turns, valves and upstream side of distribu tional fittings or branches. The lettered label,,besides identifying the material, shall indicate unusual qualities of the pipe contents, i.e., hot, cold, pressure in pounds/square inch. On service piping, either liquid or air, apply black % arrows of same height and with same background color as adjacent to identification labels to indicate direction of flow. Application; Labels shall be applied to the pipe so that the lettering is in the most legible position. Lettering size shall be in accordance with standards specified in USASI A 13; however, the nearest manufacturer shall be acceptable. Pipes to be marked shall first be wiped clean of dirt, dust, grease and moisture. Apply label over color band, using pressure, so that it lies smooth and flat. Apply a brush coat of clear lacquer, after label has been applied to pipe, making sure edges of label are well covered. Insulation of Equipment The deaerator shall be insulated with 1-1/2" thick Johns-Manville Thermobestos block insulation and covered with 0.010 thick 304 stainless steel sheet all applied in accordance with manufacturer's instructions. Alternate insulation if of equal or better insula ting value may be used if approved by Owner's representative. ASARCO ELP 0008917 12 Code WFH WFL WCH CH WP WM WT WCI WCL CH WCO SH SL AH AP AI GH GI GL A Piping Schedule Service Pressure psig Temperature F Water Feedwater, high press. 760 230 Feedwater, low press. Condensate 400# 25 or less 400 230 450 Chemical Treatment, high pressure 760 amb. Plant Service 90 amb. Softener Makeup Water 90 amb. Cooling Tower 60 amb. Condensate 150# 150 370 Condensate low press. 50 200 Chemical Treatment, low pressure 90 amb. Oily Condensate 25 or less 110 Steam Steam 400# 425 680 Steam 5# 5 240 Air Soot Blower Air 500 amb. Plant Compressed Air 90 amb. Instrument Air 90 amb. Natural Gas High Pressure 100 amb. Intermediate Pressure 35 amb. Low Pressure 5# & less Acid 5 amb. Concentrated Acid 90 amb. v Material {Specification b M .N M M N N N N N N N M N M N N N N N N ASARCO ELP 0008918 13 Piping Material Specifications Specification M Nominal Rating i r 800 psig @ 300 F. 600 psig @ 700 F. Pipe Black, ASTM A-106 Grade B seamless, plain ends 2" and larger - schedule 40 except feedwater- lines schedule 80 feedwater lines 1-1/2" and smaller - schedule 80 all lines Joints 2" and larger - butt weld 1-1/2" and smaller - socket weld weld neck flanges next to flanged equipment Flanges 600# pressure class, USASI B 16.5, ASTM A105 Grade II 1/4" raised face, weld neck Bolting Stud bolts USASI B 16.5, ASTM A193 and hex nuts ASTM A194 Gaskets Spiral wound 304 stainless steel and asbestos for raised face flanges, Flexitallic Style CG. Fittings 2" and larger, schedule 40 and 80 to match pipe, butt welding, USASI B 16.9, ASTM A234 WPB. 1-1/2" and smaller, 3000# socket weld USASI B 16.11, ASTM A105, Grade II ASARCO ELP 0008919 14 Valves (Specification M - high pressure)_ mfgr. listed or approved equal Dwg. Code V-36 Type Check Description r 600#, steel,buttfweld, piston lift, .> Edwards 690 Y V-37 Check 600#, steel, flanged, piston lift. Edwards 690 ':f V-42 Gate 2" and smaller, 800#, steel, flanged, Crane 3611XU V-43 Gate 2" and smaller, 600#, steel, flanged. Crane 3615XU V-46 Gate 2-1/2" and larger, 600#, steel, butt weld 8" and above integral bypass, Crane 76-1/2XU V-47 Gate 2-1/2 and larger, 600#, steel, flanged, 8" and above integral bypass, Crane 76XU V-51 Globe 2" and smaller, 800#, steel, socketweld Crane 3652XW V-56 Globe 2-1/2" and larger, 600#, steel, buttweld, 8" and larger integral bypass, Edwards 616Y,618Y V-57 Globe 2-1/2" and larger, 600#, steel, flanged, 8" and larger integral bypass, Edwards 616, 618 V-58 Globe 2" and smaller, 600#, steel, flanged, Crane 3656XW V-59 Globe 2-1/2" and larger, 600#, steel, buttweld. angle stop check, Edwards 605 Y Specification N Nominal Rating 150 psi @ 400 F. and lower ASARCO ELP 0008920 15. Pi^e 14" and larger, schedule 10, black ASTM A53jr seamless, E Grade A or B l 8" through 12", schedule 20, black ASTM A53 seamless, Grade A or B 6" and smaller, schedule 40, black ASTM A53 seamless. Grade A or B Pipe for underground service shall be coated and-wrapped in accordance with previous specifications. Joints 2" and larger - butt weld 1-1/2" and smaller - socket weld weld neck or slip on flanges next to flanged equipment Flanges 150# pressure class, USASI B16.9, ASTM A234 WPB, weld neck 1/16" raised face, except that flat faced flanges shall be used against flat faced valves or equipment. Bolting Stud bolts USASI B16.5, ASTM A193 and hex nuts ASTM A194 Gaskets Spiral wound 304 stainless steel and asbestos, Flexitallic Style CG Fittings 2" and larger, schedule 40, butt weld ANSI B16.9, ASTM A234 WPB 1-1/2" and smaller, 2000#, malleable iron screwed fittings, USASI B16.3 ASARCO ELP 0008921 16 Valves (Specification N - intermediate and low pressure) Dwg. Code Mfgr. listed or approved equal Type Description * t l V-ll Ball 150# nodular iron, flanged, viton seats and seals. Crane Hiflex No. 81102 V-35 Check 2-1/2" and larger, 150#, steel, flanged, swing. Crane 147X V-40 Gate 1-1/2" and smaller, 800#, steel, screwed. Crane 3607XU V-42 Gate 2" and smaller, 800#, steel, socket weld. Crane 3611XU V-45 Gate 2" and larger, 125#, iron, flanged. Crane 465-1/2 V-50 Globe 1-1/2" and smaller, 800#, steel, screwed Crane 3644 XU V-51 Globe 2" and smaller, 800#, steel, socket weld. Crane 3652 XW V-55 Globe 2" and larger, 150#, steel, flanged. Crane 143 XR V-60 Plug 1-1/2" and smaller, 200#, semisteel, screwed lubricated, Nordstrom 114 V-61 Plug 2" and larger, 200#, semisteel, flanged lubricated, Nordstrom 115 Related Specifications Construction in this section involving the following is covered by the general specifications: Concrete Structural Steel Painting Electrical ASARCO ELP 0008922 CONSTRUCTION SPECIFICATIONS FOR STEAM AUXILIARY EQUIPMENT AND PIPING FOR CONVERTER GAS ACID PLANT EL PASO, TEXAS Prepared by Central Engineering Department Design Section ' Date November 17, 1971 ASARCO ELP 0008923 CONVERTER GAS ACID PLANT CONSTRUCTION SPECIFICATIONS Section on Steam Auxiliary Equipment and Piping Scope This section covers the installation of the following: 1. Steam auxiliary equipment. 2. All piping except in the Acid Plant proper. 3. Site clearance required for installing the above. Electrical and instrumentation work related to the above equipment will be covered under separate speci fications . Drawings The following drawings delineating the construction shall be a part of these specifications. EP-17785 Power House-Boiler & Compressor Room-Arrgt. EP-17787 Site Clearance EP-17789 General Arrgt. Deaerator Installation EP-17790 Pipe Rack Plan-Area A EP-17791 Pipe Rack Sections-Area A EP-17792 Oily Condensate Filters-Area B-Plans EP-17793 Oily Condensate Filters-Area B-Sections EP-17794 Deaerator Plan Above Grade-Area C EP-17795 Deaerator Plan Above Elev. 3792'-4 -Area C EP-17796 Deaerator Sections-Area C EP-17797 Air Compressor Plan Above Elev. 3792'-4 -Area D EP-17798 Dump Condenser-Plan Above Elev. 3773'-0 -Area E EP-17799 Power House-Schematic-Modifications ASARCO ELP 0008924 2. EP-17802 Dump Condenser Plan Above Elev. 3798' 7-1/4 -Area E EP-17803 EP-17804 EP-17811 Dump Condenser Piping-Area E-Section A Dump Condenser Piping-Area E-Sections| B & C f- Steam Drums-Plan-Area P EP-17812 Steam Drums-Section-Area F EP-17813 Converter Hood Piping-Area F EP-17814 Boiler Plans-Above 3773'-0 EP-17815 Boiler Sections-Area G EP-17816 Boiler Sections-Area G EP-17817 Boiler Sections-Area G EP-17818 Spray Chamber-Sections-Area H EP-17819 Pipe Support Details EP-17820 Pipe Support Details EP-17821 Key Plan and General Notes *. EP-17822 Air Compressor Plan Above Elev. 3773'-6 - Area D EP-17823 Air Compressor Sections-Area D EP-17824 Spray Chamber Piping Plans-Area H EP-17882 Converter Hood Piping Details-Area F EP-17883 Spray Chamber Air Piping & Misc. Details EP-17884 Spray Chamber Water Spray & Piping Arrgt. EP-17885 Spray Chamber-Acid Spray Piping EP-17886 Spray Chamber-Spray Piping & Controls-Schematic EP-17944 Boiler Plan Above Elev. 3803'-0 EP-17945 Steam Trap Details-Sheet #1 .. EP-17946 Tagged Item List & Steam Trap Details-Sheet #2 Manufacturer drawings of equipment furnished by Asarco. Drawings of existing installations pertinent to the work. ASARCO ELP 0008925 3. Work Conditions The Contractor shall do the work herein described furnishing all labor, supervision, tools, equipment and personnel f- facilities. The Contractor shall furnish all materials except ^s hereinafter described. The Contractor shall remove all demolished materials, equip ment and debris to disposal areas designed by the Plant Engineer. Equipment Furnished by Asarco Asarco will furnish the following equipment as specified in the listed Asarco requisitions. Air Compressor Req. No. CE-71-EP-3 Dump Condenser Req. No. CE-71-EP-4 Feedwater Pumps Req. No. CE-71-EP-5 Deaerator Req. No. CE-71-EP-6 Valves, Hoses & Nozzles for Spray Chamber Req. No. CE-71-EP-9 Orifice Flanges Req. No. CE-71-EP-22 Condensate Storage P\imps Req. No. CE-71-EP-23 Boiler Check Valves Spray Chamber Pumps Req. No. CE-71-EP-24 On.hand at Plant. Motors and Motor Starters Requisitions pending. Exceptions and Changes All exceptions or changes in these specifications or drawings shall be approved by the Asarco Project Engineer, and a written record maintained of all such exceptions and changes for sub mission to Asarco on completion of the project. ASARCO ELP 0008926 4. Site Clearance The Contractor shall clear the site as shown on the ^drawings for the installation of equipment and piping. This [will include the removal of abandoned equipment and piping, the relocation ""and repiping of existing equipment, and the relocation of piping. Equipment The Contractor shall install all equipment shown on the drawings furnishing all except as listed above, and shall furnish and in stall all supports, structures and foundations required for the satisfactory installation and operation of the equipment. Manufacturer's installation instructions shall be followed in detail. Piping The Contractor shall furnish all material and equipment, including valves, hangers, supports and insulation; and shall fabricate and install all piping, fittings, appurtenances and devices necessary for complete piping system ready for operation. APPLICABLE PUBLICATIONS All piping shall conform to local codes if they are governing, and to the NBFU fire prevention code, as it applies, and Factory Mutual Engineering Corporation Standards. All welding shall conform to the requirements of the latest editions of the "American Standard Code for Pressure Piping" ANSI B 31.1a. Backup rings need not be used. All material furnished and procedures followed in the fabrication and erection of the pipe, valves and associated equipment shall ASARCO ELP 0008927 5 conform to the latest edition of "American Standard Code for Pressure Piping" ANSI B 31.1 and B 31.1a. MATERIALS AND WORKMANSHIP I General: Materials of construction, valving and specialties shall be as hereinafter described. Piping Layout: Major piping shall be installed as shown on the drawings. Minor piping not shown on layout drawings shall be laid out in an orderly manner, grouping lines whenever- possible and shall follow the diagrammatic layout shown on the drawings. Relocation in the field may be done only with the written consent of the Engineer. The installation shall be neat in appearance, and adequately supported. Every effort shall be made to locate piping and equipment which must be regularly serviced, inspected or tested so that this work may be done as i easily as feasible. Lines shall slope in the direction of flow, a minimum of 1/8 inch per foot whenever possible, or as shown on the drawings. Pump piping arrangements shall be in accordance with the standard details shown on the drawings. Piping running through roofs, floors and walls shall pass through sleeves as follows: Floor: Sleeves shall be of standard weight pipe, anchored in floor, flush at bottom and projecting one inch above finished floor, sized to allow 1/2 inch minimum clearance from pipe and insulation, if required. Roof: Sleeves are to be made of galvanized sheet iron fastened to roof, and flashed with galvanized sheet metal. ASARCO ELP 0008928 6. Walls: Sleeves shall be of standard weight pipe, anchored in the wall and flush bn each side of the wall. Sleeve shall provide 1/2 inch minimum clearance frdm pipe b and insulation if required. Sleeves in exterior walls shall be filled with oakum and caulked after pipe is placed in sleeve. Vertical pipelines, passing through concrete, shall be pro vided with adequate protection to prevent corrosion at point of contact of pipe with concrete. Headroom clearance of 7 ft. 0 in. shall generally be provided below all piping, insulation and appurtenances. Supports, hangers, guides and anchors: The selection of support points shall be made to utilize existing structural steel where feasible. The Contractor shall furnish and erect all hangers, brackets, rods, clips, clamps, plates, channels and other parts required for a complete installation as well as all necessary miscellaneous iron which .may be required to transfer hanger reactions to building steel. All rigid hangers shall be fitted with means of vertical adjustments and suitable locking means shall be provided. All tie rods shall be fitted with adjustment and locknuts. All welded hangers, supports, guide or other attachments shall be of material similar -to the pipe, and shall be subject to the same welding procedure as the pipe. Welded attachments to structural steel shall be such as to allow welding along the flange. Welding across the flange will not be allowed. Precautions shall be taken in piping installation to prevent stresses in piping and overstressing of flange ASARCO ELP 0008929 7. bolting at valves and equipment. Cold springing shall be used in pipe fabrication as shown on the drawings. j. ES' Underground Piping: All pipe and fittings shall be carefully handled to avoid damage and shall be inspected for defects before being lowered into the trench. Special care shall be given to handling coated and/or lined pipe to avoid damage.' Any damage to pipe, coating, or lining shall be repaired to the satisfaction of the Engineer before installation. Trenching and Backfilling; The pipe trench shall be excavated along the alignment shown on the plans. Trenches shall be kept to a minimum workable width with trench walls vertical from the bottom of the trench to the top of the pipe. Suitable shoring timbering or sheeting shall be provided where necessary to support the sides of the trench prior to and during installation of the pipe. All shoring, timbering and sheeting shall be removed before backfilling. The open ends of the pipe shall be closed at the end of each day's work, and shall not be opened until work is resumed. After the pipe is laid on suitable fill in the trench, the line shall be backfilled, leaving only the field joints exposed so that the pipe will be protected until tested and accepted by.the Engineer. In backfilling the trench around the lines, special care must be taken so as not to injure coatings or displace the pipe and to give it a solid bearing throughout its entire length. The remainder of the backfill above the pipe shall be sufficiently packed to prevent serious settlement. Open trenches across roadways or other areas to be paved shall be backfilled and compacted to a density at least equal to that of the surrounding earth. Sleeves made of steel ASARCO ELP 0008930 8. pipe shall be used for lines 12 inches and smaller crossing under truck roads and areas where concentrated loads may occur. In all cases, the sleeves shall be two nominal pipe rizes larger than the protected line except that minimum cfearance between pipe and sleeve shall be 1-1/2 inches. CLEANING AND TESTING Testing and field inspection shall conform to USASI B 31.1 1955 and B 31.1a - 1965. All lines shall be thoroughly cleaned while disconnected from all equipment. All piping, except low pressure air<, gas and vent lines, shall be tested at 1-1/2 times working pressure of line service. Low pressure air and gas lines shall be tested at 50 psi air and soapy water test. Underground Pipe Covering Underground pipe shall have a protective covering except as hereinafter specified, shall be mechanically applied in a factory or field plant especially equipped for the purpose. Specials and fittings that cannot be coated and wrapped mechani cally shall have the protective coating applied by hand, prefer ably at the plant that applies the covering to the pipe. Joints shall be coated and wrapped by hand. Hand-coating and wrapping shall be done in a manner and with materials that will produce a covering equal in effectiveness to that of the mechanically applied covering. The coating work shall be thoroughly inspected, and any flaws or holidays found shall be repaired by the Con tractor at no extra cost. The pipe covering shall consist of one of the following: Coal-tar Coating and Wrapping: A coat of coal-tar primer, a coat of coal-tar enamel, a wrapper of coal-tar-saturated asbestos felt. ASARCO ELP 0008931 9. a second coat of coal-tar enamel, a second wrapper of coal-tarsaturated asbestos felt, where indicated, and a wrapper of kraft I paper or a coat of water-resistant whitewash, applied^ in the Jorder named and conforming to the requirements of AWWA Standard C203 in all respects as to materials, thickness, methods of application, tests, and handling, except that interior lining will not be required. Joints and fittings shall be coated and wrapped either in conformity with AWWA Standard C203 or with the materials specified in Federal Specification HH-T-30, applied in accordance with the manufacturer's recommendation. Alternate No. 1: Asphalt Coating and Wrapping; A coat of asphalt primer, a coat of hot asphalt enamel, an asphalt-saturated-felt or asphaltsaturated-glass wrapper completely bonded to the enamel applied in the order named and conforming to the requirements of the Asphalt Institute Specification II--1 in all respects as to materialsthickness, methods of application, tests and handling. Alternate No. 2: "Extruded polyethylene sheath conforming to Federal Specification L-C-530 and of thicknesses not less than 54 mils. Fittings and joints shall be covered in the manner and with the materials recommended by the applier of the sheath. Pipe Insulation All pipes carrying liquids or gases in excess of 150 F. shall be insulated with a metal reinforced fiberglass blanket, JohnsManville Thermobestos or equal covering all pipes, fittings and valves except as noted on drawings. Insulation shall be applied ASARCO ELP 0008932 10. in accordance with manufacturer's instructions. The insula*tion shall have a protective covering of 0.010" thickness stain less steel #304 sheet. Alternate insulation of equa&. or better insulating value may be used if approved by Owner's representative. "Insulation thickness shall be as follows: 400# steam lines 2-1/2" 400" condensate lines 2" 150" condensate lines 1-1/2" 5# steam lines (6" dia. and larger)1-1/2" (5" dia. and smaller) 1" low pressure condensate lines 1" feed water lines (5" and larger) 1-1/2" (4" and smaller) 1" Pipe Painting and Coding Interior pipe shall not be painted. Exterior non-insulated pipe exposed to the weather shall be given a primer and finish coat in accordance with the general specifications for painting ex terior metal surfaces. Content of piping systems shall be identified according to the Texas State color classification by a colored band completely encircling pipe, at least 8 inches in length (longer where necessary to accommodate full identification labels), painted on pipe or pipe covering in every location where identification labels are required. Pipes which are concealed or- in covered pipe trenches need not . be identified. Identification labels: Identification shall be accomplished by use of Brady "Quik-Labels" (mastic book) as manufactured by the ASARCO ELP 0008933 11. W. H. Brady Company, Seton Nameplate Corporation, or equal (stenciling is acceptable). Straight lines of pipe shall be identified at intervals of 20 feet and at least oncerin each b room. Piping shall also be identified at a point approximately two feet from all turns, valves and upstream side of distribu tional fittings or branches. The lettered label,..besides identifying the material, shall indicate unusual qualities of the pipe contents, i.e., hot, cold, pressure in pounds/square inch. On service piping, either liquid or air, apply black % arrows of same height and with same background color as adjacent to identification labels to indicate direction of flow. Application: Labels shall be applied to the pipe so that the lettering is in the most legible position. Lettering size shall be in accordance with standards specified in USASI A 13; however, the nearest manufacturer shall be acceptable. Pipes to be marked shall first be wiped clean of dirt, dust, grease and moisture. Apply label over color band, using pressure, so that it lies smooth and flat. Apply a brush coat of clear lacquer, after label has been applied to pipe, making sure edges of label are well covered. Insulation of Equipment The deaerator shall be insulated with 1-1/2" thiak Johns-Manville Thermobestos block insulation and covered with 0.010 thick 304 stainless steel sheet all applied in accordance with manufacturer's instructions. Alternate insulation if of equal or better insula ting value may be used if approved by Owner's representative. ASARCO ELP 0008934 12 Code WFH WFL WCH CH WP WM WT WCI WCL CH WCO SH SL AH AP AI GH GI GL A Service Piping Schedule Pressure psig Temperature F Water Feedwater, high press. 760 230 Feedwater, low press. 25 or less 230 Condensate 400# 400 450 Chemical Treatment, high pressure 760 amb. Plant Service 90 amb. Softener Makeup Water 90 amb. Cooling Tower 60 amb. Condensate 150# 150 370 Condensate low press. 50 200 Chemical Treatment, low pressure 90 amb. Oily Condensate - 25 or less 110 Steam Steam 400# 425 680 Steam 5# 5 240 Air Soot Blower Air 500 amb. Plant Compressed Air 90 amb. Instrument Air 90 amb. Natural Gas High Pressure 100 amb. Intermediate Pressure 35 amb. Low Pressure 5# & less Acid 5 amb. Concentrated Acid 90 amb. * Material [specification r b M N ":f M M N N N N N N N M N M N N N N N N ASARCO ELP 0008935 13 Piping Material Specifications Specification M , Nominal Rating 800 psig @ 300 F. 600 psig @ 700 F. Pipe Black, ASTM A-106 Grade B seamless, plain ends 2" and larger - schedule 40 except feedwater.lines schedule 80 feedwater lines 1-1/2" and smaller - schedule 80 all lines Joints 2" and larger - butt weld 1-1/2" and smaller - socket weld weld neck flanges next to flanged equipment Flanges 600# pressure class, USASI B 16.5, ASTM A105 Grade II 1/4" raised face, weld neck Bolting Stud bolts USASI B 16.5, ASTM A193 and hex nuts ASTM A194 Gaskets Spiral wound 304 stainless steel and asbestos for raised face flanges, Flexitallic Style CG. Fittings 2" and larger, schedule 40 and 80 to match pipe, butt welding, USASI B 16.9, ASTM A234 WPB. 1-1/2" and smaller, 3000# socket weld USASI B 16.11, ASTM A105, Grade II ASARCO ELP 0008936 14. * Valves (Specification M - high pressure)^ mfgr. listed or approved equal-* Dwg. Code V-36 Type Check Description i r 600$, steel,bixttJWeld, piston lift, , Edwards 690 Y t V-37 Check 600#, steel, flanged, piston lift, Edwards 690 V-42 Gate 2" and smaller, 800#, steel, flanged, Crane 3611XU V-43 Gate 2" and smaller, 600#, steel, flanged. Crane 3615XU V-46 Gate 2-1/2" and larger, 600#, steel, butt weld 8" and above integral bypass. Crane 76-1/2XU V-47 Gate 2-1/2 and larger, 600#, steel, flanged, 8" and above integral bypass, Crane 76XU V-51 Globe 2" and smaller, 800#, steel, socketweld Crane 3652XW V-56 Globe 2-1/2" and larger, 600#, steel, buttweld, 8" and larger integral bypass, Edwards 616Y,618Y V-57 Globe 2-1/2" and larger, 600#, steel, flanged, 8" and larger integral bypass, Edwards 616, 618 V-58 Globe 2" and smaller, 600#, steel, flanged. Crane 3656XW V-59 Globe 2-1/2" and larger, 600#, steel, buttweld, angle stop check, Edwards 605 Y Specification N Nominal Rating 150 psi @ 400 F. and lower ASARCO ELP 0008937 15. Pie 14" and larger, schedule 10, black ASTM A53_ seamless, | Grade A or B r- 8" through 12", schedule 20, black ASTM A53 seamless, Grade A or B 6" and smaller, schedule 40, black ASTM A53 seamless. Grade A or B Pipe for underground service shall be coated and wrapped in accordance with previous specifications. Joints 2" and larger - butt weld 1-1/2" and smaller - socket weld weld neck or slip on flanges next to flanged equipment Flanges 150# pressure class, USASI B16.9, ASTM A234 WPB, weld neck 1/16" raised face, except that flat faced flanges shall be used against flat faced valves or equipment. Bolting Stud bolts USASI B16.5, ASTM A193 and hex nuts ASTM A194 Gaskets Spiral wound 304 stainless steel and asbestos, Flexitallic Style CG Fittings 2" and larger, schedule 40, butt weld ANSI B16.9,~ASTM A234 WPI 1-1/2" and smaller, 2000#, malleable iron screwed fittings, USASI B16.3 s ASARCO ELP 0008938 16 Valves (Specification N - intermediate and low pressure) Mfgr. listed or approved equal Dwg. Code V-ll Type Ball Description ' h 150# nodular iron, flanged, viton sea.ts and seals. Crane Hiflex No. 81102 V-35 Check 2-1/2" and larger, 150#, steel, flanged, swing. Crane 147X V-40 Gate 1-1/2" and smaller, 800#, steel, screwed. Crane 3607XU V-42 Gate 2" and smaller, 800#, steel, socket weld. Crane 3611XU V-45 Gate 2" and larger, 125#, iron, flanged. Crane 465-1/2 V-50 Globe 1-1/2" and smaller, 800#, steel, screwed Crane 3644 XU V-51 Globe 2" and smaller, 800#, steel, socket weld. Crane 3652 XW V-55 Globe 2" and larger, 150#, steel, flanged. Crane 143 XR V-60 Plug 1-1/2" and smaller, 200#, semisteel, screwed lubricated, Nordstrom 114 V-61 Plug 2" and larger, 200#, semisteel, flanged lubricated, Nordstrom 115 Related Specifications .- Construction in this section involving the following is covered by the general specifications: Concrete Structural Steel Painting Electrical ASARCO ELP 0008939 PACE INDUSTRIES 1081 SOUTH SECOND WEST P. O. BOX 2605 SALT LAKE CITY. UTAt|84IIO (801) 521-3740 *4 * *' t * January 31, 1972 American Smelting & Refining Co. Salt LakeCity, Utah Attention: Mr. Bob Jones Engineering Dept. Rej El Paso, Texas Plant Gentlemen: In line with previous discussions and with reference to your sketch submitted, we are pleased to offer for your consideration and evaluation the following bill of material for the water column and related items: 1 - RELIANCE W-350-X No-Alarm Column, per dwg. AB-13871 1 - RELIANCE #1+03-RS Gage Valves, per dwg. B-1+882-? 1 - RELIANCE C-99 Gage Insert, per dwg. B-l+366-8 1 - RELIANCE, set of 3 sGC-311 Try Cocks, per dwg. A-7I+8O 1 - RELIANCE E-300 Wall Mount Eye-Hye complete with Unitemp reservoir, 18" wall mount remote gage with shutoff valves and Vizzene fluid, per dwg. D-S>082-2 Attached are 3 copies each of above- drawings which have been CERTIFIED for your use. We request that when this equipment is ordered that one copy of each drawings be sent to us with the order and these should be marked as "approved" or "approved with changes as noted" as applicable. Tours very truly, PACE''INDUSTRIES ' ELA:A Ends. ccj Clark-Reliance Corp. M. C. Parker 'TBrnest L. Allred /'' / -' -f / l... iVr %. <' -jA r. - POWER PLANT A N O N D U S T R ^EQUIPMENT ASARCO ELP 0008940 BILL OF MATERIAL ASARCO ELP 0008941 t l t tWMfitit*teJs/ t scMiweo m m THtC to A t. o t ASARCO ELP 000894-2 asarco ELP 0008943 BILL OF MATERIAL- PER SET | PART NO. < CB < e o ** m w s<5 z i J1 y* (0 6 S ft k ft a cr X aTt MJ c & e w r s in a (SI ! s a a ft o << aa * o # k a m j i < A CD < -i 5 K LJ % Z CJ CJ aW ii ft 2 an E e a E d UI 5 LI a a fc 9 a aa mX f J ! K 1A UI UI S; a vC E d Lb-i a -J M Ut & fti 1 C a .E Vr o C & so (A to O < s K * s 08 E ft n iS ** hJ 55 a. a. a x Ui ? V o o m w3 Z o z o 2 ft 9 z o r 2 0 <1 a z < j (9 0 z X u < 01 tu 0) (A S z w hi 5 _i u> ft 01 ft (A E |U X a < * o z 5 o 2 X UI h a M z 2 i SK X d d IU N =! V * i * X* da X (il X 4A < d 1* * 1*0* UI & * CA u M t a ot U A C tel CA * Z UI Li 0 i K C oi E aiu * O w > a 1 X f<-9 Z LI a ui u 0. CA St o 0 X CA 1 a cri XC-J9 z x o < 0. (A (A < X Li ft <A Li 5 < > oz oz 2 CA CA < -J z St o fEt s Li ft CA *uUati osft CA EU ffLtti 9 (A a o L. a CSI E a>Ui O E < z < Li .1 9 O X o a* X a a ?s a i LI Li E E o *9K to ft < ft 9 z CXt <X X o Li X tt a E Li X a I X a Li o o -1 o X fot c o X fEt X 5 Ui <X X9 X a a a4 E a o Li E ft U X a E LftI ft 9 >O aO LI 5 < > 1 o - CJ N tJ M CJ 61 CJ 40 fti CJ CJ ft o - CJ LI to esj - 10 ft s X a O CJ 1 e 10 i n O I or no a. 0 a1 on E a CA e cr tt 10 O oo A a o CO E o0 CO E CoO o a* m <a * r a ca r (9 (A r o O <9 ffi CD O C9 S C9 m a vr < SKa aE (C oo v r 9 C9 CD a _ZLi fy a < U) <x> ft CD A o CJ a a ft s 1 YWH3A0 ,,Z SU31N30 NIVHD .9 71 M "mjco CJ *0i4 hxz *M3ft SB J o> ASARCO ELP 000894-4- : :' '^tev, .??'' - : !:. <; - ' v*: : .. .c,,' c ' y-:'l'>- -:c '='-rj `FnSiili aw.-;r '..vVi-:\;>^r - x M li Ial Mrt<flisnu,);>;,, o; f,, J?U, JU...U L , \vV'' \\ r-i..-. ^NJli. l! -l /inorj.35A!.u;i.>;p.- . -;IE\ \\ >V7/ H ' w ,: r-n-j.- ' * \vL _^y L . >j-xj * ? "*''ST. "H'iJ | */v. j ASARCO ELP 0008945 SOUTHWESTERN INDUSTRIAL CONTRACTORS AND RIGGERS, INC. Formerly: CONSTRUCTION DIVI5ION, SOUTHWESTERN TRANSFER CO., INC. 1730 Barrett Ave. P. O. Box 1611 El Paso, Texas 79948 (915) 532-3491 1330 South 26th Place P. O. Box 20865 Phoenix, Arizona 8S036 (602) 273-1371 527 Wyoming Blvd., S.E. P. O. Box 8057 Albuquerque, New Mexico 87108 (505) 265-7691 LETTER OF TRANSMITTAL jq. American Smelting and Refining Co. ' P.O. Box 1111 El Faso, Texas 79999 DATE: January 21,:'1972 ' RE Pneumatic Cylinder & Accessorie ATTENTION: ^r* ^English Project Engineer GENTLEMEN: ---------------------- SUBMITTAL NO.: V,'E ARE SENDING YOU 0ATTACHED [jUNDER SEPARATE COVER VIA______ THE FOLLOWING: }SHOP DRAWINGS QSAMPLES QPLANS DESCRIPTIVE LITERATURE COPY OF LETTER DATED __ QuotesJ 4-- -- -- ----- -- ------ ---------------------------- ------------------------------------- r--7--;----------- H'V '______________________________ COPIES DATE NO. DESCRIPTION ^ 1 i i * ! Quote - Tri-State Industrial Supply - Geo. S. Thomoson 4v < u ! __________ i________ THESE ARE TRANSMITTED FOR REASONS NOTED BELOW: ]REVJEW AND APPROVAL APPROVED AS SUBMITTED APPROVED AS NOTED disapproved Qas REQUESTED QfOR YOUR USE resubmit___COPIES FOR APPROVAL RETURN CORRECTED PRINTS REMARKS: ) V fi I Adi ti i nr* ... _ ASARCO ELP 0008946 1 SOUTHWESTERN INDUSTRIAL CONTRACTORS AND RIGGERS, INC. fyi CONSTRUCTION DIVISION, SOUTHWBTRRN TRANSFER CO., INC. irSOIoMttAv*. F. O.lnlill ' El Pato, Taxa*7V948 401 Cl 1330 SwAk 26th Rlu r. O. lox 20165 Phoanix, Arizona 85036 IAA4I * 491 122 Wyoming Rlvd., S.E. F. O. I.< R0I7 Albuquarque, New Mexico.87108 REQUEST FOR QUOTATION TO: Tri-State Industrial Supply 5526 E. Paisano El Paso, Texas Attn: Mr. Miller NOT AN ORDER DATE: January 7. 1Q7? CUSTOMER: AS^CCi _ JOB TITLE:__________________ Converter Gas Acid PIant To receive consideration: 3 copies of your bid must be in our office by January .V, \^2 FOR SHIPMENT TO: American Smelting and Refining Co. El Paso, Texas SHIPMENT REQUIRED BY: 1-lease submit firm Quotation on Items listed below subject to terms listed herein: Cv*u/u\ 2x a L 3 i2 3 i DESCRIPTION Quotation From: Tri-State SEE ATTACHED LIST: 1* ft It if n w w tt Each 113.70 661.62 661.62 Less Plus 5$ Tax STATE & City F.O.B. Chicago j Net 30 Days; Payment Terr.^. 1 8 Weeks Shipment For 450*Deg. F. Kax. Total 356.10 1323.24 1984.36 I366E723 166.42 '7297.73 ! 164.39 ; 3462.67 i Quotation must indicate unit price, extension, total, applicable taxes, terms of payment, FOB point, shipping point(s) and best delivery. Quotation must be in accordance with plans and specifications submitted. Deviation or substitutions must be clearly stated in your Quotation. SOUTHWEST^N^lNDUSTRIMj.CONTRACTORS & RIGGERS, INC. //{/S H. E. Wickes Project Manager r i CVJ f<\ ASARCO ELP 0008947 MSMipjpaf- ii, ^ ''', ITEM _mi_ gi*5!Sgy .'in T " !NpiW v> ` rM&tSEBT FOB QUOTATION ^^JStMLSSm___ , ;\\ ./,i t': 2;ai%i.. ' '*' .yv* wmmw, "ifB* 1 3 Rax Hanna 3*^** Bore, 18" Stroke, Head Trunion MU, 1.00" Rod. Dia., fteall Bale thread .73-16 v/rod clevis #V2, complete v/pin 2 2 Rex-**anna Pnuamatic cylinder, 8" bore, 25^" stroke w/5" rod extension. Cushioned both ends, cap fixed clevis, Mounted MFI, Rod Dia. Code J (2" dia.), Rod end snail male 1^ x 12" thread, suitable for 500 deg. F Ambient temperature, supplied v/protective boot. ifro *f. tf\ ^ 2 Rex-Hanna Mounting Bracket #|3 2 Rex-Hanna Rod Rye Item 05 ":f 2 Rex-Hanna Pin 1.751" dia. x 5.88 lg. Item #P5 2 Rex-Hanna Pin 1.001" dia. x 3.56 lg. Item #P3 3 3 Rex-Hanna Pnuem&tie cylinder, 8" bore, 25i" str^ce v/5" rod extension, cushioned both ends, cap fixed clevis-MTS MPI, rod dia. code "J" (2" dia.) Rod end small male l x 12" threaded, . supply v/protective boot suitable for 500 deg. F Ambient temperature. 3 Rex-Hanna Mounting bracket item #B3 3 Rex-Hanna Rod Eye Item #Y5 3 Rex-Hanna Pin 1.751" dia. x 5.88 lg. Item #P5 3 Rex-Hanna Pin 1.001" dia. x 3.56 lg. Item #P3 ASARCO ELP 000894-8 OTHER LOfcATlCNS: ODESSA, TEXAS ALBUQUERQUE,NEW MEXICO PHOENIX. ARIZONA CHIHUAHUA. CHIH., MEXICO PROPOSAL Geo. S. Thomson Co., Inc Industrial Supplies Southwestern Ind. Contractors & Riggers, Inc. P. 0. BOX 1611 El Paso, Texas 79948 EL PASO, TEXAS 7999 3738 DURAZNO AVENUj BOX 17 PHONE -- 533-950 TELEX NO. 74-9438 nATR Jan. 13. 197? PROPOSAL NO. Q72-41 YOUR NO._______________ QUANTITY Atten: Mr. H.E. Wickes MATERIAL UNIT PRICE EXTENSION 3 Wabco Powermaster Pnewmatic Cylinder 3-1/4" Bore w/181' 99.66/1,3 298.98 stroke MTI-P.P. (Head Trunion Mount) 1" Rod, 3/4"/16 Thread J-80002 Clevis & Pin. 5 Wabco Powermaster Pnewumatic Cylinder. 8" Bore, 25-1/2" 523.43 2,617.15 Stroke. W/5" Rod Extension, Model C-MPI-PP-C. MPI Fixed Clevis Mount, Cushions Both ends. 2" Dia. Rod W/ 1-1/2" Threads W/protective boat. Cylinder furnished with Viton Seals & 1" Diaphragm. j NOTE: Viton Seals are suggested for temperature to 400 5 ! Mounting Brackets J-800033 S 5 : Rod Eye J 800013 5 j Pin J 800021 i: i; ii 17.68 Ea. j- ii 24.35 Ea. 88.40121.75 6.25 1r i: 31.25 II41^7 TERMS: Net 30 F.O.B..Lexington, KY. APPROXIMATE DATE OP SHIPMENT 4-6 Weeks ORDERS, SALES AND DELIVERIES OF THE ABOVE OR ANY OTHER MERCHANDISE ARE SUBJECT TO THE TERMS AND CONDITIONS OF SALE PRINTED ON BOTH SIDES OF THIS INSTRUMENT. MAIL PAYMENTS TO GEO. S. THOMSON CO., INC., P. O. BOX 17. EL PASO. TEXAS. IF THERE ARE ANY QUESTIONS REGARDING THIS PROPOSAL PLEASE CONTACT. GEO. S. THOMSON CO., INC. Don Cline ASARCO ELP 0008949 SOUTHWESTERN INDUSTRIAL CONTRACTORS AND RIGGERS, INC. Formerly: CONSTRUCTION DIVISION, SOUTHWESTERN TRANSFER CO., INC. 1730 Basiett Ave. P. O. Box 1611 El Paso, Texas 79948 (915) 532-3491 1330 South 26th Place P. O. Box 20865 Phoenix, Arizona 85036 (602) 273-1371 527 Wyoming Blvd., S.E. P. O. Box 8057 Albuquerque, New Mexico 87108 (505) 265-7691 January 21, 1972 American Smelting and Refining Co. P.0. Box 1111 El Paso, Texas 79999 Attn: Mr. J. W. English Project Engineer Re: Pnuematic Cylinder & Accessories Dear Sir, Enclosed are two quotes for the above, shown on Dwgs. EP-17764, 17889, 17890 for your approval to purchase. Although Rex-Hanna is approximately $380.00 more than Westinghouse from Geo. S. Thompson, we would recommend that we use Rex-Hanna because of the temperature rating and Rex-Hanna was called out on the drawings. Thanks, Project Manager HEW/jm P.S. I have been told that there will be an increase in price around the 15th of February, 1972, so to maintain this price we should get this on order before that time. ASARCO ELP 0008950 y a id l/j ASARCO ELP 0008882