TM INTER-COMPANY AND OFFICE CORRESPONDENCE G. D. Bevis Subject: Plant EPA Construction Located at: Date: S. Cirelli Leominster, MA Dtpt { Di+ttie>n Company September 14, 1978 Request approval for the following punch list items: 1. For the centrifugal pumps in the recovery building, provide city water to pump seals instead of service water. 2. Hot D.I. water system - provide S.S. flex lines to absorb hammer in solid lines. 3. Calibrate Bacharach system in recovery building (manufacturer). 4. Rppa-ir IpaVt.. Tnotall^ag1ta toi 1 ft waste water transierr-- SC/sma cc: W. Colonis R. Slocumb D. L. Young S. Cirelli Senior Process Engineer BOR 002983