Document RpK5RVzqB1eZ6d9dmgGmJzaxE
DATE: August 7, 1992
FROM: Michael Bergstrom, Project Engineer
TO:
E.M. Hawthorne R.A. Ott J.J. Niklas
SUBJECT: VARIANCE FROM SAFETY ORDER S-144. FIRE RETARDANT CLOTHING
Present Situation
The contract work on V-BD-990, Site III, was awarded, and the first two phases of work are started. The total scope of contract work includes:
- scaffolding the sphere - enclosing the sphere/scaffolding with plastic - removing the mastic coating which contains asbestos - removing the foam glass insulation - sandblasting the red lead paint primer - repainting the sphere with rollers - reinsulating the sphere
The area around the sphere is considered an FRC required area. The sphere is empty and isolated from all other process. Appropriate personnel and equipment access over the concrete firewalls is nearing completion.
The asbestos disposal dumpsters are located on the west side of the sphere, and the decontamination trailer is located on the southwest corner of the diked area.
DPMC Policy
The existing DPMC policy states the requirements for FRC use. These requirements include:
- long sleeve FRC must be worn by all personnel while in field locations, including operating unit areas, tank farms, hydrocarbon loading/unloading areas, motor control centers, laboratory areas, hydrocarbon handling areas, etc.
FRC is worn for initial opening of all process equipment, by vacuum truck operators, and in enclosed areas when flammable dust is generated.
Proposed Variances from DPMC Policy
We are requesting that the area identified in the attached drawing be temporarily classified as a non-FRC area.
We want to be able to do the remaining work without wearing FRC clothing. The remaining work includes the last 5 phases of the
DPMC-16027
LAM 000312
project list above. The insulation removal portion of the work is routinely exempted from FRC requirements throughout the Complex because we are unable to find a laundry that can handle asbestos contaminated clothing. Additionally, the insulation removal workers wear "cool suits" to reduce the added heat stress factor of working inside the plastic enclosure. The other phases of the project will also be conducted under the plastic enclosure with the same heat stress complications. Safeguarding for the Variance The sphere is empty and blinded. We will use a firewatch to patrol the north, west, and south sides of the plot. The firewatch can quickly identify any leaks/releases that can present a danger to the workers inside the plastic enclosure, and sound an evacuation alarm to the workers inside the enclosure. This variance has been discussed with the appropriate area H&S inspector, supervisor, and group leader. Please sign below giving permission to classify the worksite as a non-FRC required area.
Michael Bergstrom
APPROVALS:
tt, Superintendent,Solvents & Distribution
LAW1 000313
DPMC-160
I k ij fs**' r
(a//Li
cropa cbavix3.
c-7137*
t-7vrr
C-TOBO
c-7uz
C-7U83
C-713M
serr i or 7 ocscocr EouincxT - irrt m jjcct * cr 7 oasxxrr cannon - inr m BCETI OT 7 OCKGOCT COumOCT - Hit m scet s or 7 cxscocT eauinocT - nrc m SCOT * or 7 OCBGDCT EOUWOCT - IITC m
SCET 7 CT 7 OOCGDCT COUinCXT - SITE D
i LAM 000314
DPMC-16029
DPMC-16030
DPMC 16026.1
LAM 000311
02,c 1
JuP + P
& {* t i) * ?
* ^*
s
fV A l-1 ^ '