Document RjXJV5Emz1m5aDvY9KBLGopqz
To: H. C. Gaffney
Location: Chicago Plant
From:
R. Johnson
Location: Chicago Plant
Extension:
Subject: Reference:
MONTH REPORT FOR JANUARY
Date: 1/23/84
CPy to: J. Daly
EFFLUENT
New control valve on order. Six weeks delivery. Sample from inside due to snow taken Jan. 18th
MAINTENANCE PROBLEMS
Frozen shut Sulfuric Acid line. Line now open, but Sulfuric acid tank still needs a new valve and plug. This to be done when the tank is empty.
jZtVTAk Changed vajrtioa4 air compressor, waiting for ours to be rebuilt. .
Install new parts 712 mill.
Rebagged outside dust collector - 144 bags 10 foot long. Spares should be ordered.
Jan. 12 feed pig lead 130 pigs/ shift.
Broke three screws in building 19.
Sprinkler line broke - frozen.
JOB ORDERS
Litharge Weighting System - will be able to check the big bin this month and correct if necessary.
Waxed Stabilizer Extruder - Talked to salesman on new pump and head, Laboratory to send samples for testing.
NA 839 REV. 4-82
4-82
CYWl 1-000206
2 JOB ORDERS ( Continued)
Oil & Gas Burner For Kiln - Rechecking new updated cost of gas vs oil to see if this burner should be installed. TRF Lab Equipment - Other Brabender hooked - up. Motor Motor on the new blower was defective. Contractor is pro viding a replacement. Purchase and Install Vertical Elevator - Elevator on order. Purchase and Install Magnetic Grate - Grate on order due 2/1/84. Purchase Semi - Bulk Containers - Containers on order. Some A/P have been delivered. Purchase IBM Micro Computer - J. Daly will order extra parts. Rider 26 Project - Job order written and submitted. Work ing on additional bids for this job.
R. Johnson