JOB CRITERIA SECTION V
UNION CARBIDE CORPORATION CHEMICALS AND PLASTICS OPERATIONS DIVISION
ENGINEERING DEPARTMENT
INSPECTION - TESTING CRITERIA ETHYLENE OXIDE PLANT SEADRIFT, TEXAS REVISED MAI 1, 1967
SOUTH CHARLESTON WEST VIRGINIA
016882
JOB CRITERIA SECTION V
UNION CARBIDE CORPORATION CHEMICALS AND PLASTICS OPERATIONS DIVISION
ENGINEERING DEPARTMENT
INSPECTION - TESTING CRITERIA ETHYLENE OXIDE PLANT SEADRIFT, TEXAS
OCTOBER 30, 1964
D. L. Runyon R. K. Wilson
REVISED MAY 1, 1967 P. E. HENRY
SOOTH CHARLESTON WEST VIRGINIA
016883
INSPECTION-TESTING CRITERIA ETHYLENE OXIDE PLANT
TABLE OF CONTENTS
1.000
2.000
3.000 3.100 3.200 3.300
4.000 4.100 4.200
5.000 5.100 5.200
6.000 6.100 6.200 6.300 6.400 6.500 6.600 6.700 6.800
GENERAL
ELECTRICAL
EXPOSED PIPING Steam Piping Process Piping Systems Testing
EQUIPMENT Rotating Equipment Oxide Converters
UNDERGROUND PIPING Pressure piping Gravity Piping
DEFINITION OF JOB COMPLETION Instruments Air Compression System Centrifugal. Compressor, Item MG-109 Water Pump System, Item MG-403 Centrifugal Compressor, Item MS-407 Other Pumps and Rotating Equipment Electric Motor Operated Valves Other Portions of the Work
r U J O J OO f* fO FO (V) 8 B
SECTION V
Page 1 1
1 1
2
016884
SECTION V PAGE 1
1.000 1.100
1.200 1.300 1.1+00
GENERAL
Except as otherwise specified, the Contractor shall he responsible for developing all inspection and testing criteria and procedures, and the performance thereof, for the Work. The Contractor shall provide:
A. The sequence for hydrotesting, the volume of water required, and the rate of water usage.
B. A list of sill pipelines that must be temporarily supported for hydrotesting.
C. A list of all pipelines that are to be pneumatically tested in lieu of hydrotesting.
In order that the Owner does not violate or circumvent any of the Contractor's warranties during initial operation, the Contractor may provide stand-by observer during these periods.
The Owner and the Contractor shall mutually agree on the need for vendor's representatives.
Complete test records shall be maintained.
2.000 2.100
ELECTRICAL
All electrical materials, equipment, and installed systems shall be inspected as necessary to assure:
(a) Specified quantity and quality of materials (b) Proper identification of equipment and materials (c) Proper and undamaged electrical continuity (d) Proper installation, cleaning, connecting, grounding, anri
servicing including setting of all overloads and other relays. (e) Agreement of final installation with drawings, wiring diagrams
and governing codes or laws. (f) Proper operation
3.000 3.100
EXPOSED PIPING
Steam Piping
Steam piping shall be tested in accordance with Section 1 of the American Standard Code for Pressure Piping, ASA B 31.1-1955, with the following additions:
016885
SECTION V PAGE 2
3.000 3.100
3.200
3*300
EXPOSED PIPING - continued
Steam Piping - continued
(a) Flanges shall not he insulated until testing, repairs, and hot bolting are completed.
(b) Steam turbines shall not' be subjected to hydrostatic tests. An operating test shall be made after erection.
(c) If isolation of piping from a vessel prior to the post erection hydrostatic test is impossible or impracticable, the piping and vessel shall be tested as a unit at the vessel's design pressure.
Process Piping
Process piping shall be tested in accordance with the American Standard Code for Pressure Piping, Petroleum Refining Piping, ASA B 31.1-1962, with the following additions:
(a) Flanges shall not be insulated until testing and repairs are completed.
(b) Machinery such as pumps and compressors shall not be subjected to hydrostatic tests.
(c) The post-erection test of process piping shall be the pneumatic system test describer in Article 3*300, herein after.
System Testing
(a) Weld leaks shall be repaired under the direction of the Inspector, by chipping and rewelding and ultrasonically inspected if possible. Leaks in flanged Joints shall be repaired by dismantling the Joint and reassembling it, tightening the bolts in the correct order. Leaks in screwed Joints shall be repaired by dismantling the Joint and reassembling it.
(b) All leaks shall, be repaired. Repairs shall be retested until satisfactory results are obtained.
(c) Attempting to repair weld leaks by caulking or peening, and leaks in flanged or screwed joints by overtightening the bolts or fittings, is not permissible.
(d) Any leaks that develop when piping is first heated-up during the initial operation of the facilities shall be repaired.
000 ^.100
EQUIPMENT
Rotating Equipment
(a) Rotating equipment other than standard pumps shall be run-in on a selective basis as further specified under Article 6.000 hereinafter.
016886
SECTION V PAGE 3
4.000 4.100
4.200
EQUIPMENT-- continued
Rotating Equipment - continued
(b) Pumps with mechanical seals shall not be given hydrostatic tests. Seals shall be protected from moisture damage until startup. These items shall receive an air test.
(c) Lubrication system piping shall be cleaned to the satisfaction of the Vendor's Erector and the Operating Department.
Oxide Converters. Item MG-101 - 106 Inc, and M3-201 - 203 inc.
Tube Side of Converters
(a) Piping will be erected up to last valve, insulated, and tested in accordance vith previous criteria.
(b) Connecting piping will be trial fitted without disturbing moisture seals on converters. Converters shall remain sealed against moisture. The Owner will arrange for clean ing, testing, catalyst installation, and installation of the piping that was trial fitted.
Shell Side of Converters
(a) The Owner will erect, connect and test the piping and equipment associated with the shell-side of the converter.
(b) Moisture seals and desiccant -shall be removed to suit the completion schedule.
5.000 5.100
UNDERGROUND PIPING
Pressure Piping
All underground pressure piping materials and installed systems shall be inspected and tested as necessary to assure:
(a) Specified size, quantity, and quality"of materials. (b) Proper alignment, bedding, jointing, joint restraint, and
backfill. (c) Internally clean and/or disinfected consistent with nature
of service. (d) Electrical isolation consistent with required control of
galvanic corrosion. (e) Agreement with final underground drawings, and governing
codes or lavs.
Note: If flushing of lines is accomplished with other than clean water, the Contractor shall purge line of all silt, mud or other foreign matter prior to pressure testing.
016887
SECTION V PAGE 1+
5.000 5.200
UNDERGROUND PIPING - continued.
Gravity Piping
All underground gravity piping materials and installed systems shall be inspected and tested as necessary to assure:
(a) Specified size, quantity, and quality of materials. (b) Proper slope, alignment, bedding, jointing, and backfill. (c) Internally free from projections or foreign material. (d) Electrical Isolation consistent with required control of
galvanic corrosion. (d) Agreement vith final underground drawings, find governing
codes or lavs.
6.000
6.100 6.200 6.300
DEFINITION OF JOB COMPLETION
The Owner will provide technical and operating personnel to aid and assist in performing the following portions of the Work. The Owner's chemical operators will also be available. Any such assistance by the Owner hereunder is for the convenience of the Contractor and in no way shall relieve the Contractor of his responsibilities for the proper performance of the Work in accordance with the terms and provisions of the Contract.
Instruments
Instrument connections shall be made and shall be free of leaks, shop calibrated, checked for action and integration vith the complete instrument system vith a power-on test.
Air Compressor System
----- delete -----
Centrifugal Compressor, Item MG-109
_
This system shall be run-in to the satisfaction of the Vendor and the Ovner. Run-in is defined as operation of the steam turbine at temperature and pressure and operation of the gas compressor at essentially atmospheric pressure and recycling sufficient air to approximate design suction temperature. The process piping will allow this by disconnecting at suitable points. Hot-checks of the coupling alignment and piping stresses shall be made.
016888
SECTION V PAGE 5
6.000 6.400
6.500
6.600
6.7OO 6.800
DEFINITION OF JOB COMPLETION - continued
Water Pump System. Item MS-403
This system shall he run-in to the satisfaction of the Vendor and the Owner. Run-in is defined as operation of the steam turbine at temperature and pressure and the pump system pumping hot water from the base of MG-4o4 through the discharge system and back through the hydraulic turbine. Hot-checks of the coupling alignment and the piping stresses shall be made.
Centrifugal Compressor. Item MG-407
This system shall be run-in to the satisfaction of the Vendor and the Owner. Run-in is defined as operation of the steam turbine at temperature and pressure and operation of the gas compressor with suction piping open to the air euad throttling the discharge to the air to approximate the design, discharge temperature. Hot-checks of the coupling alignment and piping stresses shall be made.
other Pumps and Other Rotating Equipment
This equipment shall be checked for normal rotation,electrical checks, and undue piping stresses. Pump seals that fail or leak during the initial operation shall be repaired, as specified in the Agreonent, and the manufacturer will be back-charged on a material-labor basis unless such leaks are due to Owner's negligence.
Electric-Motor Operated Valves
Both the limit and torque switches shall be set to the satis faction of the supplier.
Other Portions of the Work
All other portions of the Work shall be complete as defined in the Job Criteria.