Konsanto fhom (nami a location, R> s_ yates - General Offices 001 ; Rtf[RLNCl t TO :. October 8, 1968 . CEA 2080 - Solid'Aroclor Expansion - Anniston Utility Requirements J. P. Bufe ccRw M. Kountz C. Mcllwaine J. P. Neff )-Anniston * Will you please review the present utility services at the Anniston Aroclor Plant and determine whether they are sufficient for the following additional loads which we intend to add under the above project:, Electrical 13 motors with an installed load of 130 HP h' Tower Water One heat exchanger with a load of City Water 200 GPM r.,,t.- For ejector intercondenser and after conlenser 50 GPM 90 lb. Steam For ejector For tracer and tank heating Total 450 lbs./hr. 150 lbs./hr. 600 lbs./hr. I would like to have this information by October 21. Zo&o St /3W /L,*r far OtJz * R. 'jT/Yates RCV. II.05 ' 02 35909 TOWOLDMONOQ48265