Document RJZdwn586Bng6g7ebmbnRbOpB
Frank Conner and H. D. Stein, East Works Q. R. Reeder
April 30. 1956
Enclosed is a photo-static copy of Purchase Order No. GSE 40885-C dated April 27, 1956 from Armco Steel Corporation covering the following:
''Make the necessary changes, alterations and new construction required for the elevator shaft, pit and pent house for the new elevator in the General Office on Curtis Street. The elevator will be furnished and Installed by others.
See estimate SCE 473.
The estimated cost of this works is:
ARMCO
L& M
TOTAL
$1,481.00
$32,912.00
$34,393.00
The estimated cost for the construction is $20, 558. 00 for which we are to receive a fixed fee of $1,481.00 which Is to be billed to Armco Steel Corporation at the rate of 4 1/2% of expenditures until 90% is billed; the final 10% to be billed upon completion of all work.
For accounting purposes this work will be covered under Contract No. 382 the same as other work orders with the exception that this carry the fixed fee covered above. Mr. J. H. Stalker has been instructed to send to each of you a copy of the above estimates.
QRR pjh cc: J. B. Stalker
APR 3 01956 QRR
Q. R. Reeder
McGCon 2869
ARMCO STEEL CORPORATION DATE GENERAL PURCHASING DIVISION
MIDDLETOWN, OHIO
4/27/56 jm
PURCHASE ORDER
No. gse 40685 -c
SHOW THIS NUMBER ON ALL INVOICES. PACKAGES, SHIPPING PAPERS B CORRES-
PONDENCE.
GSE-40685-C
n MCGRAW CONSTRUCTION COMPANY FIRST NATIONAL BANK BLDG. MIDDLETOWN, OHIO
n SHIP TO: ARMCO STEEL CORPORATION
ROUTED
l_
QUOTATION
QUANTITY
F.O.B.
SHIPPING POINT
_i
DATE REQUIRED
DESCRIPTION
TERNS
COMMODITY
REG
REQ. NO.
CONSTRUCTION
FINAL CHARGE
GSE-447
C-8602
MAT'L INDEX
PRICE
"MAKE THE NECESSARY CHANGES, ALTERATIONS AND NEW CONSTRUCTION REQUIRED-FOR THE ELEVATOR SHAFT, PIT AND PENT HOUSE FOR THE NEW ELEVATOR IN THE GENERAL OFFICE ON CURTIS STREET. -THE ELEVATOR WILL-BE FURNISHED AND INSTALLED BY OTHERS.--SEE ESTIMATE. NO. GE 473o THE ESTIMATED GOST OF THIS WCRKS IS ....
EXPENSE
ARMCO 1,431
L &M 32,912
TOTAL 34,393
FEE 1,481
TOTAL MCGRAW FEE TO BE PAID $1,481
GENERAL OFFICE NORTH WING ELEVATOR SHAFT
IMPORTANT
MAIL THE FOLLOWING TO: GENERAL PURCHASING DIVISION, MIDDLETOWN, OHIO
ARMCO STEEL CORPORATION MIDDLETOWN, OHIO
J. S. THOMAS
ACKNOWLEDGMENT - ACKNOWLEDGE IMMEDIATELY - SPECIFY EXACT
SHIPPING DATE
GENERAL PURCHASING DIVISION
S/N. B/L - IMMEDIATELY FOR EACH SHIPMENT
(ALSO ONE COPY TO CONSIGNEE)
INVOICE - RENDER IN DUPLICATE ON DAY OF SHIPMENT
McGCon 2870
TERMS/CONDITIONS - SUBJECT TO TERMS & CONDITIONS ON REVERSE SIDE HEREOF.
G - 5760
40685
II I
II
I
I
i
V4 . *'
Armco Steel Corporation
GENERAL ENGINEERING DEPT.
MIDDLETOWN, OHIO
DIVISION .. ."'eSHESAEJD^ICE ........ DEPT.
. .................. EST. No.. . GE-A73..
SUBJECT
tXPERSE 1TELS - IJBTALLATIDN OP
......................................... SHEET No.............*
... .ELEVATOR ^T.
.OJEPICE............. ..................................................JOB No....................................
MATE BY. . WARPJHS................. NOTED BY.................................................. DATE . . March. 14,. 1956. IB&D
1 ^ACCT
NO.
DESCRIPTION
EQUIPMENT
LABOR
MATERIAL
3180
Removal, replacements & Alterations - Detail of
Expense
Sheet Piling Remove Stairs
420 S .F. $3./.50
L .s.
.Remove Concrete
10 C .Y. $20,/
Remove Tile & Tile Partitions L.S.
'Remove Steelox Wall & Roof
L.S.
* Remove & Reaet Window,Doors L.S.
' r"- Shoring
L.S.
Brickwork ,
3 M $125./$65.
Stonework Concrete Block
34 C.F. $4./$6. 100 Ea. $.40/$.40
Hollow Tile - Partitions 600 Ea. $.50/ .40
Tile Work - Lavatory
380 S.F, $2./l.50
Floors - Concrete
560 S.F. $.50/,25
Floors - Rubber Tile
250 S.F. $.25/.80
Steel Ladder
1 Ea. I30./150.
Steel Grating
125 S.F. $3./2.
Vk
Wire Grill Sheet Metal.Work
Toilet Partitions
y Carpentry
1 Ea. $25.A5. L.S.
L.S. L.S.
Plastering
210 S.Y. $9./l.
Electrical Work
L.S.
Plumbing
l.s.
Insulation of Piping
L.S.
Insulation of Steelox
600 S.F. $.10/10
Painting
L.S.
Replace Blacktop
50 S.Y. $.20/1.80
Hoist, Incl. Erection
120 Hrs. $4.20/. 50
Compressor
160 Hrs.
Truck Crane
40 Hrs. S6./9.50
Truck
120 Hrs. $2.25/2.
Clean-up & Safety Protc* ction L.S.
1 i !
i ! I
!!
i
f. i
Bldg, Changes Including Elevator Pit
Excavation & Backfill
120 C.Y. $7./
Formwork
2000 S.F. S1./.30
Reinforcing Steel
3000 Lb. $.07/.07
Concrete
50 C.Y. S4./9.
Structural Steel
5 T. $150./300.
Steelox Penthouse
L.S.
Steel Access Door
1 Ea. $30./60.
Hollow Metal Doors
2 Ea. $40./l50.
TOTALS
I
1,260 800 200 280 300 225 400 375 136 40
! 300 760 280
63 30 1 375 25
I 50
750 ;! 1,890
900 800
200
60
345 10
504 520 240 270 250
210
200 195 204
40 240 570 140 200 150 250
15 725 125
210 600 400 100
60 255 90
60 80 380 240 100
840 2,000 . 210
200 750 800
30 80
$ 17,548
600 210 450 1,500 400 60 300
$ 9,359
McGCon 2872
I!
!
Armco Steel Corporation
GENERAL ENGINEERING DEPT.
MIDDLETOWN, OHIO
DIVISION___ GiEERAL OFFICE........... DEPT............................................................. EST. No.. . OE-473.............
SUBJECT........ vV. ,v.r.IIST&LUTJ-JlJ.Q?................................................... SHEET No............................ ^ ........ AT. GE:: HAL. CFFJC?.................................................................................. JOB No...........2................. IkTIMATE BY__FAR? f-yTHS.................... NOTED BY.................................................. DATE . . Iferch. U,. 1956.
acc' MO
DESCRIPTION
EQUIPMENT
I
ti MATERIAL
Overhead - 5% of L. & f.!.
Taxes and Insurance -
of I..
Small Tools - 3% of L,
Contingencies - 10^ Fee - /&%
TOTAL EXPENSE - $34,393
I
-5602 CAPITAL ESTIVATE Elevator by Armco TOTAL CAPITAL - $33,000
1,141 !j $ 13,639
VA6 r 'if.
8 11,: 11
li
1,431
!i $ 1,431
!
1,869
$ 00,558
!
| 11"3
Ji 8 12,3'4
!
$ 3?,000
McGCon 2873
:i